Overlay
CCSJ 0085-01-053 · lets Jan 6, 2027 · Bowie, Morris, Atlanta · FM 561, US 259 · Rehabilitate Existing Roadway
$7,996,510Engineer's estimate
Items at market: $7,445,062 (-6.9%)
$7,528,089Most likely low bid$6,617,695 to $7,983,421 (middle half)
4.3Expected bidders0 plan holders, 0 regular bidders
64/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$7,528,089
Estimate $7,996,510
$6,154,254 (1 in 10 go lower)$10,781,653 (1 in 10 go higher)
From 32 comparable let jobs (district, estimates of $3,198,604 to $19,991,274, last 3 years). 75% of them went under the estimate; the typical low bid was -5.9% vs estimate.
Bid / no-bid score
- Competition20 / 25Jobs like this draw about 4.3 bidders.
- Margin9 / 20Low bids land at 94% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Oct 2026 | 0010-08-061Morris · 6 bidders | $11,965,134+8.4% |
| Oct 2026 | 6501-57-001Bowie · 5 bidders | $5,500,500-10.3% |
| Oct 2026 | 6501-58-001Harrison · 4 bidders | $6,111,500-0.3% |
| Aug 2026 | 0610-05-060Bowie · 4 bidders | $10,625,436-14.3% |
| Aug 2026 | 6501-56-001Bowie · 3 bidders | $3,381,575-4.6% |
| Aug 2026 | 0208-01-026Harrison · 5 bidders | $3,320,428+0.4% |
| Aug 2026 | 0222-03-065Morris · 7 bidders | $10,759,105-8.5% |
| May 2026 | 0610-03-095Titus · 6 bidders | $9,498,729-16.0% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
154 of 157 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 247-7176 FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)49 low bids · prices swing 14x | 10,745 CY | $88.59 | $43.47 – $600.00 | $951,945 | 12.8% |
| 344-7064 SP MIXES SP-D SAC-A PG76-2244 low bids | 6,297 TON | $129.17 | $106.50 – $300.00 | $813,396 | 10.9% |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-2261 low bids · prices swing 4x | 5,312 TON | $152.44 | $105.75 – $383.00 | $809,755 | 10.9% |
| 100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x | 99.5 STA | $6,072.92 | $0.0100 – $861,170.00 | $604,256 | 8.1% |
| 344-7063 SP MIXES SP-D PG76-222 low bids | 5,106 TON | $104.27 | $100.38 – $225.00 | $532,421 | 7.2% |
| 105-7008 RMV (8"-12") TRT/UNTRT BASE & ASPH PAV26 low bids · prices swing 75x | 48,498 SY | $8.89 | $4.00 – $300.00 | $430,932 | 5.8% |
| 346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-2261 low bids · prices swing 4x | 2,401 TON | $152.44 | $105.75 – $383.00 | $366,006 | 4.9% |
| 275-7001 CEMENT213 low bids · prices swing 16x | 1,534 TON | $224.93 | $167.30 – $2,750.00 | $345,048 | 4.6% |
| 100-7002 PREPARING ROW593 low bids · prices swing 86,117,000x | 43 STA | $6,072.92 | $0.0100 – $861,170.00 | $261,136 | 3.5% |
| 351-7003 FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")94 low bids · prices swing 22x | 5,299 SY | $35.01 | $15.00 – $325.00 | $185,544 | 2.5% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.34 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $178,109 | 2.4% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.33 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $172,871 | 2.3% |
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 0.33 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $172,871 | 2.3% |
| 275-7003 CEMENT TRT (EXIST MATL)(8")56 low bids · prices swing 18x | 48,498 SY | $3.04 | $1.40 – $25.00 | $147,370 | 2.0% |
| 316-7256 AGGR (TY-PB, GR-4)2 low bids · prices swing 4x | 395 CY | $243.61 | $120.00 – $500.00 | $96,228 | 1.3% |