Bridge Repair
- Let date
- Thursday, September 11, 2025
- Contract
- 250223 · job page
- J/P numbers
- 38214(04)
- District
- Division 6
- County
- Alfalfa, Woods, Woodward
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER EAGLE CHIEF CREEK AND UNNAMED CREEKS, AT MULTIPLE LOCATIONS IN DISTRICT VI.
- Classification
- Bridge Repair
- Project number
- BRO-202F(092)CB
- Working days
- 105
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $592,071 | ||
| 1 | K & R BUILDERS, INC. Low bidder | $517,974 | -12.5% | |
| 2 | Haskell Lemon Group, LLC | $589,460 | -0.4% | +13.8% |
| 3 | Wyatt Contracting | $670,000 | +13.2% | +29.4% |
| 4 | B & B CONSTRUCTION SERVICE J.T., INC. | $721,055 | +21.8% | +39.2% |
| 5 | Built Right Construction, LLC | $796,675 | +34.6% | +53.8% |
| 6 | LOGOS CONSTRUCTION CO., LLC | $887,959 | +50.0% | +71.4% |
| 7 | PBX Corporation | $923,465 | +56.0% | +78.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K & R BUILDERS,… | #2 Haskell Lemon G… | #3 Wyatt Contracti… | #4 B & B CONSTRUCT… | #5 Built Right Con… | #6 LOGOS CONSTRUCT… | #7 PBX Corporation |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 185 | CY | $30.00 | $15.00 | $23.51 | $50.00 | $50.00 | $30.00 | $177.00 | $58.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 77 | CY | $300.00 | $300.00 | $281.69 | $400.00 | $475.00 | $600.00 | $475.00 | $500.00 |
| 30 | 509(A)0210 | CLASS AA CONCRETE | 80 | CY | $1,100.00 | $855.00 | $743.03 | $940.00 | $825.00 | $1,000.00 | $1,423.00 | $1,200.00 |
| 40 | 511(A)2210 | REINFORCING STEEL | 2,413 | LB | $1.85 | $2.25 | $3.46 | $1.50 | $4.00 | $5.00 | $3.00 | $3.00 |
| 50 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 110 | TON | $115.00 | $97.00 | $110.84 | $150.00 | $178.00 | $250.00 | $263.00 | $210.00 |
| 60 | 601(C)1310 | TYPE I-A FILTER BLANKET | 30 | TON | $100.00 | $73.50 | $87.90 | $100.00 | $156.00 | $300.00 | $218.00 | $150.00 |
| 70 | 613(Z)8400 | DEWATERING | 7 | DAY | $800.00 | $146.00 | $1,013.47 | $1,000.00 | $300.00 | $1,000.00 | $120.00 | $825.00 |
| 80 | 619(B)6304 | REMOVAL OF BRIDGE ITEMS | 1 | LSUM | $7,500.00 | $16,600.00 | $15,793.44 | $10,000.00 | $5,000.00 | $7,500.00 | $7,500.00 | $5,000.00 |
| 90 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 51 | CY | $45.00 | $19.79 | $42.65 | $300.00 | $80.00 | $30.00 | $177.00 | $100.00 |
| 100 | 501(G)1800 | CLSM BACKFILL | 30 | CY | $370.00 | $350.00 | $309.57 | $500.00 | $500.00 | $600.00 | $475.00 | $990.00 |
| 110 | 509(A)0210 | CLASS AA CONCRETE | 20 | CY | $1,400.00 | $1,300.00 | $1,512.37 | $1,360.00 | $1,282.72 | $1,000.00 | $1,423.00 | $2,000.00 |
| 120 | 511(A)2210 | REINFORCING STEEL | 2,573 | LB | $1.85 | $2.45 | $3.30 | $2.00 | $4.50 | $5.00 | $3.00 | $3.00 |
| 130 | 613(Z)8400 | DEWATERING | 7 | DAY | $500.00 | $146.00 | $1,013.47 | $1,000.00 | $50.00 | $1,000.00 | $120.00 | $590.00 |
| 140 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 89 | CY | $45.00 | $17.25 | $48.88 | $190.00 | $100.00 | $30.00 | $177.00 | $75.00 |
| 150 | 501(G)1800 | CLSM BACKFILL | 56 | CY | $325.00 | $312.50 | $250.93 | $400.00 | $485.00 | $600.00 | $475.00 | $785.00 |
| 160 | 509(A)0210 | CLASS AA CONCRETE | 16 | CY | $1,400.00 | $1,400.00 | $1,435.44 | $1,335.00 | $1,500.00 | $1,000.00 | $1,423.00 | $2,300.00 |
| 170 | 511(A)2210 | REINFORCING STEEL | 3,971 | LB | $1.85 | $2.29 | $2.46 | $2.00 | $4.50 | $5.00 | $3.00 | $3.00 |
| 180 | 613(Z)8400 | DEWATERING | 7 | DAY | $500.00 | $146.00 | $1,013.47 | $1,000.00 | $50.00 | $1,000.00 | $120.00 | $590.00 |
| 190 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $7,500.00 | $9,400.00 | $15,793.44 | $10,000.00 | $5,850.00 | $15,000.00 | $7,200.00 | $10,000.00 |
| 200 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 160 | CY | $30.00 | $16.30 | $27.19 | $100.00 | $60.00 | $30.00 | $177.00 | $80.00 |
| 210 | 501(G)1800 | CLSM BACKFILL | 37 | CY | $350.00 | $325.00 | $285.68 | $400.00 | $500.00 | $600.00 | $475.00 | $900.00 |
| 220 | 509(A)0210 | CLASS AA CONCRETE | 10 | CY | $1,500.00 | $1,500.00 | $2,127.85 | $1,420.00 | $1,500.00 | $1,000.00 | $1,423.00 | $2,600.00 |
| 230 | 511(A)2210 | REINFORCING STEEL | 2,812 | LB | $1.85 | $2.45 | $3.10 | $2.00 | $4.00 | $5.00 | $3.00 | $3.00 |
| 240 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 50 | TON | $125.00 | $100.00 | $113.18 | $150.00 | $178.00 | $250.00 | $263.00 | $235.00 |
| 250 | 601(C)1310 | TYPE I-A FILTER BLANKET | 15 | TON | $120.00 | $84.00 | $87.90 | $100.00 | $156.00 | $250.00 | $218.00 | $200.00 |
| 260 | 613(Z)8400 | DEWATERING | 7 | DAY | $500.00 | $146.00 | $1,013.47 | $1,000.00 | $500.00 | $1,000.00 | $120.00 | $765.00 |
| 270 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $1,500.00 | $7,300.00 | $15,793.44 | $7,500.00 | $5,500.00 | $15,000.00 | $2,500.00 | $5,500.00 |
| 280 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 143 | CY | $35.00 | $16.50 | $30.42 | $75.00 | $100.00 | $30.00 | $177.00 | $63.00 |
| 290 | 501(G)1800 | CLSM BACKFILL | 124 | CY | $295.00 | $290.00 | $244.38 | $350.00 | $400.00 | $600.00 | $475.00 | $670.00 |
| 300 | 509(A)0210 | CLASS AA CONCRETE | 26 | CY | $1,345.00 | $1,250.00 | $991.59 | $975.00 | $1,500.00 | $1,000.00 | $1,423.00 | $2,100.00 |
| 310 | 511(A)2210 | REINFORCING STEEL | 4,503 | LB | $1.85 | $2.30 | $2.27 | $1.50 | $4.00 | $5.00 | $3.00 | $3.00 |
| 320 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 40 | TON | $140.00 | $100.00 | $119.61 | $150.00 | $178.00 | $250.00 | $263.00 | $245.00 |
| 330 | 601(C)1310 | TYPE I-A FILTER BLANKET | 10 | TON | $135.00 | $84.00 | $98.63 | $100.00 | $156.00 | $250.00 | $218.00 | $200.00 |
| 340 | 613(Z)8400 | DEWATERING | 7 | DAY | $800.00 | $437.50 | $1,013.47 | $1,000.00 | $1,000.00 | $1,000.00 | $120.00 | $880.00 |
| 350 | 202(A)2210 | UNCLASSIFIED EXCAVATION | 23 | CY | $65.00 | $44.00 | $94.57 | $100.00 | $200.00 | $30.00 | $177.00 | $118.00 |
| 360 | 506(A)7200 | STRUCTURAL STEEL | 1,680 | LB | $5.00 | $3.79 | $2.10 | $7.00 | $4.00 | $20.00 | $9.00 | $7.00 |
| 370 | 509(A)0210 | CLASS AA CONCRETE | 63 | CY | $1,100.00 | $1,075.00 | $769.90 | $1,050.00 | $1,371.71 | $1,000.00 | $1,423.00 | $1,600.00 |
| 380 | 511(A)2210 | REINFORCING STEEL | 1,307 | LB | $1.85 | $3.28 | $5.62 | $2.00 | $4.00 | $5.00 | $3.00 | $3.00 |
| 390 | 540 8100 | (PL)REPAIR BRIDGE ITEMS | 1 | LSUM | $5,000.00 | $3,600.00 | $11,532.97 | $5,000.00 | $4,000.00 | $7,500.00 | $7,350.00 | $3,000.00 |
| 400 | 540 8120 | (PL)REPAIR BRIDGE ITEM (TYPE A) | 8 | EA | $2,000.00 | $1,467.50 | $2,262.26 | $625.00 | $2,000.00 | $3,000.00 | $7,200.00 | $830.00 |
| 410 | 601(B)1230 | TYPE I-A PLAIN RIPRAP | 40 | TON | $140.00 | $102.50 | $119.61 | $150.00 | $178.00 | $250.00 | $263.00 | $190.00 |
| 420 | 601(C)1310 | TYPE I-A FILTER BLANKET | 10 | TON | $135.00 | $95.00 | $98.63 | $100.00 | $156.00 | $250.00 | $218.00 | $192.00 |
| 430 | 613(Z)8400 | DEWATERING | 7 | DAY | $800.00 | $146.00 | $1,013.47 | $1,000.00 | $300.00 | $1,000.00 | $120.00 | $425.00 |
| 440 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $14,000.00 | $6,000.00 | $14,444.56 | $20,695.00 | $5,500.00 | $7,500.00 | $11,150.00 | $12,000.00 |
| 450 | 641 2100 | MOBILIZATION | 1 | LSUM | $52,000.00 | $35,000.00 | $49,795.78 | $57,500.00 | $77,000.00 | $50,000.00 | $69,400.00 | $94,864.85 |