Bid tab 220103

Let Mar 17, 2022 · Division 4 · Payne Sign up free

‹ Mar 2022 results

BRIDGE AND APPROACHES COUNTY ROAD (EAST 86TH STREET): OVER STILLWATER CREEK, 0.9 MILES WEST OF SH -108 NEAR RIPLEY. PROJECT LENGTH = 0.402 MILE

Let date
Thursday, March 17, 2022
Contract
220103
J/P numbers
28724(04)
District
Division 4
County
Payne
Highway
Limits
BRIDGE AND APPROACHES COUNTY ROAD (EAST 86TH STREET): OVER STILLWATER CREEK, 0.9 MILES WEST OF SH -108 NEAR RIPLEY. PROJECT LENGTH = 0.402 MILE
Project number
STP-260D(073)CI

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,783,237
1 H & H BRIDGE COMPANY Low bidder $1,545,639 -13.3%
2 K & R BUILDERS, INC. $1,743,859 -2.2% +12.8%
3 Cowboy Contracting, Inc. $1,788,460 +0.3% +15.7%
4 Frontier Bridge, Inc. $1,907,346 +7.0% +23.4%
5 RRY SERVICES LLC $1,927,134 +8.1% +24.7%
6 HASKELL LEMON CONSTRUCTION CO. $1,969,061 +10.4% +27.4%
7 Central Bridge Company $2,074,996 +16.4% +34.2%
8 OBC, INC. $2,244,838 +25.9% +45.2%

Bid tab: unit prices 54 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 H & H BRIDGE CO…#2 K & R BUILDERS,…#3 Cowboy Contract…#4 Frontier Bridge…#5 RRY SERVICES LLC#6 HASKELL LEMON C…#7 Central Bridge …#8 OBC, INC.
10201(A)1200 CLEARING AND GRUBBING1LSUM $15,000.00 $7,500.00 $22,000.00 $8,500.00 $24,720.00 $50,000.00 $55,750.16 $20,000.00 $35,000.00
20202(A)2200 UNCLASSIFIED EXCAVATION17,237CY $10.00 $9.00 $9.00 $8.00 $10.56 $8.75 $7.72 $11.00 $10.92
30202(C)2400 ROCK EXCAVATION1,000CY $75.00 $15.00 $25.00 $15.00 $27.81 $40.00 $15.66 $65.00 $28.76
40210 0100 OBLITERATING ABANDONED ROAD1,152LF $25.00 $4.00 $7.00 $5.00 $9.27 $11.00 $6.16 $20.00 $20.00
50221(B)2300 TEMPORARY SILT FENCE1,400LF $2.50 $2.99 $3.30 $3.00 $3.08 $3.00 $3.29 $2.50 $3.18
60221(E)2600 TEMPORARY SILT DIKE364LF $15.00 $12.50 $13.75 $9.00 $12.88 $12.75 $13.77 $12.00 $13.31
70221(F)2710 TEMPORARY ROCK FILTER DAM TYPE 210CY $120.00 $250.00 $195.00 $100.00 $200.77 $375.00 $264.98 $120.00 $298.20
80230(A)7200 SOLID SLAB SODDING33,088SY $3.00 $2.74 $3.02 $3.50 $2.82 $2.85 $3.02 $2.85 $2.92
90233(A)0200 VEGETATIVE MULCHING16.84AC $1,000.00 $500.00 $800.00 $500.00 $822.97 $799.00 $880.08 $1,100.00 $850.94
100402(E)2600 TRAFFIC BOUND SURFACE COURSE TYPE E1,927TON $40.00 $29.60 $44.90 $53.00 $33.99 $40.00 $36.88 $45.00 $35.15
110509(D)0500 CLASS C CONCRETE10CY $350.00 $150.00 $425.00 $300.00 $560.51 $325.00 $564.23 $400.00 $372.75
120602(B)2310 REVETMENT MATTRESSES5,832SY $35.00 $43.00 $43.00 $62.50 $39.71 $50.00 $46.40 $60.00 $47.71
130613(EE)5972 (SP) 24" CORRUGATED POLYPROPYLENE PIPE202LF $65.00 $50.00 $75.00 $70.00 $93.73 $95.00 $103.59 $95.00 $96.92
140613(EE)5980 (SP) 36" CORRUGATED POLYPROPYLENE PIPE42LF $100.00 $80.00 $177.00 $80.00 $153.47 $165.00 $163.65 $350.00 $158.69
150613(L)6716 24" PREFAB. CULVERT END SEC., ROUND8EA $1,200.00 $1,000.00 $400.00 $750.00 $437.75 $740.00 $376.38 $1,500.00 $452.63
160613(L)6728 36" PREFAB. CULVERT END SEC., ROUND2EA $2,200.00 $1,000.00 $925.00 $750.00 $921.85 $950.00 $926.22 $2,500.00 $953.18
170619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $10,000.00 $10,000.00 $6,000.00 $4,000.00 $9,270.00 $6,500.00 $25,548.60 $7,500.00 $20,000.00
180623(F)1704 GUARDRAIL ANCHOR UNIT (TYPE A)4EA $2,000.00 $2,475.00 $2,625.00 $2,900.00 $2,549.25 $2,675.00 $3,131.65 $1,970.00 $2,635.88
190623(F)1724 GUARDRAIL ANCHOR UNIT (TYPE D-BF)4EA $2,000.00 $2,475.00 $2,675.00 $2,950.00 $2,549.25 $2,675.00 $3,185.64 $2,190.00 $2,635.88
200624(C)3405 FENCE-STYLE SWF (5 BARBED WIRE)3,417LF $10.00 $9.40 $9.24 $8.00 $8.76 $8.40 $9.07 $8.40 $8.95
210624(D)3500 GATE, GALVANIZED STEEL2EA $1,000.00 $1,150.00 $1,265.00 $2,200.00 $1,545.00 $1,150.00 $1,241.86 $1,150.00 $1,224.75
220501(B)1300 SUBSTRUCTURE EXCAVATION COMMON200CY $25.00 $100.00 $15.00 $22.00 $19.90 $16.00 $19.49 $25.00 $45.90
230501(G)1800 CLSM BACKFILL88CY $200.00 $150.00 $192.50 $180.00 $255.24 $195.00 $197.12 $200.00 $170.28
240503(A)4230 PRESTRESSED CONCRETE BEAMS (TYPE III)388LF $250.00 $250.00 $258.00 $240.00 $284.23 $290.00 $269.74 $300.00 $300.00
250503(A)4240 PRESTRESSED CONCRETE BEAMS (TYPE IV)284LF $275.00 $250.00 $295.00 $260.00 $311.79 $325.00 $291.44 $325.00 $350.00
260504(D)5410 CONCRETE RAIL (TR3)532.7LF $80.00 $50.00 $87.00 $75.00 $93.52 $105.00 $91.51 $80.00 $117.03
270506(A)7200 STRUCTURAL STEEL1,230LB $3.00 $10.00 $5.00 $5.00 $6.78 $5.00 $6.47 $4.00 $4.58
280507(A)8210 WEATHERING STEEL FIXED BEARING ASSEMBLY6EA $1,400.00 $2,000.00 $1,330.00 $1,000.00 $1,121.31 $1,650.00 $1,787.28 $1,500.00 $2,000.00
290507(B)8310 WEATHERING STL EXP. BEARING ASSEMBLY12EA $1,500.00 $2,000.00 $1,290.00 $1,000.00 $1,121.31 $1,650.00 $1,739.52 $1,500.00 $2,000.00
300509(A)0210 CLASS AA CONCRETE182CY $650.00 $500.00 $715.00 $630.00 $1,131.98 $730.00 $696.26 $700.00 $990.00
310509(B)0320 CLASS A CONCRETE148.4CY $700.00 $500.00 $740.00 $595.00 $759.71 $730.00 $884.29 $775.00 $1,100.00
320511(A)2210 REINFORCING STEEL71,160LB $1.25 $1.60 $1.39 $1.30 $1.39 $1.50 $1.37 $1.50 $1.28
330514(A)5210 PILES, FURNISHED (HP 10X42)118LF $50.00 $55.00 $58.80 $51.00 $58.22 $70.00 $68.54 $65.00 $57.00
340514(A)5220 PILES, FURNISHED (HP 12X53)296LF $50.00 $55.00 $65.10 $51.00 $68.05 $76.00 $79.95 $70.00 $69.00
350514(B)5310 PILES, DRIVEN (HP 10X42)118LF $13.00 $5.00 $25.20 $25.50 $42.16 $10.00 $37.25 $17.00 $30.00
360514(B)5320 PILES, DRIVEN (HP 12X53)296LF $15.00 $5.00 $27.90 $25.50 $50.42 $10.00 $29.70 $20.00 $30.00
370514(L)6300 PILE SPLICE, H-PILE (NON-BIDDABLE)1EA $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00 $400.00
380516(A)8240 DRILLED SHAFTS 60" DIAMETER182LF $1,100.00 $800.00 $980.00 $1,100.00 $946.40 $995.00 $1,189.22 $1,150.00 $960.00
390516(C)8400 CROSSHOLE SONIC LOGGING1EA $3,000.00 $10,000.00 $3,100.00 $3,000.00 $1,545.00 $10,000.00 $5,757.99 $3,000.00 $1,597.50
400518(B)0300 SEALED EXPANSION JOINTS33.06LF $300.00 $10.00 $395.00 $365.00 $567.79 $475.00 $410.62 $325.00 $275.33
410613(H)6205 6" PERFORATED PIPE UNDERDRAIN ROUND60LF $30.00 $75.00 $37.00 $28.00 $46.60 $40.00 $99.60 $28.00 $27.11
420613(I)6310 6" NON-PERF.PIPE UNDERDRAIN RND.38LF $25.00 $75.00 $46.00 $28.00 $69.13 $40.00 $36.65 $24.50 $36.23
430619(D)6700 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $25,000.00 $18,000.00 $18,500.00 $32,000.00 $46,133.00 $55,000.00 $73,286.85 $30,000.00 $214,690.00
440805(D)3528 (PL)REMOVE & RESET EXISTING SIGNS2EA $200.00 $250.00 $260.00 $250.00 $257.50 $250.00 $269.97 $250.00 $266.25
450850(A)1200 SHEET ALUMINUM SIGNS22.5SF $25.00 $50.00 $55.00 $25.00 $51.50 $50.00 $27.00 $50.00 $53.25
460851(C)2420 2 1/4" SQUARE TUBE POST26LF $12.00 $12.00 $12.50 $15.00 $12.36 $13.00 $16.20 $8.00 $12.78
470880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF300SD $0.5000 $0.2500 $0.2000 $2.00 $0.2600 $0.2500 $2.16 $0.5000 $0.2700
480880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF1,500SD $0.7500 $0.1000 $0.0500 $2.00 $0.1000 $0.1000 $2.16 $0.7500 $0.1100
490880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF600SD $1.00 $0.2500 $0.2500 $2.00 $0.2600 $0.2500 $2.16 $1.00 $0.2700
500880(C)6410 CONSTRUCTION BARRICADES(TYPE III)900SD $1.00 $1.25 $1.50 $3.00 $1.29 $1.50 $3.24 $1.40 $1.33
510880(E)6600 WARNING LIGHTS(TYPE A)1,950SD $0.5000 $1.25 $1.55 $0.5000 $1.29 $1.50 $0.5400 $0.7500 $1.33
520642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $25,000.00 $7,500.00 $8,000.00 $8,555.00 $6,180.00 $7,000.00 $16,423.63 $25,000.00 $25,000.00
530220 1100 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $3,000.00 $1,000.00 $2,000.00 $2,500.00 $2,500.00 $2,000.00 $3,444.70 $5,000.00 $4,200.00
540641 2100 MOBILIZATION1LSUM $105,100.00 $80,000.00 $88,000.00 $85,000.00 $120,384.76 $107,000.00 $121,430.23 $125,000.00 $134,000.00