Bridge Maintenance
CCSJ 0045-19-066 · lets Jan 7, 2027 · Fannin, Grayson, Paris · US 82 · Bridge Maintenance
$3,108,693Engineer's estimate
Items at market: $2,935,334 (-5.6%)
$2,867,441Most likely low bid$2,604,850 to $3,122,632 (middle half)
5.2Expected bidders0 plan holders, 0 regular bidders
53/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$2,867,441
Estimate $3,108,693
$2,296,434 (1 in 10 go lower)$3,413,406 (1 in 10 go higher)
From 74 comparable let jobs (district, estimates of $1,243,477 to $7,771,732, last 3 years). 73% of them went under the estimate; the typical low bid was -7.8% vs estimate.
Bid / no-bid score
- Competition16 / 25Jobs like this draw about 5.2 bidders.
- Margin8 / 20Low bids land at 92% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 1017-03-040Hunt · 9 bidders | $6,803,596+4.4% |
| Nov 2026 | 0901-00-066Lamar · 4 bidders | $3,520,879-11.3% |
| Nov 2026 | 0045-09-113Lamar · 5 bidders | $3,510,998-4.7% |
| Sep 2026 | 0722-03-016Red River · 8 bidders | $1,474,741-13.6% |
| Sep 2026 | 0901-19-198Grayson · 8 bidders | $2,130,337-14.9% |
| Sep 2026 | 0427-01-042Red River · 7 bidders | $1,792,908+0.5% |
| Sep 2026 | 0549-02-038Fannin · 4 bidders | $1,979,905+8.2% |
| Aug 2026 | 6506-23-001Grayson · 1 bidders | $1,934,598-1.0% |
The field: plan holders and how they bid
Last 3 years in TexasNo plan holders posted for this job yet. Check back closer to the letting.
Items that decide this job
62 of 64 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION2229 low bids · prices swing 42,200,000,000x | 1 LS | $523,850.32 | $0.0010 – $42,200,000.00 | $523,850 | 17.8% |
| 439-7017 POLYESTER POLYMER CONC OVERLAY (2")13 low bids · prices swing 3x | 2,151 SY | $234.43 | $151.00 – $525.10 | $504,267 | 17.2% |
| 439-7014 MULTI-LAYER POLYMER OVERLAY34 low bids · prices swing 10x | 11,391 SY | $40.32 | $28.00 – $275.00 | $459,283 | 15.6% |
| 439-7014 MULTI-LAYER POLYMER OVERLAY34 low bids · prices swing 10x | 4,626 SY | $40.32 | $28.00 – $275.00 | $186,520 | 6.4% |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2018 low bids · prices swing 273,686,480x | 14 MO | $11,585.04 | $0.0010 – $273,686.48 | $162,191 | 5.5% |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN)241 low bids · prices swing 20x | 757 CY | $184.74 | $60.37 – $1,180.00 | $139,847 | 4.8% |
| 427-7005 EPOXY WATERPROOF FINISH (TY X)29 low bids · prices swing 46x | 13,699 SF | $9.61 | $3.57 – $165.00 | $131,607 | 4.5% |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN)241 low bids · prices swing 20x | 677 CY | $184.74 | $60.37 – $1,180.00 | $125,068 | 4.3% |
| 787-7001 REPLACING ELASTOMERIC BEARING PADS38 low bids · prices swing 64x | 28 EA | $2,783.49 | $486.00 – $31,070.00 | $77,938 | 2.7% |
| 483-7016 SHOT BLASTING34 low bids · prices swing 65x | 13,542 SY | $5.25 | $2.00 – $130.00 | $71,146 | 2.4% |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7)154 low bids · prices swing 24x | 1,767 LF | $38.57 | $9.00 – $214.00 | $68,155 | 2.3% |
| 785-7004 BRIDGE JOINT REPAIR (ARMOR)23 low bids · prices swing 171x | 172 LF | $334.68 | $25.00 – $4,275.00 | $57,565 | 2.0% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 220 DAY | $217.57 | $0.0010 – $16,487.00 | $47,866 | 1.6% |
| 439-7014 MULTI-LAYER POLYMER OVERLAY34 low bids · prices swing 10x | 1,149 SY | $40.32 | $28.00 – $275.00 | $46,327 | 1.6% |
| 400-7010 CEM STABIL BKFL452 low bids · prices swing 1,000x | 311 CY | $138.14 | $1.00 – $1,000.00 | $42,963 | 1.5% |