| 1 | 407(B) 0250 |
TACK COAT | 7,300 | GAL |
$2.70 |
$3.00 |
$2.40 |
$2.98 |
$1.20 |
$3.24 |
| 2 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 10,575 | TON |
$82.00 |
$85.80 |
$85.00 |
$86.44 |
$93.00 |
$90.76 |
| 3 | 411(I) 6310 |
SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 350 | TON |
$120.00 |
$120.50 |
$110.00 |
$107.79 |
$115.00 |
$120.00 |
| 4 | 412 5267 |
COLD MILLING PAVEMENT | 550 | SY |
$6.00 |
$8.50 |
$6.00 |
$10.13 |
$15.06 |
$13.00 |
| 5 | 413(A) 4861 |
RUMBLE STRIP-METHOD HMA-CON | 68,550 | LF |
$0.1000 |
$0.0500 |
$0.0500 |
$0.1400 |
$0.0500 |
$0.1500 |
| 6 | 619(B) 4780 |
REMOVAL OF GUARDRAIL | 300 | LF |
$2.25 |
$8.20 |
$7.75 |
$7.75 |
$8.17 |
$7.75 |
| 7 | 623(A) 0932 |
BEAM GUARDRAIL W-BEAM SINGLE | 150 | LF |
$20.00 |
$18.00 |
$17.00 |
$17.00 |
$17.92 |
$17.00 |
| 8 | 623(F) 5686 |
GUARDRAIL ANCHOR UNIT (TYPE D-BF) | 2 | EA |
$1,700.00 |
$2,100.00 |
$1,930.00 |
$1,930.00 |
$2,034.42 |
$1,930.00 |
| 9 | 623(G) 8571 |
GUARDRAIL END TREATMENT (GET) | 2 | EA |
$2,200.00 |
$2,635.00 |
$2,500.00 |
$2,500.00 |
$2,635.26 |
$2,500.00 |
| 10 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 120,000 | LF |
$0.7000 |
$0.3400 |
$0.2600 |
$0.2600 |
$0.2700 |
$0.2600 |
| 11 | 876(A) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 14 | SD |
$20.00 |
$63.00 |
$60.00 |
$60.00 |
$63.25 |
$60.00 |
| 12 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$18,000.00 |
$22,000.00 |
$20,845.00 |
$25,377.89 |
$21,972.75 |
$20,845.00 |
| 13 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$170,000.00 |
$100,000.00 |
$175,000.00 |
$125,000.00 |
$20,000.00 |
$200,000.00 |
| 14 | 407(B) 0250 |
TACK COAT | 6,882 | GAL |
$2.70 |
$3.00 |
$2.40 |
$2.98 |
$1.20 |
$3.24 |
| 15 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 9,950 | TON |
$82.00 |
$85.80 |
$85.00 |
$86.52 |
$93.00 |
$90.76 |
| 16 | 411(I) 6310 |
SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 350 | TON |
$120.00 |
$120.50 |
$110.00 |
$101.52 |
$115.00 |
$120.00 |
| 17 | 413(A) 4861 |
RUMBLE STRIP-METHOD HMA-CON | 64,550 | LF |
$0.1000 |
$0.0500 |
$0.0500 |
$0.1400 |
$0.0500 |
$0.1500 |
| 18 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 112,900 | LF |
$0.7000 |
$0.3000 |
$0.2600 |
$0.2600 |
$0.2700 |
$0.2600 |
| 19 | 407(B) 0250 |
TACK COAT | 6,882 | GAL |
$2.70 |
$3.00 |
$2.40 |
$2.98 |
$1.20 |
$3.24 |
| 20 | 411(C) 5960 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 9,950 | TON |
$82.00 |
$85.80 |
$85.00 |
$86.52 |
$93.00 |
$90.76 |
| 21 | 411(I) 6310 |
SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 350 | TON |
$120.00 |
$120.50 |
$110.00 |
$107.79 |
$115.00 |
$120.00 |
| 22 | 413(A) 4861 |
RUMBLE STRIP-METHOD HMA-CON | 64,550 | LF |
$0.1000 |
$0.0500 |
$0.0500 |
$0.1400 |
$0.0500 |
$0.1500 |
| 23 | 856(A) 8530 |
TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 112,900 | LF |
$0.7000 |
$0.2500 |
$0.2600 |
$0.2600 |
$0.2700 |
$0.2600 |