$1,810.60Avg low bid / EACH
$1,591.14Avg of all bids
—Avg engineer's estimate
4Jobs · 6 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 2 | $1,500.78 | $1,413.39 |
| 2025 | 3 | 4 | $1,965.51 | $1,720.41 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Apr 24, 2026 | 62K33 | CookDistrict 1 | 2 EACH | $1,500.78 | Plote Construction, Inc. |
| Sep 19, 2025 | 74597 | CumberlandDistrict 7 | 2 EACH | $1,506.02 | William Charles Construction Company, LLC |
| Apr 25, 2025 | 62W87 | CookDistrict 1 | 1 EACH | $1,600.00 | Lorig Construction Company |
| Mar 7, 2025 | 64N01 | WhitesideDistrict 2 | 1 EACH | $3,250.00 | Civil Constructors, Inc. d/b/a/ Helm Civil |