Bid tab 250218

Let Sep 11, 2025 · Division 3 · Garvin, Pottawatomie, Seminole Sign up free

‹ Sep 2025 results

Bridge Repair

Let date
Thursday, September 11, 2025
Contract
250218 · job page
J/P numbers
38239(04)
District
Division 3
County
Garvin, Pottawatomie, Seminole
Highway
COUNTY ROADS
Limits
COUNTY ROADS: AT MULTIPLE LOCATIONS IN DISTRICT III.
Classification
Bridge Repair
Project number
BRO-267F(119)CB
Working days
400

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$424,294
1 K & R BUILDERS, INC. Low bidder $564,472 +33.0%
2 PBX Corporation $749,549 +76.7% +32.8%
3 Haskell Lemon Group, LLC $887,370 +109.1% +57.2%
4 B & B CONSTRUCTION SERVICE J.T., INC. $1,008,860 +137.8% +78.7%
5 LOGOS CONSTRUCTION CO., LLC $1,052,395 +148.0% +86.4%
6 Built Right Construction, LLC $1,365,000 +221.7% +141.8%

Bid tab: unit prices 114 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 K & R BUILDERS,…#2 PBX Corporation#3 Haskell Lemon G…#4 B & B CONSTRUCT…#5 LOGOS CONSTRUCT…#6 Built Right Con…
10201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,500.00 $5,525.00 $3,000.00 $4,871.00 $4,200.00 $2,100.00 $10,000.00
20202(A)2210 UNCLASSIFIED EXCAVATION37CY $35.21 $19.90 $55.00 $22.00 $40.00 $131.00 $30.00
30501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $1,500.00 $3,629.00 $4,000.00 $460.00 $400.00
40502(B)3310 FALSEWORK AND JACKING1LSUM $3,000.00 $2,375.00 $725.00 $4,910.00 $5,000.00 $2,625.00 $7,500.00
50601(B)1230 TYPE I-A PLAIN RIPRAP57TON $85.78 $83.25 $160.00 $150.00 $175.00 $182.00 $250.00
60601(C)1310 TYPE I-A FILTER BLANKET9TON $63.64 $74.00 $215.00 $131.50 $155.00 $143.00 $150.00
70201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $3,000.00 $6,900.00 $2,500.00 $5,460.00 $5,700.00 $3,150.00 $10,000.00
80202(A)2210 UNCLASSIFIED EXCAVATION28CY $37.89 $20.13 $55.00 $22.00 $40.00 $131.00 $30.00
90501(G)1800 CLSM BACKFILL2CY $421.65 $1,400.00 $1,200.00 $2,576.00 $3,750.00 $460.00 $400.00
100502(B)3310 FALSEWORK AND JACKING1LSUM $3,000.00 $3,075.00 $725.00 $5,421.00 $5,000.00 $2,625.00 $7,500.00
110601(B)1230 TYPE I-A PLAIN RIPRAP58TON $85.62 $82.45 $160.00 $150.00 $175.00 $182.00 $250.00
120601(C)1310 TYPE I-A FILTER BLANKET12TON $62.24 $66.25 $170.00 $131.50 $155.00 $143.00 $150.00
130201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,000.00 $4,500.00 $2,500.00 $5,421.00 $8,000.00 $1,575.00 $10,000.00
140202(A)2210 UNCLASSIFIED EXCAVATION138CY $24.89 $16.50 $40.00 $22.00 $40.00 $131.00 $30.00
150501(G)1800 CLSM BACKFILL8CY $361.08 $600.00 $600.00 $884.50 $50.00 $460.00 $400.00
160502(B)3310 FALSEWORK AND JACKING1LSUM $2,500.00 $3,100.00 $1,000.00 $4,910.00 $7,000.00 $2,625.00 $7,500.00
170601(B)1230 TYPE I-A PLAIN RIPRAP207TON $74.17 $73.25 $135.00 $150.00 $150.00 $182.00 $250.00
180601(C)1310 TYPE I-A FILTER BLANKET29TON $58.14 $59.75 $150.00 $131.50 $130.00 $143.00 $150.00
190201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $2,000.00 $8,300.00 $2,300.00 $6,010.00 $6,300.00 $2,100.00 $10,000.00
200202(A)2210 UNCLASSIFIED EXCAVATION67CY $30.11 $19.28 $45.00 $22.00 $40.00 $131.00 $30.00
210501(G)1800 CLSM BACKFILL3CY $402.95 $850.00 $925.00 $2,077.00 $3,500.00 $460.00 $400.00
220502(B)3310 FALSEWORK AND JACKING1LSUM $4,000.00 $4,100.00 $725.00 $5,421.00 $5,000.00 $3,150.00 $7,500.00
230601(B)1230 TYPE I-A PLAIN RIPRAP140TON $77.51 $76.25 $135.00 $150.00 $175.00 $182.00 $250.00
240601(C)1310 TYPE I-A FILTER BLANKET28TON $58.30 $65.25 $135.00 $131.50 $155.00 $143.00 $150.00
250201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $2,500.00 $5,875.00 $2,300.00 $5,971.00 $5,700.00 $2,100.00 $10,000.00
260202(A)2210 UNCLASSIFIED EXCAVATION56CY $31.57 $19.63 $55.00 $22.00 $40.00 $131.00 $30.00
270501(G)1800 CLSM BACKFILL2CY $421.65 $1,250.00 $1,300.00 $2,026.00 $3,500.00 $460.00 $400.00
280502(B)3310 FALSEWORK AND JACKING1LSUM $2,000.00 $2,000.00 $1,000.00 $3,810.00 $4,000.00 $2,625.00 $7,500.00
290601(B)1230 TYPE I-A PLAIN RIPRAP133TON $77.96 $78.25 $150.00 $150.00 $175.00 $182.00 $250.00
300601(C)1310 TYPE I-A FILTER BLANKET27TON $58.47 $65.75 $160.00 $131.50 $155.00 $143.00 $150.00
310201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $2,000.00 $2,763.00 $4,300.00 $5,460.00 $5,700.00 $2,625.00 $10,000.00
320202(A)2210 UNCLASSIFIED EXCAVATION830CY $15.52 $10.66 $40.00 $16.50 $30.00 $131.00 $30.00
330501(G)1800 CLSM BACKFILL7CY $366.51 $625.00 $635.00 $826.50 $2,000.00 $460.00 $400.00
340502(B)3310 FALSEWORK AND JACKING1LSUM $2,000.00 $3,037.50 $3,000.00 $5,421.00 $7,000.00 $2,100.00 $7,500.00
350601(B)1230 TYPE I-A PLAIN RIPRAP1,094TON $61.47 $72.75 $125.00 $122.50 $145.00 $182.00 $250.00
360601(C)1310 TYPE I-A FILTER BLANKET183TON $50.44 $57.75 $95.00 $104.00 $125.00 $143.00 $150.00
370619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,000.00 $4,425.00 $1,000.00 $10,765.00 $4,000.00 $1,312.00 $10,000.00
380201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $4,000.00 $6,250.00 $1,500.00 $4,321.00 $4,000.00 $3,150.00 $10,000.00
390501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $1,500.00 $4,729.00 $4,000.00 $460.00 $400.00
400502(B)3310 FALSEWORK AND JACKING1LSUM $2,000.00 $2,362.50 $360.00 $4,360.00 $4,500.00 $1,312.00 $7,500.00
410601(B)1230 TYPE I-A PLAIN RIPRAP52TON $86.68 $90.75 $165.00 $150.00 $175.00 $182.00 $250.00
420201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,000.00 $3,075.00 $2,000.00 $3,260.00 $3,250.00 $1,575.00 $10,000.00
430202(A)2210 UNCLASSIFIED EXCAVATION43CY $33.85 $20.50 $55.00 $22.00 $40.00 $131.00 $30.00
440501(G)1800 CLSM BACKFILL5CY $380.57 $700.00 $725.00 $959.00 $2,500.00 $460.00 $400.00
450502(B)3310 FALSEWORK AND JACKING1LSUM $3,000.00 $2,362.50 $725.00 $3,810.00 $5,500.00 $2,625.00 $7,500.00
460601(B)1230 TYPE I-A PLAIN RIPRAP65TON $84.52 $78.25 $155.00 $150.00 $175.00 $182.00 $250.00
470601(C)1310 TYPE I-A FILTER BLANKET10TON $63.13 $67.25 $200.00 $131.50 $155.00 $143.00 $150.00
480202(A)2210 UNCLASSIFIED EXCAVATION79CY $28.83 $17.50 $50.00 $22.00 $40.00 $131.00 $30.00
490501(G)1800 CLSM BACKFILL5CY $380.57 $725.00 $825.00 $1,415.00 $3,000.00 $460.00 $400.00
500502(B)3310 FALSEWORK AND JACKING1LSUM $3,000.00 $3,337.50 $950.00 $5,421.00 $5,000.00 $3,950.00 $7,500.00
510601(B)1230 TYPE I-A PLAIN RIPRAP119TON $78.95 $79.75 $145.00 $150.00 $175.00 $182.00 $250.00
520601(C)1310 TYPE I-A FILTER BLANKET18TON $60.33 $68.25 $156.00 $131.50 $155.00 $143.00 $150.00
530619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,000.00 $2,660.00 $1,500.00 $3,221.00 $3,000.00 $1,312.00 $10,000.00
540202(A)2210 UNCLASSIFIED EXCAVATION25CY $38.26 $30.50 $48.00 $22.00 $40.00 $131.00 $30.00
550501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $1,300.00 $4,729.00 $4,000.00 $460.00 $400.00
560502(B)3310 FALSEWORK AND JACKING1LSUM $2,500.00 $1,325.00 $325.00 $1,610.00 $1,500.00 $3,950.00 $7,500.00
570601(B)1230 TYPE I-A PLAIN RIPRAP87TON $81.79 $86.75 $153.00 $150.00 $175.00 $182.00 $250.00
580601(C)1310 TYPE I-A FILTER BLANKET11TON $62.66 $68.25 $208.00 $131.50 $155.00 $143.00 $150.00
590201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,500.00 $3,081.00 $1,800.00 $4,321.00 $4,000.00 $2,100.00 $10,000.00
600202(A)2210 UNCLASSIFIED EXCAVATION45CY $33.44 $24.75 $43.00 $22.00 $40.00 $131.00 $30.00
610501(G)1800 CLSM BACKFILL3CY $402.95 $800.00 $790.00 $1,710.00 $3,000.00 $460.00 $400.00
620502(B)3310 FALSEWORK AND JACKING1LSUM $1,000.00 $1,675.00 $630.00 $2,671.00 $2,200.00 $1,312.00 $7,500.00
630601(B)1230 TYPE I-A PLAIN RIPRAP80TON $82.57 $77.75 $162.00 $150.00 $175.00 $182.00 $250.00
640601(C)1310 TYPE I-A FILTER BLANKET16TON $60.88 $68.75 $157.00 $131.50 $155.00 $143.00 $150.00
650619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,000.00 $2,487.50 $1,200.00 $3,260.00 $3,250.00 $1,312.00 $10,000.00
660201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $3,000.00 $7,250.00 $4,000.00 $6,010.00 $6,500.00 $2,100.00 $10,000.00
670501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $1,800.00 $5,383.00 $3,500.00 $460.00 $400.00
680502(B)3310 FALSEWORK AND JACKING1LSUM $1,500.00 $975.00 $630.00 $3,221.00 $2,850.00 $2,625.00 $7,500.00
690601(B)1230 TYPE I-A PLAIN RIPRAP53TON $86.49 $109.75 $183.00 $150.00 $175.00 $182.00 $250.00
700201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,000.00 $4,487.50 $3,800.00 $3,771.00 $3,500.00 $2,100.00 $10,000.00
710501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $1,800.00 $4,729.00 $4,000.00 $460.00 $400.00
720502(B)3310 FALSEWORK AND JACKING1LSUM $2,000.00 $2,012.50 $630.00 $5,421.00 $5,250.00 $2,625.00 $7,500.00
730601(B)1230 TYPE I-A PLAIN RIPRAP53TON $86.49 $94.75 $156.00 $150.00 $175.00 $182.00 $250.00
740501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $3,000.00 $5,383.00 $4,000.00 $460.00 $400.00
750502(B)3310 FALSEWORK AND JACKING1LSUM $2,000.00 $2,700.00 $630.00 $1,610.00 $1,500.00 $3,950.00 $7,500.00
760601(B)1230 TYPE I-A PLAIN RIPRAP67TON $84.23 $92.75 $175.00 $150.00 $175.00 $182.00 $250.00
770202(A)2210 UNCLASSIFIED EXCAVATION39CY $34.73 $22.88 $68.00 $22.00 $40.00 $131.00 $30.00
780501(G)1800 CLSM BACKFILL2CY $421.65 $1,250.00 $1,100.00 $2,903.00 $3,000.00 $460.00 $400.00
790502(B)3310 FALSEWORK AND JACKING1LSUM $2,000.00 $2,012.50 $950.00 $1,060.00 $1,000.00 $3,950.00 $7,500.00
800601(B)1230 TYPE I-A PLAIN RIPRAP76TON $83.04 $80.75 $160.00 $150.00 $175.00 $182.00 $250.00
810601(C)1310 TYPE I-A FILTER BLANKET12TON $62.24 $71.75 $233.00 $131.50 $155.00 $143.00 $150.00
820619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,000.00 $3,887.50 $2,600.00 $4,321.00 $4,000.00 $2,100.00 $10,000.00
830201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,500.00 $2,775.00 $1,400.00 $3,771.00 $3,250.00 $1,575.00 $10,000.00
840202(A)2210 UNCLASSIFIED EXCAVATION24CY $38.26 $26.15 $80.00 $22.00 $40.00 $131.00 $30.00
850501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $2,000.00 $5,383.00 $4,000.00 $460.00 $400.00
860502(B)3310 FALSEWORK AND JACKING1LSUM $2,500.00 $2,012.50 $1,200.00 $2,710.00 $3,000.00 $3,950.00 $7,500.00
870601(B)1230 TYPE I-A PLAIN RIPRAP382TON $69.21 $77.50 $136.00 $128.00 $150.00 $182.00 $250.00
880601(C)1310 TYPE I-A FILTER BLANKET15TON $61.18 $65.00 $193.00 $131.50 $155.00 $143.00 $150.00
890201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,000.00 $3,462.50 $951.00 $2,160.00 $2,250.00 $2,625.00 $10,000.00
900202(A)2210 UNCLASSIFIED EXCAVATION39CY $34.73 $23.38 $36.00 $22.00 $40.00 $131.00 $30.00
910501(G)1800 CLSM BACKFILL4CY $390.19 $700.00 $750.00 $1,663.00 $3,000.00 $460.00 $400.00
920502(B)3310 FALSEWORK AND JACKING1LSUM $1,000.00 $1,675.00 $630.00 $2,710.00 $3,000.00 $2,625.00 $7,500.00
930601(B)1230 TYPE I-A PLAIN RIPRAP93TON $81.17 $82.00 $138.00 $150.00 $175.00 $182.00 $250.00
940601(C)1310 TYPE I-A FILTER BLANKET19TON $60.07 $70.00 $125.00 $131.50 $155.00 $143.00 $150.00
950619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $2,000.00 $4,825.00 $1,200.00 $4,321.00 $4,000.00 $2,100.00 $10,000.00
960201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,500.00 $4,500.00 $1,000.00 $3,771.00 $3,250.00 $2,625.00 $10,000.00
970501(G)1800 CLSM BACKFILL1CY $455.65 $2,500.00 $1,100.00 $3,629.00 $4,000.00 $460.00 $400.00
980502(B)3310 FALSEWORK AND JACKING1LSUM $1,000.00 $1,460.00 $325.00 $2,710.00 $3,000.00 $2,625.00 $7,500.00
990601(B)1230 TYPE I-A PLAIN RIPRAP115TON $79.25 $84.00 $130.00 $150.00 $175.00 $182.00 $250.00
1,000601(C)1310 TYPE I-A FILTER BLANKET23TON $59.19 $70.00 $100.00 $131.50 $155.00 $143.00 $150.00
1,010619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,500.00 $4,825.00 $725.00 $2,710.00 $3,000.00 $1,312.00 $10,000.00
1,020201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,000.00 $2,775.00 $3,000.00 $4,360.00 $4,500.00 $1,575.00 $10,000.00
1,030202(A)2210 UNCLASSIFIED EXCAVATION50CY $32.53 $24.80 $58.00 $22.00 $40.00 $131.00 $30.00
1,040501(G)1800 CLSM BACKFILL2CY $421.65 $1,250.00 $1,200.00 $2,026.00 $3,000.00 $460.00 $400.00
1,050502(B)3310 FALSEWORK AND JACKING1LSUM $1,000.00 $1,525.00 $950.00 $3,771.00 $3,500.00 $2,625.00 $7,500.00
1,060601(B)1230 TYPE I-A PLAIN RIPRAP126TON $78.44 $81.50 $136.00 $150.00 $175.00 $182.00 $250.00
1,070601(C)1310 TYPE I-A FILTER BLANKET22TON $59.40 $70.00 $105.00 $131.50 $155.00 $143.00 $150.00
1,080201 1100 (PL)REMOVE DRIFT AND SILT1LSUM $1,000.00 $4,500.00 $950.00 $3,771.00 $3,250.00 $2,100.00 $10,000.00
1,090501(G)1800 CLSM BACKFILL5CY $380.57 $750.00 $590.00 $1,415.00 $3,000.00 $460.00 $400.00
1,100502(B)3310 FALSEWORK AND JACKING1LSUM $2,500.00 $1,525.00 $325.00 $3,810.00 $5,500.00 $2,625.00 $7,500.00
1,110601(B)1230 TYPE I-A PLAIN RIPRAP5TON $104.40 $260.00 $481.00 $150.00 $175.00 $182.00 $250.00
1,120619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $1,000.00 $3,462.50 $725.00 $4,281.00 $3,500.00 $2,100.00 $10,000.00
1,200880(J)7110 CONSTRUCTION TRAFFIC CONTROL1LSUM $21,000.00 $19,000.00 $12,000.00 $29,883.95 $8,000.00 $29,950.00 $12,000.00
1,210641 2100 MOBILIZATION1LSUM $21,000.00 $50,000.00 $75,107.70 $69,350.00 $75,000.00 $77,617.00 $75,000.00