18-00056-00-RS
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $1,252,583 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… |
|---|---|---|---|---|---|---|
| 1 | X0325279 | CLASS SI CONC (MISC) | 8.6 | CU YD | $4,148.83 | |
| 2 | X2500900 | SEEDING CL 1 SPL | 0.5 | ACRE | $9,845.00 | |
| 3 | X6023508 | INLETS TA W/SPL F&G | 1 | EACH | $1,834.97 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,103.07 | |
| 5 | 20800150 | TRENCH BACKFILL | 15 | CU YD | $104.50 | |
| 6 | 21101625 | TOPSOIL F & P 6 | 382 | SQ YD | $19.81 | |
| 7 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $6.11 | |
| 8 | 28000510 | INLET FILTERS | 29 | EACH | $259.36 | |
| 9 | 40200800 | AGG SURF CSE B | 4 | TON | $85.76 | |
| 10 | 40600290 | BIT MATLS TACK CT | 5,777 | POUND | $1.31 | |
| 11 | 40600990 | TEMPORARY RAMP | 608 | SQ YD | $8.66 | |
| 12 | 40602965 | HMA BC IL-9.5FG N50 | 479 | TON | $141.87 | |
| 13 | 40604050 | HMA SC IL-9.5 C N50 | 720 | TON | $120.19 | |
| 14 | 40800029 | BIT MATLS TACK CT | 528 | POUND | $5.43 | |
| 15 | 40800050 | INCIDENTAL HMA SURF | 164 | TON | $260.79 | |
| 16 | 42300400 | PCC DRIVEWAY PAVT 8 | 246 | SQ YD | $102.56 | |
| 17 | 42400100 | PC CONC SIDEWALK 4 | 15,634 | SQ FT | $13.75 | |
| 18 | 42400300 | PC CONC SIDEWALK 6 | 746 | SQ FT | $15.26 | |
| 19 | 42400800 | DETECTABLE WARNINGS | 899 | SQ FT | $40.31 | |
| 20 | 44000100 | PAVEMENT REM | 144 | SQ YD | $26.66 | |
| 21 | 44000159 | HMA SURF REM 2 1/2 | 9,708 | SQ YD | $6.85 | |
| 22 | 44000200 | DRIVE PAVEMENT REM | 259 | SQ YD | $31.73 | |
| 23 | 44000500 | COMB CURB GUTTER REM | 4,003 | FOOT | $18.53 | |
| 24 | 44000600 | SIDEWALK REM | 19,451 | SQ FT | $4.65 | |
| 25 | 50800105 | REINFORCEMENT BARS | 630 | POUND | $2.60 | |
| 26 | 550A0050 | STORM SEW CL A 1 12 | 83 | FOOT | $83.03 | |
| 27 | 55100500 | STORM SEWER REM 12 | 4 | FOOT | $116.60 | |
| 28 | 60218400 | MAN TA 4 DIA T1F CL | 4 | EACH | $6,503.73 | |
| 29 | 60235700 | INLETS TA T3F&G | 5 | EACH | $1,803.08 | |
| 30 | 60260100 | INLETS ADJUST | 10 | EACH | $556.56 | |
| 31 | 60260500 | INLETS ADJ NEW T3F&G | 10 | EACH | $995.98 | |
| 32 | 60500060 | REMOV INLETS | 5 | EACH | $683.76 | |
| 33 | 60600605 | CONC CURB TB | 12 | FOOT | $80.93 | |
| 34 | 60603800 | COMB CC&G TB6.12 | 4,105 | FOOT | $64.51 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $88,051.36 | |
| 36 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $12,163.74 | |
| 37 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $7,097.70 | |
| 38 | 70300100 | SHORT TERM PAVT MKING | 784 | FOOT | $1.09 | |
| 39 | 70300150 | SHRT TRM PAVT MK REM | 65 | SQ FT | $8.54 | |
| 40 | 78001100 | PT PVT MK LTRS & SYMB | 122 | SQ FT | $7.70 | |
| 41 | 78001110 | PAINT PVT MK LINE 4 | 798 | FOOT | $2.23 | |
| 42 | 78001130 | PAINT PVT MK LINE 6 | 420 | FOOT | $3.34 | |
| 43 | 78001180 | PAINT PVT MK LINE 24 | 88 | FOOT | $13.37 |