Bridge Repair
- Let date
- Thursday, November 13, 2025
- Contract
- 250256 · job page
- J/P numbers
- 38358(04)
- District
- Division 4
- County
- Grant, Kay, Noble, Pawnee
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER WALKER CREEK, SHOO FLY CREEK, BLACK BEAR CREEK, COTTON WOOD CREEK AND UNNAMED CREEK, AT MULTIPLE LOCATIONS IN DISTRICT IV AND DISTRICT VIII.
- Classification
- Bridge Repair
- Project number
- BRO-236F(135)CB
- Working days
- 50
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $384,955 | ||
| 1 | K & R BUILDERS, INC. Low bidder | $291,246 | -24.3% | |
| 2 | Wyatt Contracting | $328,680 | -14.6% | +12.9% |
| 3 | Haskell Lemon Group, LLC | $377,170 | -2.0% | +29.5% |
| 5 | Built Right Construction, LLC | $437,415 | +13.6% | +50.2% |
| 6 | PBX Corporation | $473,742 | +23.1% | +62.7% |
| 7 | LOGOS CONSTRUCTION CO., LLC | $501,911 | +30.4% | +72.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K & R BUILDERS,… | #2 Wyatt Contracti… | #3 Haskell Lemon G… | #5 Built Right Con… | #6 PBX Corporation | #7 LOGOS CONSTRUCT… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 72 | CY | $28.00 | $36.00 | $115.00 | $11.00 | $25.00 | $45.00 | $93.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 8 | CY | $470.00 | $1,155.00 | $750.00 | $3,091.00 | $400.00 | $1,800.00 | $670.00 |
| 30 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 110 | TON | $115.00 | $98.00 | $150.00 | $240.00 | $270.00 | $160.00 | $200.00 |
| 40 | 601(C)1310 | TYPE I-A FILTER BLANKET | 30 | TON | $90.00 | $89.00 | $125.00 | $96.70 | $160.00 | $130.00 | $195.00 |
| 50 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $1,000.00 | $5,850.00 | $8,250.00 | $10,055.00 | $10,000.00 | $8,000.00 | $2,500.00 |
| 60 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 77 | CY | $28.00 | $33.80 | $75.00 | $11.00 | $25.00 | $55.00 | $93.00 |
| 70 | 501(G)1800 | CLSM BACKFILL | 1 | CY | $650.00 | $3,750.00 | $750.00 | $4,814.00 | $400.00 | $4,000.00 | $670.00 |
| 80 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 120 | TON | $115.00 | $98.00 | $125.00 | $130.50 | $220.00 | $165.00 | $200.00 |
| 90 | 601(C)1310 | TYPE I-A FILTER BLANKET | 30 | TON | $90.00 | $93.00 | $100.00 | $107.50 | $160.00 | $145.00 | $195.00 |
| 100 | 619(B)6488 | REMOVAL OF EXISTING RIPRAP | 1 | LSUM | $12,500.00 | $5,850.00 | $2,500.00 | $9,141.00 | $5,000.00 | $5,000.00 | $14,000.00 |
| 110 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 84 | CY | $28.00 | $34.50 | $100.00 | $11.00 | $25.00 | $85.00 | $93.00 |
| 120 | 501(G)1800 | CLSM BACKFILL | 23 | CY | $390.00 | $758.00 | $750.00 | $673.00 | $400.00 | $1,400.00 | $670.00 |
| 130 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 130 | TON | $110.00 | $98.00 | $125.00 | $130.50 | $220.00 | $210.00 | $200.00 |
| 140 | 601(C)1310 | TYPE I-A FILTER BLANKET | 30 | TON | $90.00 | $86.00 | $100.00 | $107.50 | $160.00 | $160.00 | $195.00 |
| 150 | 613(Z)8400 | DEWATERING | 7 | DAY | $800.00 | $617.50 | $1,200.00 | $3,283.00 | $500.00 | $1,800.00 | $1,500.00 |
| 160 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 379 | CY | $22.00 | $27.05 | $75.00 | $11.00 | $25.00 | $45.00 | $25.00 |
| 170 | 501(G)1800 | CLSM BACKFILL | 25 | CY | $390.00 | $755.00 | $550.00 | $585.50 | $400.00 | $1,200.00 | $670.00 |
| 180 | 535 7100 | CORROSION INHIBITOR(SURFACE APPLIED) | 4 | SY | $50.00 | $447.50 | $100.00 | $290.00 | $60.00 | $95.00 | $69.46 |
| 190 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 570 | TON | $80.00 | $89.60 | $85.00 | $119.50 | $220.00 | $150.00 | $200.00 |
| 200 | 601(C)1310 | TYPE I-A FILTER BLANKET | 140 | TON | $68.00 | $79.00 | $55.00 | $96.70 | $160.00 | $125.00 | $195.00 |
| 210 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 199 | CY | $23.00 | $31.08 | $100.00 | $11.00 | $25.00 | $45.00 | $93.00 |
| 220 | 501(G)1800 | CLSM BACKFILL | 31 | CY | $370.00 | $683.00 | $550.00 | $366.00 | $400.00 | $1,000.00 | $670.00 |
| 230 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 300 | TON | $90.00 | $99.50 | $85.00 | $130.50 | $220.00 | $160.00 | $200.00 |
| 240 | 601(C)1310 | TYPE I-A FILTER BLANKET | 80 | TON | $80.00 | $86.00 | $55.00 | $107.50 | $160.00 | $100.00 | $195.00 |
| 250 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $7,000.00 | $8,500.00 | $10,000.00 | $18,628.50 | $7,500.00 | $9,600.00 | $10,572.15 |
| 260 | 641 2100 | MOBILIZATION | 1 | LSUM | $22,500.00 | $27,750.00 | $30,000.00 | $37,500.00 | $30,000.00 | $49,187.45 | $49,000.00 |