FM 35 Repair and Widen
1017-03-040 · let Nov 4, 2026 · Hunt, Paris · Restoration
$6,803,596Low bid: HIGHWAY 19 CONSTRUCTION LLC+4.4% vs estimate $6,517,921
$438,151Left on the table6.4% gap to the second bid
9BiddersSpread 35% low to high
129Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HIGHWAY 19 CONSTRUCTION LLC | $6,803,596 | 4.4% | $438,151 | 1+$40,654 | 2-$1,705,183 | |
| 2 | THK CONSTRUCTION LLC | $7,241,746 | +6.4% | 11.1% | $125,008 | 4+$335,495 | 3-$1,733,205 |
| 3 | EAST TEXAS BRIDGE, INC. | $7,366,754 | +8.3% | 13.0% | $33,594 | 1+$241,990 | 3-$1,635,527 |
| 4 | D. L. LENNON INCORPORATED - CONTRACTOR | $7,400,348 | +8.8% | 13.5% | $114,369 | 4+$395,733 | 2-$1,594,329 |
| 5 | RK HALL, LLC | $7,514,717 | +10.5% | 15.3% | $280,263 | 6+$487,533 | 2-$1,591,988 |
| 6 | AUSTIN BRIDGE & ROAD SERVICES, LP | $7,794,981 | +14.6% | 19.6% | $179 | ||
| 7 | TEXAS MATERIALS GROUP, INC. | $7,795,159 | +14.6% | 19.6% | $530,346 | ||
| 8 | CDM HOLDINGS | $8,325,506 | +22.4% | 27.7% | $833,668 | ||
| 9 | ED BELL CONSTRUCTION COMPANY | $9,159,173 | +34.6% | 40.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HIGHWAY 19 CONSTRUCTION LLC vs THK CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 24,930 TON | $131.00 | $143.12 | $97.82 | $302,152 |
| 466-7190 WINGWALL (PW - 2) (HW=6 FT) | 4 EA | $18,000.00 | $45,000.00 | $20,350.40 | $108,000 |
| 500-7001 MOBILIZATION | 1 LS | $600,000.00 | $500,000.00 | $523,850.32 | -$100,000 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 18,509 CY | $15.00 | $10.00 | $12.93 | -$92,545 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $5,000.00 | $20,000.00 | $9,253.78 | $90,000 |
| 466-7191 WINGWALL (PW - 2) (HW=7 FT) | 2 EA | $21,000.00 | $60,000.00 | $28,960.30 | $78,000 |
| 400-7007 CUT & RESTORE CONC PAVING | 264 SY | $350.00 | $120.00 | $196.01 | -$60,720 |
| 110-7001 EXCAV (ROADWAY) | 22,931 CY | $7.45 | $10.00 | $11.68 | $58,474 |
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 984 CY | $194.00 | $249.67 | $137.54 | $54,779 |
| 496-7007 REMOV STR (PIPE) | 2,937 LF | $20.00 | $5.00 | $23.96 | -$44,055 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 2,339 SY | $3.00 | $20.00 | $7.43 | $39,763 |
| 530-7010 DRIVEWAYS (ACP) | 790 SY | $75.00 | $28.53 | $54.96 | -$36,713 |
| 403-7001 TEMPORARY SPL SHORING | 1,478 SF | $10.00 | $30.00 | $25.56 | $29,560 |
| 100-7002 PREPARING ROW | 281 STA | $543.00 | $643.00 | $6,072.92 | $28,100 |
| 467-7308 SET (TY II) (18 IN) (RCP) (6: 1) (P) | 191 EA | $795.00 | $700.00 | $1,176.76 | -$18,145 |
| 496-7004 REMOV STR (SET) | 37 EA | $500.00 | $100.00 | $514.07 | -$14,800 |
| 112-7004 SUBGR WIDEN (DC) | 72 SY | $50.00 | $250.00 | $4.13 | $14,400 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 70 CY | $600.00 | $750.00 | $616.83 | $10,500 |
| 462-7027 CONC BOX CULV (9 FT X 5 FT) | 112 LF | $913.00 | $1,000.00 | $1,063.28 | $9,744 |
| 416-7046 DRILL SHAFT (TRF SIG POLE) (48 IN) | 21 LF | $700.00 | $1,136.00 | $680.57 | $9,156 |
Positive: the low bidder was cheaper on that item. These 20 items account for $465,650 of the $438,151 gap.
HIGHWAY 19 CONSTRUCTION LLC: unbalanced items
Placed 1THK CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 984 CY | $249.67 | $137.54 | 1.82x | $110,340 |
| 466-7190 WINGWALL (PW - 2) (HW=6 FT) | 4 EA | $45,000.00 | $20,350.40 | 2.21x | $98,598 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $20,000.00 | $9,253.78 | 2.16x | $64,477 |
| 466-7191 WINGWALL (PW - 2) (HW=7 FT) | 2 EA | $60,000.00 | $28,960.30 | 2.07x | $62,079 |
| 100-7002 PREPARING ROW | 281 STA | $643.00 | $6,072.92 | 0.11x | -$1,525,808 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,471.55 | $11,585.04 | 0.13x | -$151,702 |
| 496-7007 REMOV STR (PIPE) | 2,937 LF | $5.00 | $23.96 | 0.21x | -$55,695 |
EAST TEXAS BRIDGE, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7004 EMBANK (FNL)(DC)(TY B) | 18,509 CY | $26.00 | $12.93 | 2.01x | $241,990 |
| 100-7002 PREPARING ROW | 281 STA | $750.00 | $6,072.92 | 0.12x | -$1,495,741 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $5,000.00 | $11,585.04 | 0.43x | -$98,776 |
| 496-7007 REMOV STR (PIPE) | 2,937 LF | $10.00 | $23.96 | 0.42x | -$41,010 |
D. L. LENNON INCORPORATED - CONTRACTOR: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 45,585 GAL | $7.50 | $3.44 | 2.18x | $185,084 |
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 984 CY | $265.00 | $137.54 | 1.93x | $125,425 |
| 112-7004 SUBGR WIDEN (DC) | 72 SY | $650.00 | $4.13 | 157.43x | $46,503 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 2,339 SY | $23.98 | $7.43 | 3.23x | $38,721 |
| 100-7002 PREPARING ROW | 281 STA | $566.00 | $6,072.92 | 0.09x | -$1,547,445 |
| 496-7007 REMOV STR (PIPE) | 2,937 LF | $8.00 | $23.96 | 0.33x | -$46,884 |
RK HALL, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 45,585 GAL | $6.83 | $3.44 | 1.99x | $154,542 |
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 984 CY | $241.87 | $137.54 | 1.76x | $102,665 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 2,339 SY | $44.92 | $7.43 | 6.05x | $87,700 |
| 112-7004 SUBGR WIDEN (DC) | 72 SY | $840.00 | $4.13 | 203.45x | $60,183 |
| 505-7001 TMA (STATIONARY) | 200 DAY | $424.36 | $217.57 | 1.95x | $41,358 |
| 168-7001 VEGETATIVE WATERING | 856 TGL | $56.43 | $8.43 | 6.69x | $41,085 |
| 100-7002 PREPARING ROW | 281 STA | $570.15 | $6,072.92 | 0.09x | -$1,546,279 |
| 496-7007 REMOV STR (PIPE) | 2,937 LF | $8.40 | $23.96 | 0.35x | -$45,709 |