| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$80,000.00 |
$83,000.00 |
$690,036.00 |
$103,331.19 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 108,381 | CY |
$12.00 |
$10.75 |
$19.07 |
$30.15 |
| 30 | 202(D)2500 |
UNCLASSIFIED BORROW | 2,500 | CY |
$15.00 |
$17.82 |
$25.34 |
$41.38 |
| 40 | 202(F)2700 |
EMBANKMENTS | 27,889 | CY |
$10.00 |
$17.82 |
$32.12 |
$41.67 |
| 50 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$50,000.00 |
$42,891.45 |
$256,919.28 |
$155,270.99 |
| 60 | 221(B)2300 |
TEMPORARY SILT FENCE | 15,040 | LF |
$3.50 |
$2.65 |
$3.50 |
$2.83 |
| 70 | 221(G)2800 |
TEMPORARY FIBER LOG | 238 | LF |
$10.00 |
$6.34 |
$7.08 |
$6.76 |
| 80 | 221(M)3400 |
TEMPORARY ENVIRONMENTAL FENCE | 4,048 | LF |
$20.00 |
$12.68 |
$5.89 |
$5.63 |
| 90 | 230(A)7200 |
SOLID SLAB SODDING | 29,360 | SY |
$3.00 |
$2.92 |
$3.26 |
$3.11 |
| 100 | 242 4101 |
STABILIZED CONSTRUCTION EXIT | 8 | EA |
$5,000.00 |
$6,000.00 |
$6,525.82 |
$7,735.03 |
| 110 | 307(K)4200 |
STABILIZED SUBGRADE | 7,937 | SY |
$12.00 |
$9.46 |
$7.58 |
$10.37 |
| 120 | 326(C)1100 |
(SP) WOVEN GEOSYNTHETIC REINFORCEMENT FABRIC | 29,360 | SY |
$2.50 |
$3.62 |
$6.54 |
$5.51 |
| 130 | 402(D)2500 |
TRAFFIC BOUND SURFACE COURSE TYPE D | 180,101 | TON |
$32.00 |
$28.00 |
$15.99 |
$41.75 |
| 140 | 408 8100 |
PRIME COAT | 2,778 | GAL |
$4.50 |
$6.00 |
$0.5900 |
$11.46 |
| 145 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 253 | TON |
$250.00 |
$269.45 |
$152.08 |
$349.70 |
| 150 | 414(A)5200 |
P.C.CONCRETE PAVEMENT(PLACEMENT) | 8,054 | SY |
$34.00 |
$40.00 |
$33.30 |
$57.89 |
| 160 | 414(G)5800 |
P.C. CONCRETE FOR PAVEMENT | 2,014 | CY |
$215.00 |
$194.63 |
$233.80 |
$279.09 |
| 170 | 509(A)0200 |
CLASS AA CONCRETE | 32 | CY |
$850.00 |
$532.50 |
$594.84 |
$852.56 |
| 180 | 509(B)0300 |
CLASS A CONCRETE | 63 | CY |
$850.00 |
$958.50 |
$1,540.42 |
$834.25 |
| 190 | 509(B)0310 |
CLASS A CONCRETE(LONG. BAR. DES. 1-A) | 39 | CY |
$600.00 |
$516.53 |
$851.70 |
$944.78 |
| 200 | 509(C)0400 |
CLASS A CONCRETE, SMALL STRUCTURES | 3 | CY |
$1,500.00 |
$1,917.00 |
$1,230.83 |
$2,141.99 |
| 210 | 511(A)2200 |
REINFORCING STEEL | 7,186 | LB |
$1.50 |
$0.6200 |
$1.07 |
$2.13 |
| 215 | 610(A)5200 |
4" CONCRETE SIDEWALK | 667 | SY |
$85.00 |
$93.72 |
$60.60 |
$89.99 |
| 220 | 610(C)5400 |
4" CONCRETE DIVIDING STRIP | 175 | SY |
$100.00 |
$83.07 |
$65.15 |
$98.61 |
| 230 | 611(G)0350 |
INLET (SMD-TYPE 1) | 1 | EA |
$6,400.00 |
$8,678.94 |
$3,821.61 |
$6,085.61 |
| 240 | 611(G)8150 |
INLET - LONG. BARRIER - TYPE I, DES. 1 | 1 | EA |
$6,000.00 |
$7,958.39 |
$3,070.52 |
$7,686.76 |
| 250 | 611(G)8170 |
INLET - LONG. BARRIER - TYPE II, DES. 1 | 1 | EA |
$8,000.00 |
$10,817.34 |
$6,234.31 |
$11,569.80 |
| 260 | 611(H)0656 |
ADD'L DEPTH IN INLET MED. BAR. TYPE I, DES. 1 | 1 | VF |
$500.00 |
$2,954.66 |
$555.70 |
$2,013.16 |
| 270 | 611(H)0660 |
ADD'L DEPTH IN INLET MED. BAR. TYPE II, DES. 1 | 5 | VF |
$700.00 |
$3,012.38 |
$555.70 |
$1,133.39 |
| 280 | 611(H)0980 |
ADD'L DEPTH IN INLET SMD TYPE 1 | 1 | VF |
$500.00 |
$3,185.60 |
$401.71 |
$1,894.34 |
| 290 | 613(B)5544 |
60" CORR. GALV. STEEL PIPE | 400 | LF |
$200.00 |
$148.47 |
$384.81 |
$247.97 |
| 300 | 613(E)5966 |
12” CORRUGATED HDPE SLOTTED DRAIN | 1,482 | LF |
$75.00 |
$210.65 |
$193.63 |
$307.88 |
| 310 | 616(P)4156 |
12" HDPE PIPE | 48 | LF |
$200.00 |
$256.56 |
$116.45 |
$1,036.03 |
| 320 | 619(A)6200 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$20,000.00 |
$25,000.00 |
$10,004.34 |
$45,492.67 |
| 330 | 619(B)6360 |
REMOVAL OF CONCRETE PAVEMENT | 784 | SY |
$21.00 |
$25.17 |
$23.18 |
$27.62 |
| 340 | 619(B)6364 |
REMOVAL OF ASPHALT PAVEMENT | 2,978 | SY |
$10.00 |
$17.91 |
$9.09 |
$18.39 |
| 350 | 619(B)6368 |
REMOVAL OF DRAINAGE INLETS | 4 | EA |
$1,000.00 |
$2,813.52 |
$605.25 |
$2,339.73 |
| 360 | 619(B)6396 |
REMOVAL OF GUARDRAIL | 438 | LF |
$8.00 |
$6.39 |
$5.35 |
$11.67 |
| 370 | 619(B)6416 |
REMOVAL OF CONCRETE MEDIAN BARRIER | 740 | LF |
$30.00 |
$25.43 |
$16.63 |
$31.20 |
| 380 | 619(B)6432 |
REMOVAL OF CABLE BARRIER | 1,819 | LF |
$25.00 |
$5.33 |
$8.86 |
$20.46 |
| 390 | 619(B)6460 |
REMOVAL OF 4" CONCRETE DIVIDING STRIP | 135 | SY |
$18.00 |
$22.81 |
$20.11 |
$45.43 |
| 400 | 619(C)6600 |
SAWING PAVEMENT | 3,401 | LF |
$5.00 |
$6.53 |
$2.58 |
$16.10 |
| 410 | 623(A)1200 |
BEAM GUARDRAIL W-BEAM SINGLE | 400 | LF |
$35.00 |
$37.28 |
$27.07 |
$31.76 |
| 420 | 623(G)1800 |
GUARDRAIL END TREATMENT (GET) | 1 | EA |
$3,750.00 |
$3,195.00 |
$3,687.98 |
$3,410.26 |
| 430 | 623(I)2050 |
GUARDRAIL BRIDGE CONN-THRIE BEAM (31") | 1 | EA |
$3,500.00 |
$3,195.00 |
$2,617.28 |
$3,666.03 |
| 440 | 627(A)6200 |
CONCRETE LONGITUDINAL BARRIER, DESIGN 1 | 118 | LF |
$125.00 |
$303.53 |
$188.44 |
$113.09 |
| 450 | 627(B)6300 |
CONCRETE LONGITUDINAL BARRIER END SEC. | 1 | EA |
$2,000.00 |
$3,727.50 |
$4,910.62 |
$1,696.42 |
| 460 | 205(A)6210 |
TYPE A-SALVAGED TOPSOIL | 760 | CY |
$10.00 |
$15.98 |
$216.93 |
$38.23 |
| 470 | 231 8100 |
PLANTS | 1 | LSUM |
$125,000.00 |
$133,125.00 |
$137,027.45 |
$95,760.90 |
| 480 | 233(D)0500 |
EXCELSIOR MAT | 3,560 | SY |
$35.00 |
$37.28 |
$29.47 |
$7.36 |
| 490 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 39 | CY |
$29.50 |
$68.37 |
$68.53 |
$27.96 |
| 500 | 501(G)1800 |
CLSM BACKFILL | 6 | CY |
$269.00 |
$391.52 |
$706.54 |
$381.41 |
| 510 | 503(A)4240 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 24,395.19 | LF |
$340.00 |
$280.00 |
$382.49 |
$425.79 |
| 520 | 504(A)5200 |
APPROACH SLAB | 684.1 | SY |
$305.00 |
$530.00 |
$307.99 |
$301.18 |
| 530 | 504(B)5300 |
SAW-CUT GROOVING | 25,926.9 | SY |
$5.58 |
$5.18 |
$5.71 |
$5.53 |
| 540 | 504(E)5520 |
42" F-SHAPED PARAPET | 10,083.8 | LF |
$114.00 |
$81.62 |
$114.25 |
$152.18 |
| 550 | 506(A)7200 |
STRUCTURAL STEEL | 117,500 | LB |
$3.19 |
$5.50 |
$8.74 |
$7.59 |
| 560 | 507(C)8400 |
ELASTOMERIC BEARING PADS | 484 | EA |
$1,000.00 |
$424.71 |
$779.71 |
$663.62 |
| 570 | 509(A)0210 |
CLASS AA CONCRETE | 7,385.3 | CY |
$950.00 |
$1,030.00 |
$1,263.67 |
$1,119.54 |
| 580 | 509(B)0320 |
CLASS A CONCRETE | 16.3 | CY |
$1,000.00 |
$2,800.00 |
$886.72 |
$1,986.82 |
| 590 | 509(D)0510 |
CLASS C CONCRETE | 24 | CY |
$550.00 |
$2,023.17 |
$1,055.29 |
$811.54 |
| 600 | 510(C)1450 |
SLOPE WALL (5") | 965 | SY |
$180.00 |
$119.28 |
$182.23 |
$322.35 |
| 610 | 511(A)2210 |
REINFORCING STEEL | 2,320 | LB |
$1.53 |
$1.13 |
$1.79 |
$2.21 |
| 620 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 1,777,570 | LB |
$1.70 |
$1.65 |
$1.88 |
$1.90 |
| 630 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 55,077 | SY |
$6.00 |
$5.40 |
$5.95 |
$5.76 |
| 640 | 517 9110 |
ELASTOMERIC COATING | 14,291 | SF |
$28.00 |
$16.51 |
$22.01 |
$20.77 |
| 650 | 518(B)0310 |
EXPANSION JOINT SYSTEM | 736.34 | LF |
$136.00 |
$97.98 |
$148.21 |
$142.87 |
| 660 | 520(A)1200 |
PREPARATION OF CRACKS, ABOVE WATER | 40 | LF |
$36.00 |
$37.28 |
$59.48 |
$34.61 |
| 670 | 520(C)1400 |
EPOXY RESIN, ABOVE WATER | 3.4 | GAL |
$123.00 |
$74.55 |
$53.54 |
$115.38 |
| 680 | 521(A)2200 |
PNEUMATICALLY PLACED MORTAR | 12 | SY |
$1,085.00 |
$692.25 |
$892.25 |
$1,153.80 |
| 690 | 523(A)3200 |
SEALER CRACK PREPARATION | 1,788 | LF |
$6.70 |
$5.40 |
$5.95 |
$5.76 |
| 700 | 523(B)3300 |
SEALER RESIN | 17.9 | GAL |
$224.00 |
$199.72 |
$220.08 |
$213.14 |
| 710 | 535 7100 |
CORROSION INHIBITOR(SURFACE APPLIED) | 12 | SY |
$45.50 |
$31.95 |
$59.48 |
$34.61 |
| 720 | 601(B)1230 |
TYPE I-A PLAIN RIPRAP | 529 | TON |
$65.00 |
$60.00 |
$63.18 |
$123.27 |
| 730 | 601(C)1310 |
TYPE I-A FILTER BLANKET | 168 | TON |
$49.00 |
$45.00 |
$70.92 |
$104.50 |
| 740 | 613(H)6205 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 123 | LF |
$33.45 |
$40.00 |
$38.03 |
$32.31 |
| 750 | 613(I)6310 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 50 | LF |
$38.30 |
$44.00 |
$45.33 |
$40.11 |
| 760 | 613(Q)7500 |
OUTLET LATERAL HEADWALL | 2 | EA |
$1,000.00 |
$1,244.88 |
$957.51 |
$1,553.14 |
| 770 | 619(B)6304 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$4,600,000.00 |
|
|
|
| 780 | 501(B)1300 |
SUBSTRUCTURE EXCAVATION COMMON | 39 | CY |
$29.50 |
$68.37 |
$68.53 |
$40.34 |
| 790 | 501(G)1800 |
CLSM BACKFILL | 6 | CY |
$269.00 |
$391.52 |
$706.54 |
$214.92 |
| 800 | 503(A)4240 |
PRESTRESSED CONCRETE BEAMS (TYPE IV) | 24,509.04 | LF |
$335.00 |
$280.00 |
$397.67 |
$425.50 |
| 810 | 504(A)5200 |
APPROACH SLAB | 576.8 | SY |
$305.00 |
$542.00 |
$328.16 |
$320.28 |
| 820 | 504(B)5300 |
SAW-CUT GROOVING | 25,868.3 | SY |
$5.58 |
$5.18 |
$5.71 |
$5.53 |
| 830 | 504(E)5520 |
42" F-SHAPED PARAPET | 10,048 | LF |
$114.00 |
$134.84 |
$117.13 |
$157.29 |
| 840 | 506(A)7200 |
STRUCTURAL STEEL | 117,500 | LB |
$3.19 |
$5.37 |
$8.77 |
$7.39 |
| 850 | 507(C)8400 |
ELASTOMERIC BEARING PADS | 484 | EA |
$1,000.00 |
$368.33 |
$847.06 |
$663.62 |
| 860 | 509(A)0210 |
CLASS AA CONCRETE | 7,369.8 | CY |
$950.00 |
$1,065.00 |
$1,324.54 |
$1,117.10 |
| 870 | 509(B)0320 |
CLASS A CONCRETE | 16.3 | CY |
$1,000.00 |
$2,800.00 |
$886.72 |
$1,918.21 |
| 880 | 510(C)1450 |
SLOPE WALL (5") | 678 | SY |
$180.00 |
$119.28 |
$199.88 |
$249.27 |
| 890 | 511(A)2210 |
REINFORCING STEEL | 2,320 | LB |
$1.53 |
$1.13 |
$1.79 |
$2.27 |
| 900 | 511(B)2310 |
EPOXY COATED REINFORCING STEEL | 1,752,700 | LB |
$1.70 |
$1.65 |
$1.89 |
$1.89 |
| 910 | 515(A)7200 |
WATER REPELLENT (VISUALLY INSPECTED) | 54,953 | SY |
$6.62 |
$5.40 |
$5.95 |
$5.76 |
| 920 | 517 9110 |
ELASTOMERIC COATING | 13,855 | SF |
$28.00 |
$16.51 |
$22.01 |
$20.77 |
| 930 | 518(B)0310 |
EXPANSION JOINT SYSTEM | 736.34 | LF |
$136.00 |
$97.98 |
$148.21 |
$142.90 |
| 940 | 520(A)1200 |
PREPARATION OF CRACKS, ABOVE WATER | 60 | LF |
$36.00 |
$37.28 |
$59.48 |
$34.61 |
| 950 | 520(C)1400 |
EPOXY RESIN, ABOVE WATER | 4.6 | GAL |
$123.00 |
$74.55 |
$53.54 |
$115.38 |
| 960 | 521(A)2200 |
PNEUMATICALLY PLACED MORTAR | 11 | SY |
$1,085.00 |
$692.25 |
$892.25 |
$1,153.80 |
| 970 | 523(A)3200 |
SEALER CRACK PREPARATION | 1,529 | LF |
$6.70 |
$5.40 |
$5.95 |
$5.76 |
| 980 | 523(B)3300 |
SEALER RESIN | 15.3 | GAL |
$224.00 |
$199.72 |
$220.08 |
$213.14 |
| 990 | 535 7100 |
CORROSION INHIBITOR(SURFACE APPLIED) | 11 | SY |
$45.50 |
$31.95 |
$59.48 |
$34.61 |
| 1,000 | 601(B)1230 |
TYPE I-A PLAIN RIPRAP | 584 | TON |
$65.00 |
$60.00 |
$63.14 |
$123.27 |
| 1,010 | 601(C)1310 |
TYPE I-A FILTER BLANKET | 186 | TON |
$49.00 |
$45.00 |
$72.81 |
$116.77 |
| 1,020 | 613(H)6205 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 105 | LF |
$33.45 |
$40.00 |
$40.18 |
$42.79 |
| 1,030 | 613(I)6310 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 80 | LF |
$38.30 |
$43.00 |
$42.04 |
$40.57 |
| 1,040 | 613(Q)7500 |
OUTLET LATERAL HEADWALL | 2 | EA |
$1,000.00 |
$1,244.88 |
$957.51 |
$1,928.92 |
| 1,050 | 619(B)6304 |
REMOVAL OF BRIDGE ITEMS | 1 | LSUM |
$4,600,000.00 |
|
|
|
| 1,060 | 624(E)3600 |
FENCE-STYLE CLF (4'HIGH, CLASS A) | 4,217 | LF |
$60.00 |
$40.47 |
$45.21 |
$43.20 |
| 1,070 | 804(A)2200 |
STRUCTURAL CONCRETE | 24 | CY |
$1,200.00 |
$1,863.75 |
$2,155.09 |
$1,599.18 |
| 1,080 | 804(B)2300 |
REINFORCING STEEL | 2,075 | LB |
$4.50 |
$10.65 |
$4.81 |
$3.17 |
| 1,090 | 805(D)3504 |
(PL)REMOVE & RESET LIGHT POLE | 7 | EA |
$5,000.00 |
$5,325.00 |
$6,340.10 |
$5,740.60 |
| 1,100 | 805(D)3532 |
(PL)REMOVE & RESET OVERHEAD SIGN STR. | 1 | EA |
$60,000.00 |
$21,300.00 |
$28,416.51 |
$48,434.82 |
| 1,110 | 850(A)1200 |
SHEET ALUMINUM SIGNS | 70 | SF |
$50.00 |
$47.93 |
$53.54 |
$86.67 |
| 1,120 | 853 5130 |
DELINEATORS(TYPE 1, CODE 1, FLEXIBLE) | 3 | EA |
$75.00 |
$53.25 |
$59.48 |
$86.67 |
| 1,130 | 856(A)8207 |
(SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE) | 39,903 | LF |
$1.25 |
$0.7500 |
$0.8300 |
$0.9600 |
| 1,140 | 628 7100 |
INSTALLATION OF CABLE BARRIER SYSTEM | 1,819 | LF |
$35.00 |
$26.63 |
$29.74 |
$19.32 |
| 1,150 | 628(C)7400 |
END ANCHORS | 3 | EA |
$12,000.00 |
$5,857.50 |
$6,543.19 |
$15,630.35 |
| 1,160 | 628(E)7600 |
CABLE BARRIER TENSION METER | 2 | EA |
$6,000.00 |
$4,792.50 |
$5,353.52 |
$5,456.41 |
| 1,170 | 870(A)1100 |
SAND FILLED IMPACT ATTEN.MODULE | 37 | EA |
$500.00 |
$452.63 |
$505.61 |
$442.61 |
| 1,180 | 870(C)1300 |
SAND FILLED IMPACT ATTEN.MODULE REMOVAL | 1 | LSUM |
$5,000.00 |
$532.50 |
$594.84 |
$4,449.18 |
| 1,190 | 857(C)9400 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 69,760 | LF |
$1.50 |
$0.4800 |
$0.5400 |
$1.65 |
| 1,200 | 871(B)2300 |
CONST.ZONE IMPACT ATTEN. | 1,220 | SD |
$20.00 |
$15.98 |
$17.85 |
$20.80 |
| 1,210 | 877(B)4300 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 9,131 | LF |
$30.00 |
$41.60 |
$36.90 |
$96.58 |
| 1,220 | 877(C)4400 |
RELOCATION OF PORT. LONGITUDINAL BARRIER | 17,056 | LF |
$5.00 |
$6.50 |
$3.96 |
$12.33 |
| 1,230 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 24,800 | SD |
$0.7500 |
$0.5300 |
$0.5900 |
$0.0200 |
| 1,240 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 9,680 | SD |
$1.00 |
$2.35 |
$2.38 |
$3.47 |
| 1,250 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 22,000 | SD |
$2.00 |
$2.35 |
$2.38 |
$0.1700 |
| 1,260 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 6,280 | SD |
$3.50 |
$1.75 |
$1.78 |
$6.93 |
| 1,270 | 880(E)6607 |
WARNING LIGHTS(TYPE B) | 15,960 | SD |
$0.7500 |
$0.5300 |
$0.5900 |
$2.31 |
| 1,280 | 880(F)6700 |
DRUMS | 75,285 | SD |
$0.5000 |
$0.3700 |
$0.4200 |
$0.2300 |
| 1,290 | 880(L)7310 |
(SP) TRAFFIC SURVEILLANCE, OHP (NON-BID) | 1,000 | HOUR |
$77.00 |
$77.00 |
$77.00 |
$77.00 |
| 1,300 | 882(A)8210 |
PORT.CHANGEABLE MESSAGE SIGN | 1,677 | SD |
$20.00 |
$26.63 |
$29.74 |
$11.56 |
| 1,310 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$50,000.00 |
$156,200.00 |
$228,630.91 |
$125,042.76 |
| 1,320 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$72,948.00 |
$5,948.35 |
$46,582.75 |
| 1,330 | 640(A)1200 |
FIELD OFFICE | 1 | EA |
$40,000.00 |
$25,000.00 |
$74,472.19 |
$65,171.95 |
| 1,340 | 641 2100 |
MOBILIZATION | 1 | LSUM |
$2,700,000.00 |
|
|
|