IH 10: SH 99 to SH 6, Landscape
0271-06-141 · let Nov 3, 2026 · Harris, Houston · Landscape & Scenic Enhancement
$1,151,035Low bid: YELLOWSTONE LANDSCAPE - CENTRAL, INC.-32.0% vs estimate $1,692,724
$354,642Left on the table30.8% gap to the second bid
5BiddersSpread 90% low to high
62Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $1,151,035 | -32.0% | $354,642 | 0 | 11-$882,976 | |
| 2 | APEX LANDSCAPE & IRRIGATION, LLC | $1,505,677 | +30.8% | -11.1% | $79,345 | 2+$45,624 | 7-$510,333 |
| 3 | GREEN SAGE SERVICES LLC | $1,585,022 | +37.7% | -6.4% | $171,004 | 5+$147,511 | 7-$685,939 |
| 4 | ABESCAPE LANDSCAPING, LLC | $1,756,026 | +52.6% | 3.7% | $436,674 | 6+$270,585 | 3-$464,129 |
| 5 | CENTRAL NORTH CONSTRUCTION, LLC | $2,192,700 | +90.5% | 29.5% | 7+$961,056 | 5-$569,555 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
YELLOWSTONE LANDSCAPE - CENTRAL, INC. vs APEX LANDSCAPE & IRRIGATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $147,500.00 | $523,850.32 | $122,500 |
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $20,000.00 | $130,500.00 | $150,903.93 | $110,500 |
| 161-7008 EROSION CONTROL COMPOST (VEH) | 2,545.25 CY | $52.39 | $25.00 | $34.44 | -$69,702 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $336.60 | $9,500.00 | $11,585.04 | $64,144 |
| 193-7002 LANDSCAPE ESTABLISH | 2 CYC | $4,958.10 | $34,000.00 | $21,267.99 | $58,084 |
| 170-7003 IRRIGATION SYSTEM (TY II) | 1 EA | $31,666.67 | $77,500.00 | $47,499.10 | $45,833 |
| 193-7028 LANDSCAPE TREAT (TY III) | 23,340 EA | $2.71 | $1.00 | $3.50 | -$40,005 |
| 161-7010 GENERAL USE COMPOST (VEH) | 1,267.25 CY | $49.98 | $24.00 | $33.88 | -$32,919 |
| 193-7010 IRRIG SYS OPER AND MAINT (SCH A) | 19 MO | $850.88 | $2,500.00 | $872.12 | $31,333 |
| 192-7011 PLANT BED PREP (TY II) | 22,956 SY | $0.3630 | $1.50 | $2.26 | $26,101 |
| 193-7037 LANDSCAPE TREAT (TY IV) | 2 CYC | $2,916.67 | $15,000.00 | $7,652.67 | $24,167 |
| 192-7039 PLANT MATERIAL (30 GAL) (TREE) | 911 EA | $285.40 | $265.00 | $323.72 | -$18,585 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $3,833.33 | $10,000.00 | $8,682.96 | $12,333 |
| 192-7028 PLANT MATERIAL (3 GAL) | 22,429 EA | $16.94 | $17.45 | $20.24 | $11,394 |
| 193-7011 IRRIG SYS OPER AND MAINT (SCH B) | 12 MO | $2,083.33 | $3,000.00 | $2,083.33 | $11,000 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $16.67 | $100.00 | $217.57 | $10,000 |
| 162-7002 BLOCK SODDING | 2,295 SY | $5.08 | $2.00 | $4.39 | -$7,078 |
| 192-7084 SOIL AMEND (TY II) | 22,956 SY | $0.1000 | $0.4000 | $0.8229 | $6,887 |
| 505-7003 TMA (MOBILE OPERATION) | 145 DAY | $43.68 | $0.1000 | $229.60 | -$6,319 |
| 432-7003 RIPRAP (CONC)(6 IN) | 37.43 CY | $890.55 | $750.00 | $580.25 | -$5,261 |
Positive: the low bidder was cheaper on that item. These 20 items account for $354,407 of the $354,642 gap.
YELLOWSTONE LANDSCAPE - CENTRAL, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $25,000.00 | $523,850.32 | 0.05x | -$498,850 |
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $20,000.00 | $150,903.93 | 0.13x | -$130,904 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $336.60 | $11,585.04 | 0.03x | -$78,739 |
| 192-7011 PLANT BED PREP (TY II) | 22,956 SY | $0.3630 | $2.26 | 0.16x | -$43,474 |
| 193-7002 LANDSCAPE ESTABLISH | 2 CYC | $4,958.10 | $21,267.99 | 0.23x | -$32,620 |
| 505-7003 TMA (MOBILE OPERATION) | 145 DAY | $43.68 | $229.60 | 0.19x | -$26,958 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $16.67 | $217.57 | 0.08x | -$24,109 |
| 192-7084 SOIL AMEND (TY II) | 22,956 SY | $0.1000 | $0.8229 | 0.12x | -$16,595 |
| 192-7008 SOIL AMEND (TY I) | 22,956 SY | $0.3050 | $0.8084 | 0.38x | -$11,556 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $3,833.33 | $8,682.96 | 0.44x | -$9,699 |
APEX LANDSCAPE & IRRIGATION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 193-7010 IRRIG SYS OPER AND MAINT (SCH A) | 19 MO | $2,500.00 | $872.12 | 2.87x | $30,930 |
| 193-7037 LANDSCAPE TREAT (TY IV) | 2 CYC | $15,000.00 | $7,652.67 | 1.96x | $14,695 |
| 500-7001 MOBILIZATION | 1 LS | $147,500.00 | $523,850.32 | 0.28x | -$376,350 |
| 193-7028 LANDSCAPE TREAT (TY III) | 23,340 EA | $1.00 | $3.50 | 0.29x | -$58,460 |
| 505-7003 TMA (MOBILE OPERATION) | 145 DAY | $0.1000 | $229.60 | 0.00x | -$33,277 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $100.00 | $217.57 | 0.46x | -$14,109 |
| 192-7084 SOIL AMEND (TY II) | 22,956 SY | $0.4000 | $0.8229 | 0.49x | -$9,708 |
| 192-7008 SOIL AMEND (TY I) | 22,956 SY | $0.4000 | $0.8084 | 0.49x | -$9,375 |
| 506-7043 BIODEG EROSN CONT LOGS (INSTL) (8") | 2,000 LF | $0.1000 | $4.63 | 0.02x | -$9,054 |
GREEN SAGE SERVICES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 145 DAY | $490.00 | $229.60 | 2.13x | $37,758 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $25,500.00 | $8,682.96 | 2.94x | $33,634 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $480.00 | $217.57 | 2.21x | $31,491 |
| 432-7003 RIPRAP (CONC)(6 IN) | 37.43 CY | $1,200.00 | $580.25 | 2.07x | $23,197 |
| 193-7010 IRRIG SYS OPER AND MAINT (SCH A) | 19 MO | $2,000.00 | $872.12 | 2.29x | $21,430 |
| 500-7001 MOBILIZATION | 1 LS | $115,000.00 | $523,850.32 | 0.22x | -$408,850 |
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $40,000.00 | $150,903.93 | 0.27x | -$110,904 |
| 193-7028 LANDSCAPE TREAT (TY III) | 23,340 EA | $0.4000 | $3.50 | 0.11x | -$72,464 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $5,700.00 | $11,585.04 | 0.49x | -$41,195 |
| 192-7011 PLANT BED PREP (TY II) | 22,956 SY | $1.00 | $2.26 | 0.44x | -$28,851 |
| 192-7084 SOIL AMEND (TY II) | 22,956 SY | $0.3000 | $0.8229 | 0.36x | -$12,004 |
| 192-7008 SOIL AMEND (TY I) | 22,956 SY | $0.3000 | $0.8084 | 0.37x | -$11,671 |
ABESCAPE LANDSCAPING, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 170-7003 IRRIGATION SYSTEM (TY II) | 1 EA | $200,000.00 | $47,499.10 | 4.21x | $152,501 |
| 192-7011 PLANT BED PREP (TY II) | 22,956 SY | $4.00 | $2.26 | 1.77x | $40,017 |
| 505-7003 TMA (MOBILE OPERATION) | 145 DAY | $450.00 | $229.60 | 1.96x | $31,958 |
| 193-7037 LANDSCAPE TREAT (TY IV) | 2 CYC | $16,000.00 | $7,652.67 | 2.09x | $16,695 |
| 193-7010 IRRIG SYS OPER AND MAINT (SCH A) | 19 MO | $1,650.00 | $872.12 | 1.89x | $14,780 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $16,000.00 | $8,682.96 | 1.84x | $14,634 |
| 500-7001 MOBILIZATION | 1 LS | $185,000.00 | $523,850.32 | 0.35x | -$338,850 |
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $35,000.00 | $150,903.93 | 0.23x | -$115,904 |
| 192-7008 SOIL AMEND (TY I) | 22,956 SY | $0.4000 | $0.8084 | 0.49x | -$9,375 |
CENTRAL NORTH CONSTRUCTION, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 170-7003 IRRIGATION SYSTEM (TY II) | 1 EA | $300,000.00 | $47,499.10 | 6.32x | $252,501 |
| 170-7002 IRRIGATION SYSTEM (TY I) | 1 EA | $382,313.72 | $150,903.93 | 2.53x | $231,410 |
| 432-7003 RIPRAP (CONC)(6 IN) | 37.43 CY | $3,850.00 | $580.25 | 6.64x | $122,387 |
| 193-7037 LANDSCAPE TREAT (TY IV) | 2 CYC | $68,000.00 | $7,652.67 | 8.89x | $120,695 |
| 193-7010 IRRIG SYS OPER AND MAINT (SCH A) | 19 MO | $7,000.00 | $872.12 | 8.03x | $116,430 |
| 193-7011 IRRIG SYS OPER AND MAINT (SCH B) | 12 MO | $7,000.00 | $2,083.33 | 3.36x | $59,000 |
| 193-7036 LANDSCAPE TREAT (TY III) | 2 CYC | $38,000.00 | $8,682.96 | 4.38x | $58,634 |
| 500-7001 MOBILIZATION | 1 LS | $105,000.00 | $523,850.32 | 0.20x | -$418,850 |
| 193-7028 LANDSCAPE TREAT (TY III) | 23,340 EA | $1.00 | $3.50 | 0.29x | -$58,460 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 MO | $5,000.00 | $11,585.04 | 0.43x | -$46,095 |
| 505-7003 TMA (MOBILE OPERATION) | 145 DAY | $50.00 | $229.60 | 0.22x | -$26,042 |
| 505-7001 TMA (STATIONARY) | 120 DAY | $50.00 | $217.57 | 0.23x | -$20,109 |