RESURFACE (ASPHALT) SH-9: FROM US-277, EXTEND EAST. PROJECT LENGTH = 1.730 MILES
- Let date
- Thursday, March 19, 2015
- Contract
- 150104
- J/P numbers
- 30564(04)
- District
- Division 3
- County
- Mcclain
- Highway
- Limits
- RESURFACE (ASPHALT) SH-9: FROM US-277, EXTEND EAST. PROJECT LENGTH = 1.730 MILES
- Project number
- NHPP-244N(032)3P
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $587,321 | ||
| 1 | T.J. CAMPBELL CONSTRUCTION CO. Low bidder | $495,834 | -15.6% | |
| 2 | MARKWELL PAVING COMPANY, INC. | $499,477 | -15.0% | +0.7% |
| 3 | Silver Star Construction Company, Inc. | $539,000 | -8.2% | +8.7% |
| 4 | HASKELL LEMON CONSTRUCTION CO. | $634,195 | +8.0% | +27.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 T.J. CAMPBELL C… | #2 MARKWELL PAVING… | #3 Silver Star Con… | #4 HASKELL LEMON C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 407(B) 0250 | TACK COAT | 2,712 | GAL | $2.90 | $3.50 | $1.50 | $2.50 | $2.75 |
| 2 | 411(D) 5970 | SUPERPAVE, TYPE S5(PG 70-28 OK) | 4,784 | TON | $89.00 | $82.00 | $78.25 | $81.45 | $99.50 |
| 3 | 412 5267 | COLD MILLING PAVEMENT | 54,245 | SY | $1.95 | $1.00 | $1.50 | $2.05 | $2.15 |
| 4 | 855(A) 8812 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 31,045 | LF | $0.9500 | $0.5000 | $0.7000 | $0.4800 | $0.5000 |
| 5 | 855(A) 8818 | TRAFFIC STRIPE(PLASTIC)(12" WIDE) | 2,330 | LF | $1.75 | $2.30 | $2.20 | $2.15 | $2.20 |
| 6 | 855(A) 8825 | TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 100 | LF | $6.00 | $23.00 | $11.00 | $21.30 | $22.00 |
| 7 | 855(B) 8818 | TRAFFIC STRIPE(PLASTIC)(ARROWS) | 49 | EA | $95.00 | $91.00 | $93.50 | $85.30 | $88.00 |
| 8 | 880(A) 8812 | ARROW DISPLAY(TYPE C) | 14 | SD | $5.50 | $12.00 | $11.00 | $10.65 | $110.00 |
| 9 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $9,000.00 | $12,000.00 | $7,000.00 | $4,991.05 | $5,401.75 |