$2,925.67Avg low bid / EA
$3,021.18Avg of all bids
$2,710.00Avg engineer's estimate
6Jobs · 18 EA
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 2 | $3,536.00 | $3,490.33 |
| 2019 | 3 | 12 | $3,033.33 | $3,112.33 |
| 2018 | 2 | 4 | $2,297.50 | $2,822.99 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| May 20, 2021 | 210127 | BlaineDivision 5 | 2 EA | $3,536.00 | THE CUMMINS CONSTRUCTION CO., INC. |
| Sep 19, 2019 | 190216 | McclainDivision 3 | 2 EA | $4,700.00 | ALLEN CONTRACTING, INC./SHELL CONSTRUCTION CO., INC. (JV) |
| Aug 22, 2019 | 190257 | SequoyahDivision 1 | 6 EA | $3,000.00 | JOB CONSTRUCTION CO., INC. |
| May 16, 2019 | 190179 | McclainDivision 3 | 4 EA | $2,250.00 | BRIDGECO CONTRACTORS, INC. |
| Mar 15, 2018 | 180054 | McclainDivision 3 | 2 EA | $1,400.00 | SEWELL BROS., INC. |
| Feb 15, 2018 | 180009 | KingfisherDivision 4 | 2 EA | $3,195.00 | DUIT CONSTRUCTION COMPANY, INC. |