D7 BRIDGE PAINTING 2021-4
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Venus Painting Co. Low bidder | $856,700 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $986,600 | +15.2% | |
| 3 | Three Star Painting, Inc. | $1,036,820 | +21.0% | |
| 4 | All States Painting, Inc. | $1,094,000 | +27.7% | |
| 5 | Eagle Painting & Maintenance Company, Inc. | $1,103,573 | +28.8% | |
| 6 | Civil Coatings and Construction Inc. | $1,230,765 | +43.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Venus Painting … | #2 ERA-Valdivia Co… | #3 Three Star Pain… | #4 All States Pain… | #5 Eagle Painting … | #6 Civil Coatings … |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7040125 | PIN TEMP CONC BARRIER | 120 | EACH | $10.00 | $20.00 | $10.00 | $1.00 | $10.00 | $5.00 | |
| 2 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $5,000.00 | $55,400.00 | $2,500.00 | $7,000.00 | $17,000.00 | $1,000.00 | |
| 3 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $5,000.00 | $55,400.00 | $2,500.00 | $7,000.00 | $17,000.00 | $1,000.00 | |
| 4 | Z0007103 | C&D LEAD PT CL RS N3 | 1 | L SUM | $5,000.00 | $36,600.00 | $2,500.00 | $12,000.00 | $40,000.00 | $1,000.00 | |
| 5 | Z0007104 | C&D LEAD PT CL RS N4 | 1 | L SUM | $5,000.00 | $31,410.00 | $2,500.00 | $12,000.00 | $30,000.00 | $1,000.00 | |
| 6 | Z0007105 | C&D LEAD PT CL RS N5 | 1 | L SUM | $5,000.00 | $30,240.00 | $2,500.00 | $12,000.00 | $30,000.00 | $1,000.00 | |
| 7 | Z0007106 | C&D LEAD PT CL RS N6 | 1 | L SUM | $5,000.00 | $30,900.00 | $2,500.00 | $12,000.00 | $30,000.00 | $1,000.00 | |
| 8 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $80,000.00 | $83,100.00 | $61,243.17 | $117,540.00 | $68,000.00 | $111,000.00 | |
| 9 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $80,000.00 | $83,100.00 | $61,243.17 | $117,540.00 | $68,000.00 | $111,000.00 | |
| 10 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $156,000.00 | $134,200.00 | $223,087.17 | $160,000.00 | $150,000.00 | $220,000.00 | |
| 11 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $135,000.00 | $115,170.00 | $183,757.17 | $160,000.00 | $140,000.00 | $220,000.00 | |
| 12 | Z0010505 | CLEAN & PT STL BR N5 | 1 | L SUM | $145,000.00 | $110,880.00 | $191,173.17 | $160,000.00 | $130,000.00 | $220,000.00 | |
| 13 | Z0010506 | CLEAN & PT STL BR N6 | 1 | L SUM | $145,000.00 | $113,300.00 | $183,775.17 | $160,000.00 | $130,000.00 | $220,000.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $45,000.00 | $45,000.00 | $51,841.00 | $60,000.00 | $50,000.00 | $50,000.00 | |
| 15 | 70100207 | TRAF CONT-PROT 701402 | 8 | EACH | $1,000.00 | $1,500.00 | $2,000.00 | $2,000.00 | $17,925.00 | $5,850.00 | |
| 16 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $3,000.00 | $500.00 | $8,000.00 | $5,000.00 | $360.00 | $360.00 | |
| 17 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $3,000.00 | $500.00 | $8,000.00 | $5,000.00 | $1.00 | $5.00 | |
| 18 | 70400100 | TEMP CONC BARRIER | 1,100 | FOOT | $10.00 | $20.00 | $20.00 | $12.00 | $20.00 | $5.00 | |
| 19 | 70400200 | REL TEMP CONC BARRIER | 3,300 | FOOT | $1.00 | $5.00 | $1.00 | $12.00 | $10.00 | $3.00 | |
| 20 | 70600250 | IMP ATTN TEMP NRD TL3 | 4 | EACH | $1,300.00 | $500.00 | $1,500.00 | $3,000.00 | $900.00 | $900.00 | |
| 21 | 70600350 | IMP ATTN REL NRD TL3 | 12 | EACH | $500.00 | $500.00 | $100.00 | $500.00 | $1.00 | $500.00 |