D7 BRIDGE PAINTING 2026-2
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Eagle Painting & Maintenance Company, Inc. Low bidder | $669,591 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $723,650 | +8.1% | |
| 3 | Civil Coatings and Construction Inc. | $843,923 | +26.0% | |
| 4 | Three Star Painting, Inc. | $865,700 | +29.3% | |
| 5 | Venus Painting Co. | $1,199,845 | +79.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Eagle Painting … | #2 ERA-Valdivia Co… | #3 Civil Coatings … | #4 Three Star Pain… | #5 Venus Painting … |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $23,500.00 | $49,080.00 | $1,000.00 | $7,500.00 | $28,565.00 | |
| 2 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $27,500.00 | $52,065.00 | $1,000.00 | $7,500.00 | $28,565.00 | |
| 3 | Z0007103 | C&D LEAD PT CL RS N3 | 1 | L SUM | $27,500.00 | $52,065.00 | $1,000.00 | $7,500.00 | $28,565.00 | |
| 4 | Z0007104 | C&D LEAD PT CL RS N4 | 1 | L SUM | $27,300.00 | $51,345.00 | $1,000.00 | $7,500.00 | $28,565.00 | |
| 5 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $84,140.00 | $116,319.60 | $164,402.00 | $213,000.00 | $222,106.88 | |
| 6 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $101,200.00 | $123,394.05 | $164,402.00 | $165,000.00 | $262,999.88 | |
| 7 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $101,200.00 | $123,394.05 | $164,402.00 | $165,000.00 | $262,999.88 | |
| 8 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $98,300.00 | $121,687.65 | $164,405.80 | $213,000.00 | $247,778.10 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $32,500.00 | $25,000.00 | $42,000.00 | $56,800.00 | $66,000.00 | |
| 10 | 70100207 | TRAF CONT-PROT 701402 | 4 | EACH | $27,300.00 | $1,000.00 | $18,750.00 | $2,500.00 | $250.00 | |
| 11 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1.00 | $100.00 | $10.00 | $2,500.00 | $5,000.00 | |
| 12 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $1,650.00 | $100.00 | $500.00 | $2,500.00 | $3,000.00 | |
| 13 | 70400100 | TEMP CONC BARRIER | 1,200 | FOOT | $15.50 | $2.50 | $32.00 | $1.00 | $5.00 | |
| 14 | 70400125 | PIN TEMP CONC BARRIER | 100 | EACH | $12.00 | $1.00 | $0.0100 | $10.00 | $1.00 | |
| 15 | 70400200 | REL TEMP CONC BARRIER | 1,200 | FOOT | $2.00 | $1.00 | $15.00 | $1.00 | $3.00 | |
| 16 | 70600251 | IMP ATTN TEMP NRN TL3 | 4 | EACH | $2,350.00 | $100.00 | $1,500.00 | $750.00 | $750.00 | |
| 17 | 70600350 | IMP ATTN REL NRD TL3 | 4 | EACH | $1,000.00 | $100.00 | $600.00 | $375.00 | $500.00 |