RESURFACE (ASPHALT ) SH-8: BEGIN 3.0 MILES SOUTH OF THE MAJOR COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 8.00 MILES
- Let date
- Thursday, January 23, 2014
- Contract
- 140051
- J/P numbers
- 30521(04)
- District
- Division 6
- County
- Major
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-8: BEGIN 3.0 MILES SOUTH OF THE MAJOR COUNTY LINE , EXTEND NORTH . PROJECT LENGTH = 8.00 MILES
- Project number
- SSR-247B(010)SR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,189,200 | ||
| 1 | THE CUMMINS CONSTRUCTION CO., INC. Low bidder | $1,150,075 | -3.3% | |
| 2 | J & R SAND COMPANY, INC. | $1,183,915 | -0.4% | +2.9% |
| 3 | HASKELL LEMON CONSTRUCTION CO. | $1,440,475 | +21.1% | +25.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THE CUMMINS CON… | #2 J & R SAND COMP… | #3 HASKELL LEMON C… |
|---|---|---|---|---|---|---|---|---|
| 1 | 407(B) 0250 | TACK COAT | 8,200 | GAL | $3.00 | $3.00 | $2.50 | $2.50 |
| 2 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 11,400 | TON | $86.00 | $86.40 | $90.00 | $109.00 |
| 3 | 411(I) 6310 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 350 | TON | $125.00 | $148.85 | $145.00 | $175.00 |
| 4 | 413(A) 4861 | RUMBLE STRIP-METHOD HMA-CON | 84,500 | LF | $0.1000 | $0.0700 | $0.0700 | $0.2500 |
| 5 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 120,000 | LF | $0.7000 | $0.2500 | $0.2500 | $0.5000 |
| 6 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $8,000.00 | $9,752.00 | $7,750.00 | $10,000.00 |
| 7 | 641 1552 | MOBILIZATION | 1 | LSUM | $40,000.00 | $42,750.00 | $43,000.00 | $25,000.00 |