| Let date | Contract / J/P | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| May 8, 2025 | 250109 STP-251B(179)3P | MuskogeeDivision 1 | US-62 (SH-16) | Resurface (Asphalt) US-62 (SH-16) : FROM 0.378 MILES EAST OF THE US-64 (SH-72) INTERSECTION, EXTEND EAST NEAR MUSKOGEE. | $2,164,351 | Let | APAC-CENTRAL, INC. $1,785,929 · -17.5% | |
| Jun 12, 2025 | 250086 SSP-251F(183)PM | McintoshMuskogeeOkmulgeeSequoyahDivision 1 | SH-101SH-72US-266US-75 | Bridge Waterproof Seal US-75/US-266/SH-72/SH-101: OVER ELK CREEK, SH-16, COAL CREEK, BIG SKIN BAYOU, AND UNNAMED CREEK AT MULTIPLE LOCATIONS IN DISTRICT I. | $89,727 | Let | GARY A. CRAIN, INC. $81,103 · -9.6% | |
| Sep 18, 2025 | 250260 STP-251C(193)PM | MuskogeeDivision 1 | SH-71 | Bridge And Approaches SH-71: OVER BELLE STAR CREEK, 5.36 MILES SOUTHWEST OF THE SH-2 INTERSECTION NEAR THE EUFAULA DAM. | $3,560,784 | Let | Lopp Construction, LLC $2,536,981 · -28.8% | |
| Oct 9, 2025 | 250279 SBR-251B(186)SB | MuskogeeDivision 1 | SH-16 | Bridge Rehabilitation SH-16: OVER ARKANSAS RIVER, 1.7 MILES NORTH OF THE US-69 JUNCTION NEAR MUSKOGEE. | $1,109,770 | Let | LOGOS CONSTRUCTION CO., LLC $899,510 · -18.9% | |
| Oct 9, 2025 | 250280 BRO-251F(190)CB | McintoshMuskogeeOkmulgeeWagonerDivision 1 | COUNTY ROADS | Bridge Repair COUNTY ROADS: AT MULTIPLE LOCATIONS IN DISTRICT I. | $496,365 | Let | PBX Corporation $295,913 · -40.4% | |
| Oct 9, 2025 | 250346 E-SAP-251B(199)ES | MuskogeeDivision 1 | SH-165 | Bridge Repair SH-165: REPAIR VEHICLE IMPACT DAMAGE OVER CHANDLER STREET, 2.1 MILES SOUTH OF THE US-62 INTERCHANGE IN MUSKOGEE. | — | Let | K & R BUILDERS, INC. $408,483 · | |
| Oct 16, 2025 | 250306 BRO-256F(109)CB | McintoshMuskogeeOkmulgeeDivision 1 | COUNTY ROADS | Bridge Repair COUNTY ROADS: AT MULTIPLE LOCATIONS IN DISTRICT I. | — | Let | K & R BUILDERS, INC. $497,424 · |
1–7 of 7
Lettings: ODOT Contracts and Proposals (letting spreadsheets and item lists). Planned projects: ODOT 8-Year Construction Work Plan (roads and bridges layers on the ODOT open data hub). Years are federal fiscal years; let months are shown only where ODOT lists one. Right of way and utility pieces are left out. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.