17-00031-01-PV
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Baxmeyer Construction, Inc. Low bidder | $1,536,288 | ||
| 2 | DMS Contracting, Inc. | $1,549,201 | +0.8% | |
| 3 | Stutz Excavating, Inc. | $1,656,251 | +7.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Baxmeyer Constr… | #2 DMS Contracting… | #3 Stutz Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0323389 | STORM SEW CONNECTION | 10 | EACH | $1,140.00 | $827.00 | $855.00 | |
| 2 | X0325405 | FILL EX STORM SEWERS | 2 | CU YD | $485.00 | $689.00 | $485.00 | |
| 3 | X0327235 | LOC UNDERGR UTILITIES | 176 | FOOT | $50.60 | $48.00 | $21.00 | |
| 4 | X1200108 | INLET BOX SPL | 7 | EACH | $3,240.00 | $2,740.00 | $2,750.00 | |
| 5 | X1700067 | STAMP COL PCC SDWLK 5 | 896 | SQ FT | $20.00 | $16.00 | $17.80 | |
| 6 | X6026634 | METER VAULTS ADJ | 2 | EACH | $357.00 | $1,306.00 | $360.00 | |
| 7 | X6040171 | GRATES SPL | 1 | EACH | $1,550.00 | $639.00 | $365.00 | |
| 8 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,300.00 | $21,730.00 | $18,800.00 | |
| 9 | X7240300 | SIGN REMOVAL | 4 | EACH | $124.00 | $205.00 | $75.00 | |
| 10 | Z0004518 | HMA DRIVEWAY PAVT 5 | 213 | SQ YD | $43.65 | $55.00 | $61.00 | |
| 11 | Z0056668 | SS 2 WAT MN 12 | 533 | FOOT | $107.80 | $113.00 | $125.00 | |
| 12 | Z0056670 | SS 2 WAT MN 18 | 54 | FOOT | $198.20 | $222.00 | $185.00 | |
| 13 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 14 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 15 | 20100110 | TREE REMOV 6-15 | 24 | UNIT | $0.0100 | $0.0100 | $120.00 | |
| 16 | 20200100 | EARTH EXCAVATION | 3,870 | CU YD | $28.00 | $34.00 | $33.25 | |
| 17 | 20201200 | REM & DISP UNS MATL | 43 | CU YD | $27.50 | $34.80 | $28.00 | |
| 18 | 20800150 | TRENCH BACKFILL | 717 | CU YD | $42.50 | $34.75 | $42.00 | |
| 19 | 21101615 | TOPSOIL F & P 4 | 2,420 | SQ YD | $21.00 | $18.80 | $18.70 | |
| 20 | 25000100 | SEEDING CL 1 | 0.5 | ACRE | $3,518.00 | $10,300.00 | $3,115.00 | |
| 21 | 25000400 | NITROGEN FERT NUTR | 46 | POUND | $8.50 | $4.75 | $7.50 | |
| 22 | 25000500 | PHOSPHORUS FERT NUTR | 46 | POUND | $8.50 | $4.75 | $7.50 | |
| 23 | 25000600 | POTASSIUM FERT NUTR | 46 | POUND | $8.50 | $4.75 | $7.50 | |
| 24 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $6,620.00 | $7,000.00 | $5,860.00 | |
| 25 | 25100630 | EROSION CONTR BLANKET | 729 | SQ YD | $2.90 | $3.70 | $2.60 | |
| 26 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $10.80 | $5.80 | $6.00 | |
| 27 | 28000400 | PERIMETER EROS BAR | 111 | FOOT | $15.90 | $7.90 | $8.00 | |
| 28 | 28000500 | INLET & PIPE PROTECT | 44 | EACH | $215.75 | $302.00 | $75.00 | |
| 29 | 31100100 | SUB GRAN MAT A | 2,903 | TON | $28.10 | $35.00 | $36.35 | |
| 30 | 35100300 | AGG BASE CSE A 4 | 651 | SQ YD | $27.00 | $43.00 | $28.00 | |
| 31 | 40201000 | AGGREGATE-TEMP ACCESS | 201 | TON | $34.25 | $81.00 | $51.00 | |
| 32 | 40600290 | BIT MATLS TACK CT | 2,939 | POUND | $0.0100 | $0.0100 | $1.35 | |
| 33 | 40603085 | HMA BC IL-19.0 N70 | 1,097 | TON | $155.00 | $135.75 | $143.50 | |
| 34 | 40604052 | HMA SC IL-9.5 C N70 | 731 | TON | $155.00 | $135.75 | $161.20 | |
| 35 | 42300200 | PCC DRIVEWAY PAVT 6 | 651 | SQ YD | $92.50 | $128.00 | $105.00 | |
| 36 | 42400100 | PC CONC SIDEWALK 4 | 15,526 | SQ FT | $10.25 | $8.00 | $7.55 | |
| 37 | 42400800 | DETECTABLE WARNINGS | 312 | SQ FT | $64.50 | $62.00 | $57.10 | |
| 38 | 44000100 | PAVEMENT REM | 195 | SQ YD | $31.25 | $32.00 | $19.00 | |
| 39 | 44000200 | DRIVE PAVEMENT REM | 514 | SQ YD | $18.70 | $6.70 | $24.25 | |
| 40 | 44000300 | CURB REM | 12 | FOOT | $11.50 | $32.00 | $36.00 | |
| 41 | 44000500 | COMB CURB GUTTER REM | 1,204 | FOOT | $4.85 | $5.25 | $12.00 | |
| 42 | 44000600 | SIDEWALK REM | 7,431 | SQ FT | $1.00 | $0.7500 | $2.45 | |
| 43 | 50105220 | PIPE CULVERT REMOV | 133 | FOOT | $13.00 | $13.00 | $10.00 | |
| 44 | 54210182 | PIPE ELBOW 12 | 1 | EACH | $2,150.00 | $1,382.00 | $1,125.00 | |
| 45 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $1,180.00 | $1,365.00 | $1,060.00 | |
| 46 | 54248510 | CONCRETE COLLAR | 0.9 | CU YD | $574.00 | $1,065.00 | $795.00 | |
| 47 | 550A0340 | STORM SEW CL A 2 12 | 1,387 | FOOT | $60.00 | $73.00 | $91.40 | |
| 48 | 550A0380 | STORM SEW CL A 2 18 | 307 | FOOT | $79.00 | $77.00 | $96.20 | |
| 49 | 550A0410 | STORM SEW CL A 2 24 | 22 | FOOT | $102.00 | $97.00 | $101.00 | |
| 50 | 55100300 | STORM SEWER REM 8 | 76 | FOOT | $21.00 | $11.50 | $8.25 | |
| 51 | 55100500 | STORM SEWER REM 12 | 92 | FOOT | $16.00 | $19.00 | $19.50 | |
| 52 | 55100700 | STORM SEWER REM 15 | 87 | FOOT | $10.50 | $15.00 | $16.70 | |
| 53 | 55101200 | STORM SEWER REM 24 | 45 | FOOT | $13.25 | $29.00 | $29.15 | |
| 54 | 60100905 | PIPE DRAINS 4 | 78 | FOOT | $88.00 | $50.00 | $29.00 | |
| 55 | 60218500 | MAN TA 4 DIA T3F&G | 2 | EACH | $3,830.00 | $2,500.00 | $2,550.00 | |
| 56 | 60219540 | MAN TA 4 DIA T24F&G | 2 | EACH | $3,680.00 | $2,500.00 | $2,550.00 | |
| 57 | 60235700 | INLETS TA T3F&G | 1 | EACH | $2,230.00 | $1,460.00 | $1,730.00 | |
| 58 | 60236200 | INLETS TA T8G | 7 | EACH | $1,875.00 | $1,440.00 | $1,585.00 | |
| 59 | 60237460 | INLETS TA T23F&G | 2 | EACH | $2,053.00 | $1,460.00 | $1,680.00 | |
| 60 | 60237470 | INLETS TA T24F&G | 5 | EACH | $2,077.00 | $1,460.00 | $1,535.00 | |
| 61 | 60240220 | INLETS TB T3F&G | 3 | EACH | $2,783.00 | $1,890.00 | $2,040.00 | |
| 62 | 60240327 | INLETS TB T23F&G | 7 | EACH | $2,608.00 | $1,890.00 | $1,925.00 | |
| 63 | 60240328 | INLETS TB T24F&G | 8 | EACH | $2,953.00 | $1,890.00 | $2,010.00 | |
| 64 | 60255500 | MAN ADJUST | 6 | EACH | $357.00 | $1,360.00 | $730.00 | |
| 65 | 60260100 | INLETS ADJUST | 2 | EACH | $357.00 | $1,300.00 | $425.00 | |
| 66 | 60265700 | VV ADJUST | 11 | EACH | $283.00 | $1,300.00 | $285.00 | |
| 67 | 60500060 | REMOV INLETS | 5 | EACH | $437.00 | $430.00 | $185.00 | |
| 68 | 60600605 | CONC CURB TB | 35 | FOOT | $63.00 | $68.00 | $110.00 | |
| 69 | 60604400 | COMB CC&G TB6.18 | 1,002 | FOOT | $45.00 | $57.00 | $63.00 | |
| 70 | 60605000 | COMB CC&G TB6.24 | 2,704 | FOOT | $40.60 | $36.00 | $51.00 | |
| 71 | 67100100 | MOBILIZATION | 1 | L SUM | $49,590.64 | $44,000.00 | $97,000.00 | |
| 72 | 70300100 | SHORT TERM PAVT MKING | 203 | FOOT | $3.60 | $2.00 | $3.50 | |
| 73 | 70300150 | SHRT TRM PAVT MK REM | 68 | SQ FT | $6.60 | $13.00 | $10.00 | |
| 74 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 5,828 | FOOT | $0.5000 | $1.00 | $0.4500 | |
| 75 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 871 | FOOT | $14.50 | $5.30 | $13.20 | |
| 76 | 72000100 | SIGN PANEL T1 | 136 | SQ FT | $44.60 | $53.50 | $38.50 | |
| 77 | 72400100 | REMOV SIN PAN ASSY TA | 18 | EACH | $100.00 | $78.00 | $65.00 | |
| 78 | 72800100 | TELES STL SIN SUPPORT | 324 | FOOT | $39.40 | $25.00 | $21.25 | |
| 79 | 78000200 | THPL PVT MK LINE 4 | 5,828 | FOOT | $1.65 | $4.25 | $1.45 | |
| 80 | 78000650 | THPL PVT MK LINE 24 | 871 | FOOT | $17.50 | $15.90 | $16.00 | |
| 81 | 78300201 | PAVMT MRKG REM GRIND | 860 | SQ FT | $3.65 | $5.30 | $2.25 |