$101.12Avg low bid / LF
$141.94Avg of all bids
$114.30Avg engineer's estimate
5Jobs · 1,156 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 3 | 854 | $86.37 | $141.24 |
| 2019 | 2 | 302 | $142.82 | $145.10 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Oct 15, 2020 | 200077 | PottawatomieDivision 3 | 522 LF | $85.00 | OVERLAND CORPORATION |
| Jul 23, 2020 | 200261 | Pontotoc | 38 LF | $123.75 | THE CUMMINS CONSTRUCTION CO., INC. |
| May 14, 2020 | 200197 | JohnstonDivision 3 | 294 LF | $83.97 | C3 Construction, Inc. |
| Jul 25, 2019 | 190269 | Roger MillsDivision 5 | 104 LF | $150.00 | SEWELL BROS., INC. |
| May 16, 2019 | 190081 | JohnstonDivision 3 | 198 LF | $139.05 | Treas Construction Inc |