(91-3,91-1,44-1-1,44-1)RS-3
- Let date
- Friday, June 16, 2023
- Contract
- 78599 · job page
- District
- District 9
- County
- Johnson, Union
- Highway
- Limits
- 12.7 miles of PCC overlay on I-57 northbound from just north of IL 146 to the Williamson / Johnson County line. Also includes resurfacing northbound ramps at the Goreville and Lick Creek interchanges.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $36,839,730 | ||
| 2 | Illinois Valley Paving, a div of UCM, Inc. | $37,775,491 | +2.5% | |
| 3 | Keller Construction, Inc. | $42,333,101 | +14.9% | |
| 4 | Samron Midwest Contracting, Inc. | $46,881,445 | +27.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 Illinois Valley… | #3 Keller Construc… | #4 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0301993 | REM & REIN C HWL P DR | 270 | EACH | $365.50 | $650.65 | $630.00 | $250.00 | |
| 2 | X0325747 | BR DK CONC CRACK SEAL | 2,500 | FOOT | $20.00 | $17.59 | $4.00 | $2.00 | |
| 3 | X2503100 | MOWING | 2,688 | UNIT | $90.40 | $57.75 | $31.00 | $10.00 | |
| 4 | X4400110 | TEMP PAVT REMOVAL | 5,824 | SQ YD | $15.00 | $14.64 | $17.00 | $10.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 1,555 | SQ YD | $21.70 | $22.76 | $22.00 | $25.00 | |
| 6 | X6013700 | PIPE UNDERDRN REM SPL | 476 | FOOT | $13.40 | $26.47 | $11.00 | $12.00 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $101,275.03 | $395,398.95 | $87,500.00 | $3,400,000.00 | |
| 8 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,863.25 | $10,061.59 | $2,200.00 | $25,000.00 | |
| 9 | Z0005600 | BREAKING PAVED DITCH | 1,030 | FOOT | $9.30 | $7.16 | $11.00 | $10.00 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $161,950.00 | $154,245.00 | $257,000.00 | $400,000.00 | |
| 11 | Z0016200 | DECK SLAB REP (PART) | 3 | SQ YD | $7,003.00 | $4,987.50 | $1,300.00 | $2,600.00 | |
| 12 | Z0034105 | MATL TRANSFER DEVICE | 11,383 | TON | $3.30 | $3.50 | $3.39 | $3.50 | |
| 13 | Z0040530 | PIPE UNDERDRAIN REMOV | 8,354 | FOOT | $1.60 | $10.56 | $7.30 | $1.00 | |
| 14 | Z0062456 | TEMP PAVEMENT | 6,622 | SQ YD | $79.00 | $101.97 | $100.00 | $100.00 | |
| 15 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 1,210 | CU YD | $16.90 | $31.55 | $27.00 | $17.00 | |
| 18 | 20201200 | REM & DISP UNS MATL | 22,015 | CU YD | $23.60 | $27.11 | $21.00 | $20.00 | |
| 19 | 20400100 | BORROW EXCAVATION | 24,000 | CU YD | $30.00 | $37.35 | $19.00 | $25.00 | |
| 20 | 25000210 | SEEDING CL 2A | 31.25 | ACRE | $1,775.00 | $1,548.75 | $1,810.50 | $2,000.00 | |
| 21 | 25000350 | SEEDING CL 7 | 31.25 | ACRE | $450.00 | $1,233.75 | $459.00 | $500.00 | |
| 22 | 25000400 | NITROGEN FERT NUTR | 2,814 | POUND | $1.60 | $3.78 | $1.63 | $1.60 | |
| 23 | 25000500 | PHOSPHORUS FERT NUTR | 2,814 | POUND | $1.60 | $4.15 | $1.63 | $1.60 | |
| 24 | 25000600 | POTASSIUM FERT NUTR | 2,814 | POUND | $1.60 | $3.31 | $1.63 | $1.60 | |
| 25 | 25000700 | AGR GROUND LIMESTONE | 61.9 | TON | $250.00 | $204.75 | $255.00 | $275.00 | |
| 26 | 25100115 | MULCH METHOD 2 | 31.25 | ACRE | $1,250.00 | $1,596.00 | $1,275.00 | $1,500.00 | |
| 27 | 28000250 | TEMP EROS CONTR SEED | 3,126 | POUND | $5.00 | $5.67 | $2.25 | $0.0100 | |
| 28 | 28000400 | PERIMETER EROS BAR | 11,725 | FOOT | $5.00 | $7.06 | $7.80 | $3.00 | |
| 29 | 28000500 | INLET & PIPE PROTECT | 71 | EACH | $350.00 | $404.47 | $345.00 | $250.00 | |
| 30 | 28100807 | STONE DUMP RIP CL A4 | 7,052 | TON | $40.60 | $35.92 | $65.50 | $35.00 | |
| 31 | 30300001 | AGG SUBGRADE IMPROVE | 14,791 | CU YD | $33.00 | $52.58 | $52.80 | $60.00 | |
| 32 | 31100500 | SUB GRAN MAT A 6 | 7,705 | SQ YD | $14.00 | $12.50 | $12.18 | $11.00 | |
| 33 | 31200500 | STAB SUBBASE HMA 4 | 21,976 | SQ YD | $30.00 | $27.69 | $26.90 | $30.00 | |
| 34 | 40600290 | BIT MATLS TACK CT | 3,080 | POUND | $8.70 | $9.20 | $8.93 | $9.00 | |
| 35 | 40600295 | P BIT MATLS TACK CT | 82,811 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 36 | 40600982 | HMA SURF REM BUTT JT | 1,654 | SQ YD | $22.80 | $23.90 | $23.20 | $25.00 | |
| 37 | 40600985 | PCC SURF REM BUTT JT | 106 | SQ YD | $70.70 | $73.16 | $71.00 | $80.00 | |
| 38 | 40600990 | TEMPORARY RAMP | 813 | SQ YD | $71.90 | $75.50 | $73.34 | $75.00 | |
| 39 | 40602975 | HMA BC IL-9.5FG N90 | 12,015 | TON | $94.80 | $99.58 | $96.74 | $100.00 | |
| 40 | 40603085 | HMA BC IL-19.0 N70 | 655 | TON | $202.00 | $212.50 | $206.42 | $220.00 | |
| 41 | 40604052 | HMA SC IL-9.5 C N70 | 485 | TON | $167.00 | $174.36 | $169.00 | $180.00 | |
| 42 | 40604164 | P HMA SC IL-9.5 D N90 | 671 | TON | $155.00 | $162.49 | $158.00 | $170.00 | |
| 43 | 40800050 | INCIDENTAL HMA SURF | 353 | TON | $180.00 | $189.65 | $184.00 | $200.00 | |
| 44 | 42000060 | WELDED WIRE REINF | 1,039 | SQ YD | $16.00 | $16.11 | $12.00 | $15.00 | |
| 45 | 42000080 | PVT CON PCC BR APP SL | 273 | SQ YD | $299.00 | $283.50 | $300.00 | $200.00 | |
| 46 | 42000216 | PCC PVT 7 3/4 JOINTD | 2,315 | SQ YD | $104.00 | $107.68 | $78.90 | $85.00 | |
| 47 | 42000416 | PCC PVT 9 3/4 JOINTD | 172,928 | SQ YD | $63.25 | $66.44 | $83.21 | $75.00 | |
| 48 | 42000516 | PCC PVT 10 3/4 JOINTD | 11,043 | SQ YD | $79.00 | $81.52 | $91.00 | $85.00 | |
| 49 | 44000100 | PAVEMENT REM | 13,541 | SQ YD | $22.00 | $20.55 | $22.00 | $15.00 | |
| 50 | 44000154 | HMA SURF REM 1 1/4 | 172,082 | SQ YD | $1.60 | $1.66 | $1.60 | $1.80 | |
| 51 | 44004250 | PAVED SHLD REMOVAL | 9,402 | SQ YD | $11.00 | $12.00 | $19.50 | $5.00 | |
| 52 | 44200970 | CL B PATCH T2 10 | 134 | SQ YD | $180.00 | $194.25 | $188.70 | $195.00 | |
| 53 | 44200974 | CL B PATCH T3 10 | 260 | SQ YD | $176.00 | $189.00 | $183.60 | $185.00 | |
| 54 | 44200976 | CL B PATCH T4 10 | 598 | SQ YD | $150.00 | $181.13 | $175.95 | $175.00 | |
| 55 | 44201299 | DOWEL BARS 1 1/2 | 1,260 | EACH | $26.00 | $31.58 | $30.50 | $25.00 | |
| 56 | 44213200 | SAW CUTS | 2,438 | FOOT | $8.00 | $9.02 | $9.00 | $5.00 | |
| 57 | 44213204 | TIE BARS 3/4 | 64 | EACH | $17.00 | $12.63 | $12.25 | $15.00 | |
| 58 | 48101200 | AGGREGATE SHLDS B | 9,217 | TON | $47.00 | $32.92 | $38.50 | $50.00 | |
| 59 | 48101500 | AGGREGATE SHLDS B 6 | 807 | SQ YD | $25.00 | $18.91 | $10.30 | $14.00 | |
| 60 | 48300215 | PCC SHOULDERS 7 3/4 | 1,612 | SQ YD | $99.00 | $95.81 | $119.00 | $95.00 | |
| 61 | 48300415 | PCC SHOULDERS 9 3/4 | 108,881 | SQ YD | $65.00 | $49.28 | $72.25 | $85.00 | |
| 62 | 48300515 | PCC SHOULDERS 10 3/4 | 7,149 | SQ YD | $75.00 | $58.05 | $75.60 | $95.00 | |
| 63 | 50102400 | CONC REM | 2.8 | CU YD | $5,322.00 | $6,195.00 | $4,150.00 | $5,000.00 | |
| 64 | 50104400 | CONC HDWL REM | 28 | EACH | $92.00 | $517.12 | $428.40 | $260.00 | |
| 65 | 50300255 | CONC SUP-STR | 27.4 | CU YD | $2,898.00 | $2,992.50 | $2,225.00 | $2,500.00 | |
| 66 | 50300300 | PROTECTIVE COAT | 101 | SQ YD | $4.60 | $1.05 | $12.60 | $0.0100 | |
| 67 | 50800205 | REINF BARS, EPOXY CTD | 4,650 | POUND | $5.00 | $1.30 | $3.55 | $4.50 | |
| 68 | 50900207 | STEEL RAILING TY CO-10 | 64.5 | FOOT | $290.00 | $305.33 | $324.00 | $350.00 | |
| 69 | 5421D015 | P CUL CL D 1 15 TEMP | 800 | FOOT | $55.00 | $82.95 | $61.40 | $35.00 | |
| 70 | 5421D018 | P CUL CL D 1 18 TEMP | 550 | FOOT | $60.00 | $87.98 | $71.20 | $52.00 | |
| 71 | 5421D024 | P CUL CL D 1 24 TEMP | 320 | FOOT | $76.00 | $95.43 | $85.50 | $60.00 | |
| 72 | 5421D030 | P CUL CL D 1 30 TEMP | 1,460 | FOOT | $94.00 | $121.04 | $114.00 | $65.00 | |
| 73 | 60100060 | CONC HDWL FOR P DRAIN | 28 | EACH | $400.00 | $486.90 | $473.00 | $825.00 | |
| 74 | 60108100 | PIPE UNDERDRAIN 4 SP | 1,286 | FOOT | $19.40 | $13.09 | $12.70 | $12.00 | |
| 75 | 60108104 | PIPE UNDERDR T 1 4 | 8,354 | FOOT | $19.50 | $14.41 | $14.00 | $10.00 | |
| 76 | 60260100 | INLETS ADJUST | 7 | EACH | $380.00 | $4,497.87 | $2,600.00 | $1,150.00 | |
| 77 | 60600605 | CONC CURB TB | 120 | FOOT | $109.00 | $74.80 | $71.15 | $50.00 | |
| 78 | 63000001 | SPBGR TY A 6FT POSTS | 13,418 | FOOT | $28.00 | $29.48 | $31.62 | $30.00 | |
| 79 | 63100045 | TRAF BAR TERM T2 | 15 | EACH | $1,600.00 | $1,684.56 | $1,856.40 | $1,850.00 | |
| 80 | 63100085 | TRAF BAR TERM T6 | 5 | EACH | $4,000.00 | $4,211.41 | $4,549.20 | $4,700.00 | |
| 81 | 63100119 | TRAF BAR TERM T14 | 6 | EACH | $5,800.00 | $6,106.54 | $4,758.30 | $6,800.00 | |
| 82 | 63100167 | TR BAR TRM T1 SPL TAN | 28 | EACH | $3,100.00 | $3,263.84 | $3,498.60 | $3,600.00 | |
| 83 | 63200310 | GUARDRAIL REMOV | 14,159 | FOOT | $4.40 | $4.63 | $5.45 | $3.50 | |
| 84 | 63500105 | DELINEATORS | 258 | EACH | $84.00 | $265.93 | $87.72 | $115.00 | |
| 85 | 63700180 | CONC BAR 1F 44HT | 20 | FOOT | $525.00 | $840.00 | $355.00 | $300.00 | |
| 86 | 63700805 | CONC BAR TRANS | 10 | FOOT | $1,003.00 | $945.00 | $555.00 | $175.00 | |
| 87 | 63700900 | CONC BARRIER BASE | 30 | FOOT | $400.00 | $367.50 | $55.00 | $100.00 | |
| 88 | 64200116 | SHOULDER RUM STRIP 16 | 129,030 | FOOT | $0.2500 | $0.2800 | $0.1500 | $0.2400 | |
| 89 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,400.00 | $2,281.68 | $2,400.00 | $2,000.00 | |
| 90 | 67100100 | MOBILIZATION | 1 | L SUM | $2,136,676.00 | $2,982,400.96 | $2,282,370.18 | $2,800,000.00 | |
| 91 | 70100410 | TRAF CONT-PROT 701416 | 1 | EACH | $534,673.00 | $90,013.52 | $326,678.28 | $1,500,000.00 | |
| 92 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $0.0100 | $151,770.34 | $0.0100 | $0.0100 | |
| 93 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $136,114.09 | $194,584.00 | $343,000.00 | $500,000.00 | |
| 94 | 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $31,710.66 | $32,586.96 | $58,700.00 | $150,000.00 | |
| 95 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $0.0100 | $11,982.18 | $0.0100 | $0.0100 | |
| 96 | 70107025 | CHANGEABLE MESSAGE SN | 112 | CAL DA | $158.13 | $73.05 | $81.60 | $115.00 | |
| 97 | 70300150 | SHRT TRM PAVT MK REM | 1,114 | SQ FT | $8.00 | $8.40 | $3.06 | $1.00 | |
| 98 | 70306120 | TEMP PVT MK L4 T3 TAPE | 18,366 | FOOT | $0.0100 | $1.58 | $2.43 | $0.0100 | |
| 99 | 70400100 | TEMP CONC BARRIER | 68,758 | FOOT | $68.00 | $71.40 | $76.00 | $70.00 | |
| 100 | 70500100 | TEMP SPBGR TY A | 238 | FOOT | $30.00 | $31.59 | $37.74 | $31.00 | |
| 101 | 70500615 | TEMP TR BAR TERM T1 | 1 | EACH | $3,500.00 | $3,684.99 | $2,065.50 | $4,100.00 | |
| 102 | 70500625 | TEMP TR BAR TERM T2 | 1 | EACH | $1,500.00 | $1,579.27 | $2,397.00 | $1,750.00 | |
| 103 | 72501000 | TERMINAL MARKER - DA | 29 | EACH | $50.00 | $52.64 | $43.00 | $60.00 | |
| 104 | 78001110 | PAINT PVT MK LINE 4 | 273,563 | FOOT | $0.0100 | $0.3000 | $0.2700 | $0.6000 | |
| 105 | 78001140 | PAINT PVT MK LINE 8 | 3,870 | FOOT | $0.5500 | $0.6100 | $0.5500 | $3.30 | |
| 106 | 78009000 | MOD URETH PM LTR-SYM | 998 | SQ FT | $15.00 | $16.83 | $15.30 | $13.50 | |
| 107 | 78009006 | MOD URETH PM LINE 6 | 317,757 | FOOT | $1.30 | $1.46 | $1.32 | $1.25 | |
| 108 | 78009008 | MOD URETH PM LINE 8 | 4,138 | FOOT | $3.00 | $3.37 | $3.00 | $5.00 | |
| 109 | 78009024 | MOD URETH PM LINE 24 | 94 | FOOT | $20.00 | $22.44 | $20.40 | $13.50 | |
| 110 | 78100100 | RAISED REFL PAVT MKR | 963 | EACH | $35.40 | $37.13 | $36.00 | $95.00 | |
| 111 | 78112000 | RAISED REFL PAVT MKR BRDG | 8 | EACH | $48.35 | $126.00 | $51.00 | $125.00 | |
| 112 | 78200005 | GRDRAIL REF TYPE A | 155 | EACH | $10.00 | $10.53 | $11.00 | $10.00 | |
| 113 | 78300200 | RAISED REF PVT MK REM | 971 | EACH | $9.60 | $10.08 | $10.00 | $10.00 | |
| 114 | 78300201 | PAVMT MRKG REM GRIND | 147,917 | SQ FT | $0.8000 | $0.8400 | $0.7700 | $0.0100 |