17-00042-01-WR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | RCS Construction, Inc. Low bidder | $572,483 | ||
| 2 | Stutz Excavating, Inc. | $584,360 | +2.1% | |
| 3 | DMS Contracting, Inc. | $706,275 | +23.4% | |
| 4 | Keeley & Sons, Inc. | $795,897 | +39.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 RCS Constructio… | #2 Stutz Excavatin… | #3 DMS Contracting… | #4 Keeley & Sons, … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $11,000.00 | $9,000.00 | $8,950.00 | $17,890.00 | |
| 2 | X1700005 | ISLAND PAVEMENT (SPL) | 365 | SQ FT | $5.00 | $8.85 | $8.65 | $22.80 | |
| 3 | X5510100 | STORM SEWER REMOVAL | 339 | FOOT | $5.50 | $10.55 | $9.80 | $8.90 | |
| 4 | X6020074 | INLETS TA T3V F&G | 3 | EACH | $515.00 | $860.00 | $1,600.00 | $1,565.00 | |
| 5 | X6020075 | INLETS TB T3V F&G | 3 | EACH | $1,350.00 | $1,195.00 | $1,600.00 | $1,870.00 | |
| 6 | X6022230 | MAN TA 4 DIA SPL F&G | 1 | EACH | $1,550.00 | $1,630.00 | $3,375.00 | $2,165.00 | |
| 7 | X6022502 | MAN TA 4D T3F&G SPL | 1 | EACH | $1,550.00 | $1,720.00 | $2,300.00 | $2,165.00 | |
| 8 | X6024240 | INLETS SPL | 2 | EACH | $1,550.00 | $1,490.00 | $3,050.00 | $2,190.00 | |
| 9 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $12,500.00 | $11,920.00 | $16,100.00 | $25,650.00 | |
| 10 | X7010502 | TC-PROT 701502 SPL | 1 | L SUM | $2,000.00 | $1,785.00 | $4,460.00 | $3,003.90 | |
| 11 | X7240300 | SIGN REMOVAL | 11 | EACH | $50.00 | $45.00 | $225.00 | $187.90 | |
| 12 | X7240600 | REM RE-ERECT EX SIGN | 1 | EACH | $175.00 | $167.00 | $550.00 | $162.69 | |
| 13 | Z0036200 | PAINT CURB | 97 | FOOT | $12.00 | $18.50 | $19.50 | $5.10 | |
| 14 | Z0054408 | ROCK FILL - SUBGRADE | 57 | CU YD | $110.00 | $73.40 | $84.50 | $39.80 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 20100110 | TREE REMOV 6-15 | 12 | UNIT | $32.50 | $19.25 | $145.00 | $27.51 | |
| 18 | 20100210 | TREE REMOV OVER 15 | 170 | UNIT | $15.50 | $22.00 | $117.00 | $41.11 | |
| 19 | 20200100 | EARTH EXCAVATION | 946 | CU YD | $12.50 | $24.50 | $13.75 | $9.95 | |
| 20 | 20400800 | FURNISHED EXCAVATION | 355 | CU YD | $8.70 | $14.00 | $30.90 | $19.85 | |
| 21 | 20800150 | TRENCH BACKFILL | 258 | CU YD | $55.00 | $28.00 | $38.00 | $37.50 | |
| 22 | 21101505 | TOPSOIL EXC & PLAC | 799 | CU YD | $5.50 | $9.40 | $13.75 | $23.80 | |
| 23 | 25000110 | SEEDING CL 1A | 1 | ACRE | $2,750.00 | $1,415.00 | $2,400.00 | $1,377.00 | |
| 24 | 25000400 | NITROGEN FERT NUTR | 90 | POUND | $0.0100 | $1.25 | $7.30 | $1.23 | |
| 25 | 25000500 | PHOSPHORUS FERT NUTR | 90 | POUND | $0.0100 | $1.25 | $7.20 | $1.23 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 90 | POUND | $0.0100 | $1.25 | $6.95 | $1.23 | |
| 27 | 25000700 | AGR GROUND LIMESTONE | 2.1 | TON | $136.00 | $315.00 | $1,000.00 | $306.00 | |
| 28 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $4,225.00 | $2,100.00 | $5,950.00 | $2,040.00 | |
| 29 | 25100630 | EROSION CONTR BLANKET | 3,161 | SQ YD | $1.00 | $1.40 | $4.00 | $1.38 | |
| 30 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $1.00 | $3.00 | $12.00 | $5.10 | |
| 31 | 28000305 | TEMP DITCH CHECKS | 182 | FOOT | $14.00 | $7.00 | $23.50 | $23.80 | |
| 32 | 28000400 | PERIMETER EROS BAR | 355 | FOOT | $6.00 | $4.00 | $10.00 | $5.61 | |
| 33 | 28000500 | INLET & PIPE PROTECT | 3 | EACH | $110.00 | $60.00 | $150.00 | $173.80 | |
| 34 | 28000510 | INLET FILTERS | 17 | EACH | $55.00 | $50.00 | $50.00 | $267.80 | |
| 35 | 28100107 | STONE RIPRAP CL A4 | 91 | SQ YD | $43.00 | $42.00 | $42.00 | $54.24 | |
| 36 | 28200200 | FILTER FABRIC | 91 | SQ YD | $3.00 | $2.00 | $1.70 | $2.04 | |
| 37 | 31100300 | SUB GRAN MAT A 4 | 192 | SQ YD | $9.25 | $5.85 | $6.50 | $28.29 | |
| 38 | 35100700 | AGG BASE CSE A 8 | 4,098 | SQ YD | $12.00 | $13.65 | $12.80 | $17.95 | |
| 39 | 40201000 | AGGREGATE-TEMP ACCESS | 25 | TON | $37.50 | $30.00 | $62.75 | $20.00 | |
| 40 | 42000301 | PCC PVT 8 JOINTED | 3,454 | SQ YD | $51.75 | $52.00 | $41.50 | $79.85 | |
| 41 | 42001300 | PROTECTIVE COAT | 3,924 | SQ YD | $1.50 | $0.5000 | $0.0100 | $2.45 | |
| 42 | 42300400 | PCC DRIVEWAY PAVT 8 | 196 | SQ YD | $75.00 | $61.00 | $73.50 | $43.90 | |
| 43 | 42400200 | PC CONC SIDEWALK 5 | 2,096 | SQ FT | $6.00 | $6.30 | $5.65 | $8.90 | |
| 44 | 44000100 | PAVEMENT REM | 3,130 | SQ YD | $6.00 | $5.45 | $17.00 | $11.95 | |
| 45 | 44000200 | DRIVE PAVEMENT REM | 240 | SQ YD | $12.75 | $7.80 | $10.00 | $14.28 | |
| 46 | 44000500 | COMB CURB GUTTER REM | 680 | FOOT | $4.50 | $3.50 | $6.85 | $5.87 | |
| 47 | 54213660 | PRC FLAR END SEC 15 | 4 | EACH | $800.00 | $600.00 | $1,100.00 | $782.00 | |
| 48 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $800.00 | $695.00 | $1,150.00 | $807.00 | |
| 49 | 54213675 | PRC FLAR END SEC 30 | 1 | EACH | $1,075.00 | $965.00 | $2,200.00 | $1,047.00 | |
| 50 | 54216560 | R C PIPE TEE 18P 15R | 1 | EACH | $1,050.00 | $790.00 | $1,500.00 | $1,047.00 | |
| 51 | 550A2330 | SS RG CL A 1 15 | 379 | FOOT | $45.00 | $46.95 | $51.50 | $37.80 | |
| 52 | 550A2340 | SS RG CL A 1 18 | 13 | FOOT | $55.00 | $58.00 | $84.00 | $39.15 | |
| 53 | 550A2360 | SS RG CL A 1 24 | 251 | FOOT | $65.00 | $57.65 | $60.85 | $43.80 | |
| 54 | 550A2380 | SS RG CL A 1 30 | 39 | FOOT | $75.00 | $79.15 | $89.90 | $67.80 | |
| 55 | 550A2530 | SS RG CL A 2 15 | 126 | FOOT | $45.00 | $44.00 | $49.10 | $37.35 | |
| 56 | 550A2540 | SS RG CL A 2 18 | 168 | FOOT | $55.00 | $48.00 | $52.75 | $43.80 | |
| 57 | 550A2580 | SS RG CL A 2 30 | 33 | FOOT | $75.00 | $76.35 | $102.00 | $63.80 | |
| 58 | 60219570 | MAN TA 4 DIA T3V F&G | 3 | EACH | $1,600.00 | $1,400.00 | $1,850.00 | $2,849.00 | |
| 59 | 60222270 | MAN TA 5 DIA T3V F&G | 1 | EACH | $2,100.00 | $1,895.00 | $2,950.00 | $2,849.00 | |
| 60 | 60223810 | MAN TA 6 DIA T3F&G | 1 | EACH | $2,150.00 | $2,185.00 | $4,350.00 | $3,103.00 | |
| 61 | 60235700 | INLETS TA T3F&G | 2 | EACH | $1,150.00 | $930.00 | $1,380.00 | $1,520.00 | |
| 62 | 60237460 | INLETS TA T23F&G | 1 | EACH | $1,550.00 | $965.00 | $1,350.00 | $1,520.00 | |
| 63 | 60300105 | FR & GRATES ADJUST | 1 | EACH | $800.00 | $170.00 | $235.00 | $297.80 | |
| 64 | 60500060 | REMOV INLETS | 6 | EACH | $220.00 | $95.00 | $625.00 | $215.00 | |
| 65 | 60604400 | COMB CC&G TB6.18 | 1,445 | FOOT | $26.00 | $35.30 | $69.00 | $31.95 | |
| 66 | 60604700 | COMB CC&G TB6.18 MOD | 69 | FOOT | $49.50 | $40.15 | $82.00 | $32.85 | |
| 67 | 60605300 | COMB CC&G TB6.24 MOD | 28 | FOOT | $64.50 | $34.25 | $92.00 | $37.80 | |
| 68 | 67100100 | MOBILIZATION | 1 | L SUM | $35,000.00 | $32,625.00 | $18,000.00 | $46,800.00 | |
| 69 | 70300100 | SHORT TERM PAVT MKING | 168 | FOOT | $3.00 | $2.50 | $0.0100 | $3.00 | |
| 70 | 70300150 | SHRT TRM PAVT MK REM | 56 | SQ FT | $1.50 | $5.00 | $0.0100 | $8.00 | |
| 71 | 72000100 | SIGN PANEL T1 | 86 | SQ FT | $26.50 | $25.00 | $39.00 | $24.48 | |
| 72 | 72800100 | TELES STL SIN SUPPORT | 53 | FOOT | $15.00 | $14.00 | $33.50 | $13.77 | |
| 73 | 72900200 | METAL POST TY B | 140 | FOOT | $13.00 | $12.50 | $33.50 | $12.24 | |
| 74 | 78009000 | MOD URETH PM LTR-SYM | 63 | SQ FT | $10.00 | $23.50 | $25.00 | $15.30 | |
| 75 | 78009004 | MOD URETH PM LINE 4 | 1,753 | FOOT | $3.00 | $3.25 | $3.50 | $5.10 | |
| 76 | 78009008 | MOD URETH PM LINE 8 | 309 | FOOT | $6.00 | $7.85 | $8.50 | $8.16 | |
| 77 | 78009012 | MOD URETH PM LINE 12 | 427 | FOOT | $9.00 | $11.80 | $12.50 | $15.30 | |
| 78 | 78009024 | MOD URETH PM LINE 24 | 66 | FOOT | $3.25 | $23.50 | $25.00 | $25.50 | |
| 79 | 78200020 | CURB REFLECTORS | 13 | EACH | $82.00 | $105.00 | $175.00 | $10.20 |