RESURFACE (ASPHALT ) COUNTY ROAD (NS-242): FROM SH-54B IN COLONY, EXTEND NORTH . PROJECT LENGTH = 4.980 MILES
- Let date
- Thursday, June 20, 2013
- Contract
- 130228
- J/P numbers
- 26626(04)
- District
- Division 5
- County
- Washita
- Highway
- Limits
- RESURFACE (ASPHALT ) COUNTY ROAD (NS-242): FROM SH-54B IN COLONY, EXTEND NORTH . PROJECT LENGTH = 4.980 MILES
- Project number
- STP-175C(117)CI
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,132,348 | ||
| 1 | CIRCLE S PAVING CO., INC. Low bidder | $1,258,329 | +11.1% | |
| 2 | HASKELL LEMON CONSTRUCTION CO. | $1,591,074 | +40.5% | +26.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CIRCLE S PAVING… | #2 HASKELL LEMON C… |
|---|---|---|---|---|---|---|---|
| 1 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $5,000.00 | $3,000.00 | $120,000.00 |
| 2 | 402(E) 0225 | TRAFFIC BOUND SURFACE COURSE TYPE E | 472 | TON | $30.00 | $29.00 | $85.00 |
| 3 | 407(B) 0250 | TACK COAT | 3,336 | GAL | $3.00 | $4.00 | $2.50 |
| 4 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 13,358 | TON | $75.00 | $86.50 | $98.00 |
| 5 | 611(G) 5706 | INLET CDI RCP DES. 3 | 2 | EA | $500.00 | $250.00 | $5,000.00 |
| 6 | 611(H) 5791 | ADD'L DEPTH IN INLET CDI RCP DES. 3 | 1 | VF | $400.00 | $500.00 | $500.00 |
| 7 | 629(E) 5048 | REMOVE AND RESET MAILBOX | 14 | EA | $100.00 | $200.00 | $500.00 |
| 8 | 855(A) 8812 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 102,060 | LF | $0.5000 | $0.5000 | $0.5000 |
| 9 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $10,000.00 | $3,000.00 | $5,000.00 |
| 10 | 642(B) 0096 | CONSTRUCTION STAKING LEVEL II | 1 | LSUM | $7,500.00 | $2,000.00 | $5,000.00 |
| 11 | 641 1399 | MOBILIZATION | 1 | LSUM | $30,000.00 | $13,000.00 | $35,000.00 |