| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 9 | 9 | $51,297.72 | $30,043.02 |
| 2025 | 4 | 4 | $16,310.00 | $16,961.68 |
| 2024 | 1 | 1 | $8,900.00 | $29,266.67 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 76R36 | St. ClairDistrict 8 | 1 L SUM | $158,000.00 | The Kilian Corporation |
| Apr 24, 2026 | 80B54 | DupageDistrict 1 | 1 L SUM | $46,870.00 | ERA-Valdivia Contractors, Inc. |
| Apr 24, 2026 | 74D61 | VariousDistrict 7 | 1 L SUM | $42,885.15 | ERA-Valdivia Contractors, Inc. |
| Apr 24, 2026 | 74D63 | WayneDistrict 7 | 1 L SUM | $27,300.00 | Eagle Painting & Maintenance Company, Inc. |
| Feb 27, 2026 | 64U96 | Rock IslandDistrict 2 | 1 L SUM | $14,297.00 | Eagle Painting & Maintenance Company, Inc. |
| Feb 27, 2026 | 64U97 | Rock Island WhitesideDistrict 2 | 1 L SUM | $18,850.00 | Venus Painting Co. |
| Feb 27, 2026 | 68K62 | VariousDistrict 4 | 1 L SUM | $23,149.09 | Venus Painting Co. |
| Jan 16, 2026 | 72A25 | Pike, ScottDistrict 6 | 1 L SUM | $2,500.00 | Three Star Painting, Inc. |
| Jan 16, 2026 | 70H59 | ChampaignDistrict 5 | 1 L SUM | $127,828.25 | ERA-Valdivia Contractors, Inc. |
| Nov 7, 2025 | 78B82 | VariousDistrict 9 | 1 L SUM | $9,240.00 | Eagle Painting & Maintenance Company, Inc. |
| Apr 25, 2025 | 70H47 | VariousDistrict 5 | 1 L SUM | $1,000.00 | Three Star Painting, Inc. |
| Mar 7, 2025 | 74D01 | FayetteDistrict 7 | 1 L SUM | $37,000.00 | Eagle Painting & Maintenance Company, Inc. |
| Mar 7, 2025 | 76R99 | St. ClairDistrict 8 | 1 L SUM | $18,000.00 | The Kilian Corporation and Christ Brothers Asphalt |
| Dec 13, 2024 | 64N05 | HenryDistrict 2 | 1 L SUM | $8,900.00 | Civil Constructors d/b/a Helm Civil and Phoenix Corporation of the Quad Cities |