| 1 | 223 2801 |
TEMPORARY SILT FENCE | 200 | LF |
$3.00 |
$3.75 |
$2.00 |
$7.00 |
| 2 | 303 5912 |
AGGREGATE BASE | 1,011 | TON |
$49.20 |
$29.50 |
$28.00 |
$39.50 |
| 3 | 403(A) 0217 |
TRAFFIC BOUND SURFACE COURSE TYPE A | 15 | TON |
$49.00 |
$80.00 |
$28.00 |
$39.50 |
| 4 | 504(G) 6006 |
HANDRAILING | 117 | LF |
$92.00 |
$250.00 |
$60.00 |
$150.00 |
| 5 | 509(C) 0322 |
CLASS A CONCRETE FOR SMALL STRUCTURES | 19 | CY |
$564.40 |
$550.00 |
$675.00 |
$1,100.00 |
| 6 | 511(A) 0332 |
REINFORCING STEEL | 33.4 | LB |
$3.15 |
$4.50 |
$4.00 |
$10.00 |
| 7 | 609(B) 0384 |
COMBINED CURB & GUTTER (8" BARRIER) | 1,505 | LF |
$20.00 |
$28.00 |
$20.00 |
$27.00 |
| 8 | 610(A) 0602 |
4" CONCRETE SIDEWALK | 2,302 | SY |
$41.50 |
$43.00 |
$55.00 |
$47.00 |
| 9 | 610(I) 4610 |
(PL)TACTILE WARNING DEVICE-NEW | 81 | SF |
$29.10 |
$30.00 |
$35.00 |
$38.00 |
| 10 | 612(G) 0647 |
VALVE BOXES ADJUST TO GRADE | 2 | EA |
$252.00 |
$300.00 |
$125.00 |
$280.00 |
| 11 | 612(H) 0648 |
METER BOXES ADJUST TO GRADE | 44 | EA |
$252.00 |
$200.00 |
$75.00 |
$280.00 |
| 12 | 612(J) 0650 |
FIRE HYDRANT RESET | 2 | EA |
$2,000.00 |
$2,500.00 |
$6,000.00 |
$3,000.00 |
| 13 | 612(P) 0674 |
(PL)RESET LIGHT POLES | 11 | EA |
$4,000.00 |
$1,505.00 |
$3,000.00 |
$2,200.00 |
| 14 | 619(A) 0920 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$5,000.00 |
$4,750.00 |
$3,000.00 |
$25,000.00 |
| 15 | 619(B) 4726 |
REMOVAL OF CURB AND GUTTER | 1,479 | LF |
$5.20 |
$4.00 |
$6.00 |
$7.50 |
| 16 | 619(B) 4728 |
REMOVAL OF ASPHALT PAVEMENT | 165 | SY |
$9.90 |
$6.00 |
$6.00 |
$7.50 |
| 17 | 619(B) 4792 |
REMOVAL OF SIDEWALK | 2,291 | SY |
$12.50 |
$5.00 |
$6.00 |
$11.00 |
| 18 | 619(C) 0924 |
SAWING PAVEMENT | 2,968 | LF |
$4.50 |
$3.00 |
$3.00 |
$5.00 |
| 19 | 851(C) 8327 |
2 1/4" SQUARE TUBE POST | 66 | LF |
$13.90 |
$4.05 |
$7.00 |
$20.00 |
| 20 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$9,023.70 |
$9,400.00 |
$12,500.00 |
$16,000.00 |
| 21 | 890A/B 8756 |
(PL)REMOVE & RESET EXISTING SIGNS | 6 | EA |
$154.00 |
$300.00 |
$150.00 |
$490.00 |
| 22 | 642 0098 |
STAKING | 1 | LSUM |
$4,000.00 |
$4,900.00 |
$12,500.00 |
$18,000.00 |
| 23 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$16,000.00 |
$25,000.00 |
$50,000.00 |
$46,500.00 |
| 24 | 411(S3) 5945 |
(SP)ASPHALT CONCRETE TYPE S3(PG 64-22 OK) | 1,150 | TON |
$100.00 |
$97.50 |
$105.00 |
$81.00 |
| 25 | 417 4267 |
COLD MILLING BITUMINOUS PAVEMENT | 6,750 | SY |
$2.25 |
$4.50 |
$2.50 |
$2.90 |
| 26 | 854(C) 8525 |
(SP)TRAFFIC STRIPE (MULTI-POLYMER)(SYMBOLS, WORDS. ETC.) | 8 | EA |
$250.00 |
$535.00 |
$550.00 |
$500.00 |
| 27 | 855(A) 8812 |
TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 4,150 | LF |
$0.6000 |
$2.45 |
$2.30 |
$2.05 |