Bid Tab X-ray: 6501-58-001

Oct 6, 2026 · Harrison Sign up free
Set your company to personalize scores

Mill and Inlay (S) FY2027

6501-58-001 · let Oct 6, 2026 · Harrison, Atlanta · Routine Maintenance Project - Sealed

$6,111,500Low bid: EAST TEXAS BRIDGE, INC.-0.3% vs estimate $6,132,750
$68,000Left on the table1.1% gap to the second bid
4BiddersSpread 17% low to high
19Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1EAST TEXAS BRIDGE, INC. $6,111,500-0.3% $68,000 1+$195,193 0
2HIGHWAY 19 CONSTRUCTION LLC $6,179,500+1.1%0.8% $359,785 1+$595,193 0
3MADDEN CONTRACTING COMPANY, LLC. $6,539,285+7.0%6.6% $627,690 1+$527,193 1-$69,252
4LONGVIEW BRIDGE AND ROAD, LTD. $7,166,975+17.3%16.9% 2+$495,441 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

EAST TEXAS BRIDGE, INC. vs HIGHWAY 19 CONSTRUCTION LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
344-7030 SP MIXES SP-C SAC-A PG76-2220,000 TON $196.00$175.00$138.38 -$420,000
500-7002 MOBILIZATION (CALLOUT)8 EA $25,000.00$75,000.00$600.85 $400,000
305-7018 SALV,HAUL & STKPL RCL APH PV (2")50,000 SY $3.00$3.95$2.36 $47,500
305-7016 SALV, HAUL & STKPL RCL APH PV (3")50,000 SY $4.00$4.45$3.61 $22,500
342-7001 PFC-C PG76-22 SAC-A5,000 TON $224.00$220.00$170.34 -$20,000
342-7015 TACK COAT5,500 GAL $5.00$8.00$3.37 $16,500
662-7115 WK ZN PAV MRK SHT TERM RMV (W)(4")10,000 LF $1.85$3.50$1.83 $16,500
662-7116 WK ZN PAV MRK SHT TERM RMV (Y)(4")10,000 LF $1.85$3.50$1.57 $16,500
305-7039 SALV, HAUL & STKPL RCL APH PV (5"-7")6,000 SY $9.00$6.50$9.00 -$15,000
505-7001 TMA (STATIONARY)50 DAY $250.00$500.00$217.57 $12,500
305-7022 SALV, HAUL & STKPL RCL APH PV (4")30,000 SY $5.30$5.05$4.16 -$7,500
505-7002 TMA (MOBILE OPERATION)350 HR $30.00$40.00$64.00 $3,500
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN50 DAY $200.00$250.00$87.82 $2,500
666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL)50,000 LF $0.7000$0.6500$0.6917 -$2,500
666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL)50,000 LF $0.7000$0.6500$0.6819 -$2,500
668-7089 PREFAB PM TY C (W)(24")(SLD)1,000 LF $15.00$13.50$13.72 -$1,500
666-7310 ALL-WTHER PM TY I (W)6"(BRK)(100MIL)10,000 LF $0.8000$0.7500$0.8630 -$500
666-7316 ALL-WTHER PM TY I (Y)6"(BRK)(100MIL)10,000 LF $0.8000$0.7500$0.7727 -$500
344-7077 TACK COAT22,000 GAL $5.00$5.00$3.25 $0

Positive: the low bidder was cheaper on that item. These 19 items account for $68,000 of the $68,000 gap.

EAST TEXAS BRIDGE, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)8 EA $25,000.00$600.8541.61x$195,193

HIGHWAY 19 CONSTRUCTION LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)8 EA $75,000.00$600.85124.82x$595,193

MADDEN CONTRACTING COMPANY, LLC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)8 EA $66,500.00$600.85110.68x$527,193
344-7077 TACK COAT22,000 GAL $0.1000$3.250.03x-$69,252

LONGVIEW BRIDGE AND ROAD, LTD.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
500-7002 MOBILIZATION (CALLOUT)8 EA $50,000.00$600.8583.22x$395,193
305-7022 SALV, HAUL & STKPL RCL APH PV (4")30,000 SY $7.50$4.161.80x$100,248