Bridge Repair
- Let date
- Thursday, November 13, 2025
- Contract
- 250251 · job page
- J/P numbers
- 38340(04)
- District
- Division 5
- County
- Blaine, Garfield, Kingfisher, Logan
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: AT MULTIPLE LOCATIONS IN DISTRICT IV AND DISTRICT V.
- Classification
- Bridge Repair
- Project number
- BRO-224F(114)CB
- Working days
- 105
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $468,271 | ||
| 1 | Redlands Contracting, LLC Low bidder | $508,302 | +8.5% | |
| 2 | K & R BUILDERS, INC. | $589,229 | +25.8% | +15.9% |
| 3 | Wyatt Contracting | $639,260 | +36.5% | +25.8% |
| 4 | Haskell Lemon Group, LLC | $713,136 | +52.3% | +40.3% |
| 5 | Built Right Construction, LLC | $853,685 | +82.3% | +67.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Redlands Contra… | #2 K & R BUILDERS,… | #3 Wyatt Contracti… | #4 Haskell Lemon G… | #5 Built Right Con… |
|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $1,500.00 | $2,500.00 | $9,300.00 | $6,925.00 | $12,010.00 | $10,000.00 |
| 20 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 67 | CY | $30.00 | $18.00 | $30.00 | $100.00 | $34.30 | $20.00 |
| 30 | 501(G)1800 | CLSM BACKFILL | 3 | CY | $575.00 | $450.00 | $1,240.00 | $750.00 | $986.50 | $400.00 |
| 40 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 100 | TON | $110.00 | $125.00 | $118.00 | $175.00 | $116.50 | $220.00 |
| 50 | 601(C)1310 | TYPE I-A FILTER BLANKET | 25 | TON | $95.00 | $120.00 | $110.00 | $150.00 | $94.50 | $185.00 |
| 60 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 26 | CY | $38.00 | $18.00 | $60.00 | $125.00 | $132.50 | $20.00 |
| 70 | 501(G)1800 | CLSM BACKFILL | 2 | CY | $575.00 | $450.00 | $2,240.00 | $750.00 | $795.00 | $400.00 |
| 80 | 540 8100 | (PL)REPAIR BRIDGE ITEMS | 1 | LSUM | $15,000.00 | $5,000.00 | $20,000.00 | $10,000.00 | $27,935.00 | $13,000.00 |
| 90 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 40 | TON | $120.00 | $125.00 | $133.00 | $250.00 | $134.00 | $220.00 |
| 100 | 601(C)1310 | TYPE I-A FILTER BLANKET | 10 | TON | $115.00 | $120.00 | $177.00 | $200.00 | $161.50 | $185.00 |
| 110 | 613(Z)8400 | DEWATERING | 7 | DAY | $800.00 | $1,500.00 | $530.00 | $1,200.00 | $1,313.00 | $500.00 |
| 120 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $6,000.00 | $2,500.00 | $8,800.00 | $11,500.00 | $12,590.00 | $10,000.00 |
| 130 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 31 | CY | $36.00 | $18.00 | $30.00 | $100.00 | $95.40 | $20.00 |
| 140 | 501(G)1800 | CLSM BACKFILL | 3 | CY | $575.00 | $450.00 | $1,240.00 | $750.00 | $549.00 | $400.00 |
| 150 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 50 | TON | $120.00 | $125.00 | $140.00 | $175.00 | $144.00 | $220.00 |
| 160 | 601(C)1310 | TYPE I-A FILTER BLANKET | 15 | TON | $105.00 | $120.00 | $127.00 | $150.00 | $128.50 | $185.00 |
| 170 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 45 | CY | $33.00 | $18.00 | $250.00 | $105.00 | $76.60 | $20.00 |
| 180 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $515.00 | $450.00 | $1,140.00 | $750.00 | $508.00 | $400.00 |
| 190 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 70 | TON | $115.00 | $125.00 | $126.00 | $250.00 | $127.00 | $220.00 |
| 200 | 601(C)1310 | TYPE I-A FILTER BLANKET | 20 | TON | $100.00 | $120.00 | $108.00 | $200.00 | $112.00 | $185.00 |
| 210 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $7,500.00 | $2,500.00 | $16,500.00 | $9,250.00 | $14,065.00 | $10,000.00 |
| 220 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 35 | CY | $35.00 | $18.00 | $40.00 | $100.00 | $98.50 | $30.00 |
| 230 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $515.00 | $450.00 | $1,140.00 | $750.00 | $508.00 | $450.00 |
| 240 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 60 | TON | $115.00 | $125.00 | $129.00 | $175.00 | $134.00 | $245.00 |
| 250 | 601(C)1310 | TYPE I-A FILTER BLANKET | 15 | TON | $105.00 | $120.00 | $160.00 | $150.00 | $128.50 | $185.00 |
| 260 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 417 | CY | $20.00 | $18.00 | $20.00 | $40.00 | $37.80 | $30.00 |
| 270 | 501(G)1800 | CLSM BACKFILL | 8 | CY | $470.00 | $450.00 | $890.00 | $750.00 | $713.50 | $400.00 |
| 280 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 620 | TON | $78.00 | $125.00 | $94.00 | $85.00 | $108.00 | $245.00 |
| 290 | 601(C)1310 | TYPE I-A FILTER BLANKET | 140 | TON | $68.00 | $120.00 | $80.00 | $55.00 | $91.10 | $185.00 |
| 300 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 215 | CY | $25.00 | $18.00 | $22.50 | $100.00 | $64.10 | $30.00 |
| 310 | 509(A)0210 | CLASS AA CONCRETE | 70 | CY | $1,125.00 | $950.00 | $935.00 | $710.00 | $1,201.00 | $1,200.00 |
| 320 | 511(A)2210 | REINFORCING STEEL | 5,560 | LB | $1.70 | $2.50 | $2.65 | $1.50 | $3.35 | $3.00 |
| 330 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 320 | TON | $90.00 | $125.00 | $109.00 | $100.00 | $134.00 | $245.00 |
| 340 | 601(C)1310 | TYPE I-A FILTER BLANKET | 80 | TON | $80.00 | $120.00 | $86.00 | $75.00 | $112.00 | $185.00 |
| 350 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $2,500.00 | $2,500.00 | $7,000.00 | $6,500.00 | $15,245.00 | $15,000.00 |
| 360 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 62 | CY | $30.00 | $18.00 | $31.00 | $100.00 | $53.20 | $30.00 |
| 370 | 501(G)1800 | CLSM BACKFILL | 5 | CY | $515.00 | $450.00 | $1,140.00 | $750.00 | $550.50 | $450.00 |
| 380 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 100 | TON | $110.00 | $125.00 | $112.00 | $175.00 | $117.50 | $245.00 |
| 390 | 601(C)1310 | TYPE I-A FILTER BLANKET | 25 | TON | $95.00 | $120.00 | $89.00 | $150.00 | $95.70 | $185.00 |
| 400 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $500.00 | $2,500.00 | $7,000.00 | $6,000.00 | $14,010.00 | $15,000.00 |
| 410 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 49 | CY | $33.00 | $18.00 | $30.00 | $100.00 | $50.50 | $30.00 |
| 420 | 501(G)1800 | CLSM BACKFILL | 3 | CY | $575.00 | $450.00 | $1,490.00 | $750.00 | $495.50 | $450.00 |
| 430 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 80 | TON | $115.00 | $125.00 | $102.50 | $175.00 | $115.50 | $245.00 |
| 440 | 601(C)1310 | TYPE I-A FILTER BLANKET | 15 | TON | $105.00 | $120.00 | $115.00 | $150.00 | $117.50 | $185.00 |
| 450 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $750.00 | $2,500.00 | $7,000.00 | $3,000.00 | $19,075.00 | $15,000.00 |
| 460 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 110 | CY | $27.00 | $18.00 | $35.00 | $50.00 | $41.80 | $30.00 |
| 470 | 501(G)1800 | CLSM BACKFILL | 24 | CY | $390.00 | $450.00 | $590.00 | $500.00 | $412.00 | $400.00 |
| 480 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 170 | TON | $100.00 | $125.00 | $113.00 | $125.00 | $120.00 | $245.00 |
| 490 | 601(C)1310 | TYPE I-A FILTER BLANKET | 40 | TON | $85.00 | $120.00 | $90.00 | $100.00 | $112.00 | $185.00 |
| 500 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 18 | CY | $40.00 | $18.00 | $55.00 | $215.00 | $191.50 | $30.00 |
| 510 | 501(G)1800 | CLSM BACKFILL | 3 | CY | $575.00 | $450.00 | $1,490.00 | $1,000.00 | $986.50 | $450.00 |
| 520 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 30 | TON | $125.00 | $125.00 | $113.00 | $500.00 | $150.50 | $245.00 |
| 530 | 601(C)1310 | TYPE I-A FILTER BLANKET | 10 | TON | $115.00 | $120.00 | $172.00 | $450.00 | $161.50 | $185.00 |
| 540 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 26 | CY | $38.00 | $18.00 | $60.00 | $125.00 | $132.50 | $30.00 |
| 550 | 501(G)1800 | CLSM BACKFILL | 26 | CY | $370.00 | $450.00 | $640.00 | $600.00 | $485.50 | $400.00 |
| 560 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 40 | TON | $120.00 | $125.00 | $126.00 | $250.00 | $159.00 | $245.00 |
| 570 | 601(C)1310 | TYPE I-A FILTER BLANKET | 10 | TON | $115.00 | $120.00 | $188.00 | $200.00 | $161.50 | $185.00 |
| 580 | 613(Z)8400 | DEWATERING | 7 | DAY | $800.00 | $1,500.00 | $530.00 | $1,200.00 | $2,627.00 | $500.00 |
| 590 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 38 | CY | $35.00 | $18.00 | $40.00 | $115.00 | $90.70 | $30.00 |
| 600 | 501(G)1800 | CLSM BACKFILL | 13 | CY | $435.00 | $450.00 | $740.00 | $650.00 | $574.00 | $400.00 |
| 610 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 60 | TON | $115.00 | $125.00 | $120.00 | $250.00 | $134.00 | $245.00 |
| 620 | 601(C)1310 | TYPE I-A FILTER BLANKET | 10 | TON | $115.00 | $120.00 | $187.00 | $200.00 | $161.50 | $185.00 |
| 630 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $15,000.00 | $15,000.00 | $21,000.00 | $17,500.00 | $31,739.75 | $9,000.00 |
| 640 | 641 2100 | MOBILIZATION | 1 | LSUM | $45,000.00 | $40,000.00 | $50,000.00 | $55,000.00 | $60,650.00 | $80,000.00 |