24-00056-00-SW
- Let date
- Friday, November 7, 2025
- Contract
- 87884 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Sidewalk construction at various locations in Dwight.
- Classification
- ·
- Project number
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $230,453 | ||
| 2 | Phoenix Corporation of the Quad Cities | $273,187 | +18.5% | |
| 3 | Davis Concrete Construction Co. | $279,243 | +21.2% | |
| 4 | Gensini Excavating, Inc. | $283,380 | +23.0% | |
| 5 | Tobey's Construction & Cartage, Inc. | $309,163 | +34.2% | |
| 6 | Knapp Concrete Contractors, Inc. | $383,643 | +66.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Phoenix Corpora… | #3 Davis Concrete … | #4 Gensini Excavat… | #5 Tobey's Constru… | #6 Knapp Concrete … |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326862 | STRUCTURE ADJ | 8 | EACH | $750.00 | $1,335.00 | $550.00 | $500.00 | $375.00 | $1,920.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $5,000.00 | $5,880.00 | $15,000.00 | $8,500.00 | $16,500.00 | |
| 3 | Z0017700 | DRAIN UTIL STR RECON | 2 | EACH | $2,000.00 | $1,875.00 | $2,000.00 | $1,500.00 | $1,050.00 | $3,000.00 | |
| 4 | 28000510 | INLET FILTERS | 18 | EACH | $275.00 | $400.00 | $25.00 | $250.00 | $1.00 | $400.00 | |
| 5 | 42300200 | PCC DRIVEWAY PAVT 6 | 353 | SQ YD | $80.00 | $125.00 | $87.00 | $120.00 | $101.00 | $108.00 | |
| 6 | 42400100 | PC CONC SIDEWALK 4 | 13,213 | SQ FT | $10.00 | $10.25 | $13.95 | $12.00 | $15.75 | $15.60 | |
| 7 | 42400800 | DETECTABLE WARNINGS | 81 | SQ FT | $40.00 | $45.00 | $24.00 | $30.00 | $19.00 | $34.00 | |
| 8 | 44000200 | DRIVE PAVEMENT REM | 566 | SQ YD | $12.50 | $19.00 | $18.00 | $15.00 | $17.50 | $24.00 | |
| 9 | 44000500 | COMB CURB GUTTER REM | 47 | FOOT | $12.00 | $35.00 | $20.00 | $10.00 | $42.00 | $16.80 | |
| 10 | 44000600 | SIDEWALK REM | 1,481 | SQ FT | $3.00 | $3.00 | $4.00 | $2.00 | $2.75 | $2.40 | |
| 11 | 60603800 | COMB CC&G TB6.12 | 47 | FOOT | $55.00 | $98.00 | $55.00 | $100.00 | $235.00 | $96.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $12,000.00 | $32,150.00 | $18,500.00 | $20,000.00 | $18,500.00 | $24,000.00 | |
| 13 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $10,000.00 | $1,800.00 | $250.00 | $10,000.00 | $1.00 | $33,000.00 | |
| 14 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $1,600.00 | $4,400.00 | $0.0100 | $1.00 | $4,950.00 | |
| 15 | 78000400 | THPL PVT MK LINE 6 | 415 | FOOT | $4.29 | $3.05 | $3.90 | $4.00 | $3.90 | $3.41 | |
| 16 | 78000600 | THPL PVT MK LINE 12 | 404 | FOOT | $8.53 | $12.60 | $7.75 | $13.00 | $7.75 | $14.30 |