$3.72Avg low bid / SY
$6.41Avg of all bids
$7.57Avg engineer's estimate
10Jobs · 30,102 SY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 3 | 2,800 | $7.73 | $7.35 |
| 2020 | 4 | 7,280 | $5.92 | $5.34 |
| 2019 | 1 | 19,635 | $2.13 | $6.86 |
| 2018 | 2 | 387 | $14.33 | $7.44 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 18, 2021 | 210045 | ClevelandDivision 3 | 1,000 SY | $6.00 | T.J. CAMPBELL CONSTRUCTION COMPANY |
| Feb 18, 2021 | 210070 | WoodwardDivision 6 | 1,500 SY | $7.16 | BRIDGECO CONTRACTORS, INC. |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 100 SY | $16.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 100 SY | $16.00 | OVERLAND CORPORATION |
| Jan 21, 2021 | 200340 | Bsap-207c(102)fm | 100 SY | $17.00 | OVERLAND CORPORATION |
| May 14, 2020 | 200208 | PittsburgDivision 2 | 1,000 SY | $6.80 | DUIT CONSTRUCTION COMPANY, INC. |
| May 14, 2020 | 200212 | StephensDivision 7 | 450 SY | $9.40 | SEWELL BROS., INC. |
| May 14, 2020 | 200197 | JohnstonDivision 3 | 500 SY | $5.44 | C3 Construction, Inc. |
| Apr 16, 2020 | 200153 | Jefferson | 5,330 SY | $5.50 | K & R BUILDERS, INC. |
| Jul 25, 2019 | 190145 | BryanDivision 2 | 19,635 SY | $2.13 | DUIT CONSTRUCTION COMPANY, INC. |
| Jun 14, 2018 | 180232 | WashitaDivision 5 | 150 SY | $32.00 | SEWELL BROS., INC. |
| May 17, 2018 | 180216 | WoodwardDivision 6 | 237 SY | $3.15 | SEWELL BROS., INC. |