Bridge Repair
- Let date
- Thursday, September 18, 2025
- Contract
- 250262 · job page
- J/P numbers
- 38401(04)
- District
- Division 3
- County
- Cleveland, Oklahoma
- Highway
- COUNTY ROADS AND CITY STREETS
- Limits
- COUNTY ROADS AND CITY STREETS: OVER N CANADIAN RIVER, CROOKED OAK CREEK, CRUTCHO CREEK, AND HOG CREEK, AT MULTIPLE LOCATIONS IN DISTRICT III AND DISTRICT IV.
- Classification
- Bridge Repair
- Project number
- BRO-255F(709)CB
- Working days
- 65
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $268,253 | ||
| 1 | Haskell Lemon Group, LLC Low bidder | $310,629 | +15.8% | |
| 2 | Built Right Construction, LLC | $345,670 | +28.9% | +11.3% |
| 3 | K & R BUILDERS, INC. | $356,703 | +33.0% | +14.8% |
| 4 | SAC Services, Inc. | $363,260 | +35.4% | +16.9% |
| 5 | LOGOS CONSTRUCTION CO., LLC | $367,511 | +37.0% | +18.3% |
| 6 | PBX Corporation | $370,425 | +38.1% | +19.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Haskell Lemon G… | #2 Built Right Con… | #3 K & R BUILDERS,… | #4 SAC Services, I… | #5 LOGOS CONSTRUCT… | #6 PBX Corporation |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $2,000.00 | $7,666.00 | $7,500.00 | $16,750.00 | $7,500.00 | $9,760.00 | $4,000.00 |
| 20 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 89 | CY | $45.00 | $8.95 | $30.00 | $31.50 | $60.00 | $163.00 | $56.00 |
| 30 | 509(A)0210 | CLASS AA CONCRETE | 1 | CY | $1,750.00 | $9,025.00 | $1,500.00 | $6,104.00 | $1,250.00 | $6,500.00 | $6,500.00 |
| 40 | 511(A)2210 | REINFORCING STEEL | 140 | LB | $2.15 | $8.20 | $3.00 | $4.70 | $10.00 | $3.55 | $3.00 |
| 50 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 140 | TON | $110.00 | $83.60 | $175.00 | $109.00 | $125.00 | $194.00 | $165.00 |
| 60 | 601(C)1310 | TYPE I-A FILTER BLANKET | 35 | TON | $70.00 | $68.00 | $150.00 | $80.00 | $115.00 | $155.00 | $155.00 |
| 70 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $3,000.00 | $9,688.00 | $7,500.00 | $7,900.00 | $7,500.00 | $11,400.00 | $7,000.00 |
| 80 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 77 | CY | $45.00 | $33.30 | $30.00 | $29.50 | $60.00 | $163.00 | $55.00 |
| 90 | 521(A)2200 | PNEUMATICALLY PLACED MORTAR | 2 | SY | $1,260.00 | $4,842.00 | $1,000.00 | $2,329.50 | $300.00 | $1,273.00 | $1,500.00 |
| 100 | 535 7100 | CORROSION INHIBITOR(SURFACE APPLIED) | 1 | SY | $50.00 | $349.00 | $60.00 | $175.00 | $350.00 | $50.00 | $25.00 |
| 110 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 120 | TON | $115.00 | $130.50 | $175.00 | $109.00 | $125.00 | $194.00 | $200.00 |
| 120 | 601(C)1310 | TYPE I-A FILTER BLANKET | 30 | TON | $70.00 | $130.50 | $150.00 | $80.00 | $115.00 | $155.00 | $185.00 |
| 130 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 61 | CY | $45.00 | $42.00 | $30.00 | $51.50 | $60.00 | $163.00 | $90.00 |
| 140 | 501(G)1800 | CLSM BACKFILL | 28 | CY | $370.00 | $306.00 | $450.00 | $350.00 | $750.00 | $500.00 | $775.00 |
| 150 | 509(A)0210 | CLASS AA CONCRETE | 39 | CY | $1,260.00 | $1,306.00 | $1,300.00 | $500.00 | $1,220.00 | $952.00 | $1,100.00 |
| 160 | 511(A)2210 | REINFORCING STEEL | 5,450 | LB | $1.70 | $2.80 | $3.00 | $2.55 | $3.00 | $2.41 | $3.00 |
| 170 | 535 7100 | CORROSION INHIBITOR(SURFACE APPLIED) | 31 | SY | $50.00 | $33.60 | $60.00 | $65.00 | $350.00 | $50.00 | $25.00 |
| 180 | 540 8100 | (PL)REPAIR BRIDGE ITEMS | 1 | LSUM | $5,000.00 | $9,444.00 | $6,000.00 | $58,850.00 | $12,500.00 | $3,255.00 | $3,000.00 |
| 190 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 90 | TON | $105.00 | $152.00 | $175.00 | $118.00 | $125.00 | $194.00 | $185.00 |
| 200 | 601(C)1310 | TYPE I-A FILTER BLANKET | 25 | TON | $75.00 | $148.00 | $150.00 | $92.00 | $115.00 | $155.00 | $155.00 |
| 210 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 103 | CY | $40.00 | $49.70 | $30.00 | $32.00 | $60.00 | $163.00 | $74.00 |
| 220 | 501(G)1800 | CLSM BACKFILL | 13 | CY | $435.00 | $332.00 | $450.00 | $828.00 | $700.00 | $702.00 | $920.00 |
| 230 | 509(A)0210 | CLASS AA CONCRETE | 40 | CY | $1,260.00 | $1,222.00 | $1,500.00 | $1,125.00 | $1,220.00 | $952.00 | $1,300.00 |
| 240 | 511(A)2210 | REINFORCING STEEL | 5,560 | LB | $1.70 | $2.80 | $3.00 | $2.55 | $3.00 | $2.41 | $3.00 |
| 250 | 540 8100 | (PL)REPAIR BRIDGE ITEMS | 1 | LSUM | $5,000.00 | $9,300.00 | $6,000.00 | $30,000.00 | $7,800.00 | $3,255.00 | $4,000.00 |
| 260 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 160 | TON | $105.00 | $114.50 | $175.00 | $112.50 | $125.00 | $194.00 | $165.00 |
| 270 | 601(C)1310 | TYPE I-A FILTER BLANKET | 40 | TON | $65.00 | $109.50 | $150.00 | $87.00 | $115.00 | $155.00 | $155.00 |
| 280 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $9,000.00 | $4,575.00 | $7,000.00 | $7,000.00 | $10,500.00 | $10,200.00 | $7,000.00 |
| 290 | 641 2100 | MOBILIZATION | 1 | LSUM | $25,000.00 | $20,402.00 | $25,000.00 | $30,000.00 | $45,000.00 | $20,750.00 | $39,583.72 |