Sweeping and Debris North & West 2027
6509-25-001 · let Nov 3, 2026 · Harris, Houston · Routine Maintenance Project - Sealed
$4,495,312Low bid: SWEEPING CORPORATION OF AMERICA, LLC+18.1% vs estimate $3,805,043
$909,542Left on the table20.2% gap to the second bid
2BiddersSpread 20% low to high
9Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SWEEPING CORPORATION OF AMERICA, LLC | $4,495,312 | 18.1% | $909,542 | 0 | 4-$644,781 | |
| 2 | PROFESSIONAL TRAFFIC CONTROL LLC | $5,404,854 | +20.2% | 42.0% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.
Where the job was won
SWEEPING CORPORATION OF AMERICA, LLC vs PROFESSIONAL TRAFFIC CONTROL LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 1,560 DAY | $1.00 | $350.00 | $217.57 | $544,440 |
| 735-7003 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) | 2,280 MI | $22.00 | $100.00 | $72.08 | $177,840 |
| 738-7049 CLEANING / SWEEPING (FRONTAGE ROAD) | 4,356 MI | $164.00 | $125.00 | $175.99 | -$169,884 |
| 735-7049 DEBRIS REMOVAL (DIRECT CONNECTOR) | 1,632 MI | $22.00 | $100.00 | $75.88 | $127,296 |
| 735-7037 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 2,052 MI | $22.00 | $75.00 | $73.08 | $108,756 |
| 738-7025 CLEANING / SWEEPING (OUTSIDE MAIN LANE) | 8,984.44 MI | $164.00 | $175.00 | $197.36 | $98,829 |
| 738-7001 CLEANING / SWEEPING (CENTER MEDIAN) | 8,844.44 MI | $164.00 | $175.00 | $187.45 | $97,289 |
| 738-7070 CLEANING / SWEEPING(ENTRANCE/EXIT RAMP) | 2,472 MI | $164.00 | $125.00 | $162.48 | -$96,408 |
| 738-7091 CLEANING / SWEEPING (DIRECT CONNECTOR) | 1,944 MI | $164.00 | $175.00 | $169.58 | $21,384 |
Positive: the low bidder was cheaper on that item. These 9 items account for $909,542 of the $909,542 gap.
SWEEPING CORPORATION OF AMERICA, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 1,560 DAY | $1.00 | $217.57 | 0.00x | -$337,852 |
| 735-7003 DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES) | 2,280 MI | $22.00 | $72.08 | 0.31x | -$114,182 |
| 735-7037 DEBRIS REMOVAL (ENTRANCE/EXIT RAMPS) | 2,052 MI | $22.00 | $73.08 | 0.30x | -$104,810 |
| 735-7049 DEBRIS REMOVAL (DIRECT CONNECTOR) | 1,632 MI | $22.00 | $75.88 | 0.29x | -$87,937 |