$58,048.74Avg low bid / L SUM
$30,136.59Avg of all bids
—Avg engineer's estimate
5Jobs · 5 L SUM
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 4 | 4 | $70,250.92 | $35,207.12 |
| 2025 | 1 | 1 | $9,240.00 | $14,925.00 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Apr 24, 2026 | 74D61 | VariousDistrict 7 | 1 L SUM | $41,980.60 | ERA-Valdivia Contractors, Inc. |
| Feb 27, 2026 | 68K62 | VariousDistrict 4 | 1 L SUM | $23,149.09 | Venus Painting Co. |
| Jan 16, 2026 | 76E84 | Madison, St.clairDistrict 8 | 1 L SUM | $24,100.00 | The Kilian Corporation & Christ Brothers Asphalt & Keeley & Sons, Inc. tri-venture |
| Jan 16, 2026 | 70H59 | ChampaignDistrict 5 | 1 L SUM | $191,774.00 | ERA-Valdivia Contractors, Inc. |
| Nov 7, 2025 | 78B82 | VariousDistrict 9 | 1 L SUM | $9,240.00 | Eagle Painting & Maintenance Company, Inc. |