RESURFACE (ASPHALT ) SH-14: BEGIN 7.5 MILES NORTH OF US -281 IN WAYNOKA , EXTEND NORTH . PROJECT LENGTH = 7.10 MILES
- Let date
- Thursday, February 21, 2013
- Contract
- 130117
- J/P numbers
- 27578(04)
- District
- Division 6
- County
- Woods
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-14: BEGIN 7.5 MILES NORTH OF US -281 IN WAYNOKA , EXTEND NORTH . PROJECT LENGTH = 7.10 MILES
- Project number
- STPY-176C(180)3P
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,319,290 | ||
| 1 | Venture Corporation dba VCO Paving Low bidder | $1,411,530 | +7.0% | |
| 2 | THE CUMMINS CONSTRUCTION CO., INC. | $1,478,755 | +12.1% | +4.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Venture Corpora… | #2 THE CUMMINS CON… |
|---|---|---|---|---|---|---|---|
| 1 | 202(D) 0184 | UNCLASSIFIED BORROW | 1,500 | CY | $5.00 | $1.00 | $23.60 |
| 2 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $20,000.00 | $20,000.00 | $13,850.00 |
| 3 | 230(A) 2806 | SOLID SLAB SODDING | 31,000 | SY | $2.00 | $2.00 | $1.45 |
| 4 | 407(B) 0250 | TACK COAT | 6,200 | GAL | $2.70 | $2.00 | $4.10 |
| 5 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 11,500 | TON | $80.00 | $85.00 | $94.70 |
| 6 | 411(I) 6310 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 500 | TON | $125.00 | $170.00 | $129.25 |
| 7 | 412 5267 | COLD MILLING PAVEMENT | 3,200 | SY | $6.00 | $10.00 | $7.05 |
| 8 | 619(B) 4780 | REMOVAL OF GUARDRAIL | 400 | LF | $12.50 | $25.00 | $25.00 |
| 9 | 623(A) 0932 | BEAM GUARDRAIL W-BEAM SINGLE | 1,650 | LF | $25.00 | $30.00 | $30.00 |
| 10 | 623(G) 8571 | GUARDRAIL END TREATMENT (GET) | 16 | EA | $2,200.00 | $2,250.00 | $2,250.00 |
| 11 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 117,000 | LF | $0.7000 | $0.3900 | $0.4300 |
| 12 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $8,000.00 | $30,000.00 | $3,690.00 |
| 13 | 641 1552 | MOBILIZATION | 1 | LSUM | $40,000.00 | $50,000.00 | $33,400.00 |