| 1 | 876(A) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 240 | SD |
$23.00 |
$8.00 |
$5.00 |
$51.40 |
| 2 | 880(A) 8812 |
ARROW DISPLAY(TYPE C) | 240 | SD |
$6.00 |
$7.00 |
$10.00 |
$17.15 |
| 3 | 880(B) 8818 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 2,040 | SD |
$0.3000 |
$1.60 |
$0.5000 |
$1.20 |
| 4 | 880(B) 8821 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 2,640 | SD |
$0.6000 |
$1.60 |
$0.5000 |
$1.20 |
| 5 | 880(B) 8824 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 6,000 | SD |
$1.50 |
$1.60 |
$2.00 |
$1.20 |
| 6 | 880(C) 8842 |
CONSTRUCTION BARRICADES(TYPE III) | 3,360 | SD |
$1.00 |
$0.0500 |
$1.00 |
$1.20 |
| 7 | 880(C) 8848 |
WING BARRICADES | 480 | SD |
$1.30 |
$5.00 |
$5.00 |
$11.50 |
| 8 | 880(E) 8860 |
WARNING LIGHTS(TYPE A) | 7,560 | SD |
$0.4000 |
$0.1000 |
$0.1000 |
$0.3500 |
| 9 | 880(F) 8878 |
DRUMS | 13,800 | SD |
$0.2500 |
$0.1000 |
$0.1000 |
$0.3500 |
| 10 | 880(G) 8890 |
CHANNELIZER CONES | 58,080 | SD |
$0.3500 |
$0.3500 |
$0.3000 |
$0.3000 |
| 11 | 880(L) 8920 |
(SP) TRAFFIC SURVEILLANCE, OHP (NON-BIDDABLE) | 200 | HOUR |
$69.00 |
$69.00 |
$69.00 |
$69.00 |
| 12 | 882(A) 8306 |
PORT.CHANGEABLE MESSAGE SIGN | 536 | SD |
$15.00 |
$12.00 |
$15.00 |
$18.25 |
| 13 | 805(D) 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 77 | EA |
$100.00 |
$50.00 |
$100.00 |
$230.00 |
| 14 | 221(C) 2801 |
TEMPORARY SILT FENCE | 1,000 | LF |
$2.50 |
$1.90 |
$2.40 |
$2.75 |
| 15 | 221(D) 2803 |
TEMPORARY SEDIMENT FILTER | 17 | EA |
$200.00 |
$100.00 |
$150.00 |
$115.00 |
| 16 | 221(F) 0100 |
TEMPORARY SILT DIKE | 686 | LF |
$8.00 |
$9.00 |
$12.00 |
$9.15 |
| 17 | 230(A) 2806 |
SOLID SLAB SODDING | 38,850 | SY |
$2.00 |
$1.50 |
$2.50 |
$1.85 |
| 18 | 241 2832 |
MOWING | 24.08 | AC |
$120.00 |
$60.00 |
$75.00 |
$28.55 |
| 19 | 411(C) 5950 |
SUPERPAVE, TYPE S4(PG 76-28 OK) | 5,221.44 | TON |
$100.00 |
$127.00 |
$123.20 |
$150.00 |
| 20 | 509(A) 0319 |
CLASS AA CONCRETE | 415.37 | CY |
$450.00 |
$145.00 |
$300.00 |
$360.00 |
| 21 | 628(B) 5125 |
HIGH-TENSION CABLE BARRIER(TL-4) | 34,965 | LF |
$12.00 |
$11.00 |
$12.05 |
$11.10 |
| 22 | 628(C) 5110 |
END ANCHORS | 30 | EA |
$2,500.00 |
$4,335.00 |
$1,000.00 |
$1,165.00 |
| 23 | 628(E) 5175 |
CABLE BARRIER TENSION METER | 1 | EA |
$3,000.00 |
$3,200.00 |
$3,750.00 |
$3,655.00 |
| 24 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$7,000.00 |
$4,550.00 |
$10,250.00 |
$19,410.00 |
| 25 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$2,500.00 |
$3,000.00 |
$5,000.00 |
$2,855.00 |
| 26 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$93,855.00 |
$98,030.00 |
$150,000.00 |
$165,115.00 |