| 1 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 398 | CY |
$20.00 |
$21.85 |
$37.50 |
$15.00 |
$23.90 |
| 2 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,000 | LF |
$2.25 |
$6.60 |
$1.75 |
$2.50 |
$7.15 |
| 3 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 398 | CY |
$75.00 |
$60.75 |
$67.50 |
$40.00 |
$66.40 |
| 4 | 307(C) 4220 |
PORTLAND CEMENT | 1,024 | TON |
$160.00 |
$192.30 |
$175.00 |
$141.00 |
$210.00 |
| 5 | 307(K) 4300 |
STABILIZED SUBGRADE | 71,111 | SY |
$6.00 |
$1.58 |
$4.44 |
$6.00 |
$1.75 |
| 6 | 311(D) 0154 |
PROCESSING EXISTING BASE & SURFACE, METHOD D | 25,600 | LF |
$8.00 |
$8.55 |
$7.77 |
$12.50 |
$4.30 |
| 7 | 326(B) 0100 |
GEOGRID REINFORCEMENT | 500 | SY |
$4.00 |
$6.75 |
$5.75 |
$2.00 |
$7.35 |
| 8 | 402(E) 0225 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 4,100 | TON |
$25.00 |
$28.70 |
$31.50 |
$26.00 |
$37.30 |
| 9 | 407(D) 0401 |
(SP) NT TACK MATERIAL | 5,006 | GAL |
$2.00 |
$2.70 |
$2.41 |
$2.50 |
$5.50 |
| 10 | 408 5774 |
PRIME COAT | 21,902 | GAL |
$2.50 |
$0.8600 |
$0.2500 |
$4.85 |
$7.75 |
| 11 | 411(B) 5945 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 11,500 | TON |
$75.00 |
$80.96 |
$85.63 |
$74.50 |
$108.00 |
| 12 | 411(D) 5975 |
SUPERPAVE, TYPE S5(PG 64-22 OK) | 7,600 | TON |
$80.00 |
$87.00 |
$89.66 |
$80.50 |
$103.50 |
| 13 | 619(C) 0924 |
SAWING PAVEMENT | 44 | LF |
$3.00 |
$11.00 |
$1.00 |
$3.00 |
$49.30 |
| 14 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 450 | LF |
$25.00 |
$20.75 |
$38.00 |
$20.00 |
$20.40 |
| 15 | 623(F) 4446 |
GUARDRAIL ANCHOR UNIT (TYPE A) | 34 | EA |
$1,500.00 |
$2,570.00 |
$2,000.00 |
$2,400.00 |
$1,725.00 |
| 16 | 623(F) 4447 |
GUARDRAIL ANCHOR UNIT (TYPE B) | 2 | EA |
$1,500.00 |
$1,610.00 |
$2,200.00 |
$1,500.00 |
$862.50 |
| 17 | 629(E) 5048 |
REMOVE AND RESET MAILBOX | 30 | EA |
$188.00 |
$490.00 |
$50.00 |
$300.00 |
$57.50 |
| 18 | 823 8478 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 90 | SD |
$130.00 |
$109.00 |
$10.00 |
$110.00 |
$109.50 |
| 19 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 102,400 | LF |
$0.4000 |
$0.3700 |
$0.4400 |
$0.3500 |
$0.4100 |
| 20 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$15,000.00 |
$55,580.00 |
$12,500.00 |
$12,000.00 |
$50,930.00 |
| 21 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$15,000.00 |
$7,650.00 |
$25,000.00 |
$41,000.00 |
$23,495.00 |
| 22 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$176,000.00 |
$123,000.00 |
$50,000.00 |
$100,000.00 |
$216,507.90 |