| 1 | 201 0181 |
SELECTIVE CLEARING | 1 | LSUM |
$5,000.00 |
$2,500.00 |
$61,500.00 |
$20,000.00 |
$15,256.00 |
| 2 | 202(A) 0183 |
UNCLASSIFIED EXCAVATION | 4,534 | CY |
$15.00 |
$11.00 |
$28.44 |
$16.00 |
$17.00 |
| 3 | 202(D) 0184 |
UNCLASSIFIED BORROW | 100 | CY |
$30.00 |
$12.00 |
$22.50 |
$25.00 |
$35.00 |
| 4 | 221(C) 2801 |
TEMPORARY SILT FENCE | 939 | LF |
$1.50 |
$3.00 |
$2.50 |
$4.00 |
$5.50 |
| 5 | 221(D) 2803 |
TEMPORARY SEDIMENT FILTER | 5 | EA |
$200.00 |
$450.00 |
$142.00 |
$200.00 |
$275.00 |
| 6 | 221(G) 0152 |
TEMPORARY ROCK FILTER DAM TYPE 3 | 47 | CY |
$100.00 |
$39.00 |
$74.00 |
$125.00 |
$137.50 |
| 7 | 230(A) 2806 |
SOLID SLAB SODDING | 6,500 | SY |
$4.50 |
$5.00 |
$4.25 |
$4.50 |
$4.55 |
| 8 | 230(B) 2807 |
MULCH SODDING | 51 | SY |
$105.00 |
$9.00 |
$43.60 |
$10.00 |
$190.00 |
| 9 | 303(A) 2100 |
AGGREGATE BASE TYPE A | 560 | CY |
$35.00 |
$50.00 |
$60.00 |
$65.00 |
$192.00 |
| 10 | 310(B) 0149 |
SUBGRADE, METHOD B | 920 | SY |
$4.00 |
$3.00 |
$7.50 |
$1.50 |
$70.90 |
| 11 | 325 5271 |
SEPARATOR FABRIC | 1,500 | SY |
$10.00 |
$2.50 |
$2.50 |
$1.50 |
$11.70 |
| 12 | 501(B) 1307 |
SUBSTRUCTURE EXCAVATION COMMON | 4,000 | CY |
$15.00 |
$14.00 |
$27.00 |
$16.00 |
$37.40 |
| 13 | 501(E) 6354 |
SELECT BACKFILL | 1,380 | CY |
$30.00 |
$45.00 |
$27.00 |
$30.00 |
$60.50 |
| 14 | 504(F) 6006 |
HANDRAILING | 172 | LF |
$125.00 |
$100.00 |
$174.00 |
$160.00 |
$197.50 |
| 15 | 509(A) 1326 |
CLASS AA CONCRETE | 15 | CY |
$1,200.00 |
$760.00 |
$590.00 |
$900.00 |
$1,735.00 |
| 16 | 509(B) 1328 |
CLASS A CONCRETE | 135 | CY |
$800.00 |
$660.00 |
$350.00 |
$1,000.00 |
$769.00 |
| 17 | 510(A) 6333 |
RETAINING WALL | 990 | SY |
$665.00 |
$422.10 |
$420.00 |
$700.00 |
$516.50 |
| 18 | 510(A) 6334 |
RETAINING WALL | 45 | SY |
$1,200.00 |
$422.10 |
$502.00 |
$850.00 |
$2,799.00 |
| 19 | 535 6785 |
PREFABRICATED PEDESTRIAN BRIDGE | 1 | EA |
$105,000.00 |
$175,000.00 |
$104,000.00 |
$157,500.00 |
$112,110.00 |
| 20 | 601(A) 0297 |
TYPE I PLAIN RIPRAP | 4 | TON |
$200.00 |
$53.00 |
$130.00 |
$100.00 |
$248.50 |
| 21 | 601(C) 0538 |
TYPE I-A FILTER BLANKET | 2 | TON |
$100.00 |
$40.00 |
$220.00 |
$100.00 |
$406.50 |
| 22 | 609(A) 5864 |
CONCRETE CURB (6" BARRIER-DOWELLED) | 65 | LF |
$35.00 |
$35.00 |
$24.00 |
$25.00 |
$54.80 |
| 23 | 610(A) 0604 |
5" CONCRETE SIDEWALK | 1,151 | SY |
$70.00 |
$75.00 |
$77.50 |
$80.00 |
$158.50 |
| 24 | 610(E) 0425 |
(PL) CONCRETE PAVERS | 290 | SF |
$30.00 |
$15.00 |
$13.42 |
$30.00 |
$62.00 |
| 25 | 610(I) 4610 |
TACTILE WARNING DEVICE-NEW | 25 | SF |
$45.00 |
$115.00 |
$42.00 |
$24.00 |
$54.90 |
| 26 | 611(A) 2657 |
MANHOLE (4' DIAMETER) | 2 | EA |
$4,000.00 |
$4,500.00 |
$3,900.00 |
$3,500.00 |
$4,780.00 |
| 27 | 611(G) 4012 |
SPECIAL INLET DRAIN | 3 | EA |
$3,000.00 |
$6,000.00 |
$2,250.00 |
$3,000.00 |
$5,746.00 |
| 28 | 616(P) 0300 |
8" HDPE PIPE | 16 | LF |
$40.00 |
$31.00 |
$62.00 |
$45.00 |
$90.60 |
| 29 | 616(P) 0500 |
12" HDPE PIPE | 112 | LF |
$50.00 |
$45.00 |
$66.00 |
$45.00 |
$75.40 |
| 30 | 616(P) 0550 |
18" HDPE PIPE | 32 | LF |
$55.00 |
$57.00 |
$72.00 |
$55.00 |
$74.40 |
| 31 | 616(P) 0600 |
24" HDPE PIPE | 40 | LF |
$60.00 |
$165.00 |
$82.00 |
$70.00 |
$107.00 |
| 32 | 616(P) 0700 |
36" HDPE PIPE | 40 | LF |
$90.00 |
$500.00 |
$100.00 |
$110.00 |
$159.00 |
| 33 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$30,000.00 |
$5,000.00 |
$63,265.14 |
$35,000.00 |
$34,470.00 |
| 34 | 619(B) 4725 |
REMOVAL OF FENCE | 65 | LF |
$30.00 |
$30.00 |
$5.00 |
$15.00 |
$51.30 |
| 35 | 619(B) 4792 |
REMOVAL OF SIDEWALK | 355 | SY |
$13.50 |
$24.00 |
$4.50 |
$10.00 |
$34.30 |
| 36 | 619(B) 5881 |
REMOVAL OF CONCRETE DITCH LINER | 700 | LF |
$50.00 |
$7.75 |
$6.50 |
$8.00 |
$46.40 |
| 37 | 631(A) 0210 |
(SP)REMOVABLE BOLLARD | 4 | EA |
$2,200.00 |
$655.00 |
$2,000.00 |
$1,700.00 |
$2,810.00 |
| 38 | 802(A) 8322 |
4" GALV. STEEL ELECTRICAL CONDUIT EXPOSED | 35 | LF |
$75.00 |
$21.00 |
$45.00 |
$50.00 |
$550.00 |
| 39 | 802(B) 8342 |
2" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 70 | LF |
$20.00 |
$7.00 |
$15.00 |
$50.00 |
$330.00 |
| 40 | 802(B) 8350 |
4" PVC SCH.40 PLASTIC CONDUIT TRENCHED | 66 | LF |
$25.00 |
$21.00 |
$21.00 |
$60.00 |
$440.00 |
| 41 | 805(A) 8712 |
(PL)REMOVAL OF LIGHT POLE | 6 | EA |
$1,000.00 |
$400.00 |
$410.00 |
$1,000.00 |
$5,500.00 |
| 42 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$10,000.00 |
$2,500.00 |
$8,900.00 |
$2,150.00 |
$5,940.00 |
| 43 | 642(B) 0096 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$9,200.00 |
$8,500.00 |
$6,200.00 |
$8,800.00 |
| 44 | 220 2800 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,500.00 |
$26,000.00 |
$500.00 |
$8,250.00 |
| 45 | 641 1399 |
MOBILIZATION | 1 | LSUM |
$155,000.00 |
$100,000.00 |
$99,350.00 |
$115,000.00 |
$230,444.80 |
| 46 | 648(C) 0305 |
(PL) UTILITY SYSTEM (ELECTRICAL) | 1 | LSUM |
$38,000.00 |
$13,500.00 |
$11,100.00 |
$41,000.00 |
$326,150.00 |
| 47 | 809 8090 |
ENHANCEMENT LIGHTING (COMPLETE) | 11 | EA |
$9,000.00 |
$9,100.00 |
$9,250.00 |
$9,800.00 |
$29,675.00 |
| 48 | 616 5010 |
(PL) IRRIGATION SYSTEM | 1 | LSUM |
$72,000.00 |
$50,000.00 |
$48,000.00 |
$52,800.00 |
$85,545.00 |