(11BR,10B-1,10B-5)BDR
- Let date
- Friday, June 12, 2026
- Contract
- 72J76 · job page
- District
- District 6
- County
- Schuyler
- Highway
- Limits
- Microsilica concrete overlays on IL 99 at Cedar Creek 0.5 miles north of Camden and Missouri Creek and Little Missouri Creek 1 mile and 0.3 miles north of the Brown County line. (085-0031, 085-0030, and 085-0029)
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $1,870,400 | ||
| 2 | Freesen, a div of UCM, Inc. | $1,924,874 | +2.9% | |
| 3 | County Contractors, Inc. | $1,960,022 | +4.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Freesen, a div … | #3 County Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2020060 | EXC & GR EX SHLD SPL | 14 | UNIT | $2,911.76 | $5,289.16 | $1,100.00 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 426 | SQ YD | $15.80 | $97.15 | $20.00 | |
| 3 | X5030250 | BR DECK GROOVING LONG | 1,926 | SQ YD | $16.05 | $13.58 | $11.00 | |
| 4 | X5230190 | DRAINAGE SCUPPR DS-33 | 6 | EACH | $5,884.64 | $3,870.11 | $4,545.00 | |
| 5 | X6010003 | PIPE DRAIN REMOVAL | 50 | FOOT | $31.31 | $31.18 | $30.00 | |
| 6 | X6050222 | FILL INLETS TEMPORARY | 2 | EACH | $3,403.98 | $1,710.96 | $3,575.00 | |
| 7 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $2,632.72 | $2,625.00 | $4,375.00 | |
| 8 | Z0001495 | BR APPROACH SHLD REM | 81 | SQ YD | $131.55 | $132.20 | $105.00 | |
| 9 | Z0041895 | POLYMER CONCRETE | 5.9 | CU FT | $1,655.16 | $1,441.78 | $1,300.00 | |
| 10 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 12 | 28100105 | STONE RIPRAP CL A3 | 34 | SQ YD | $66.48 | $56.29 | $73.00 | |
| 13 | 28200200 | FILTER FABRIC | 34 | SQ YD | $18.30 | $11.03 | $8.00 | |
| 14 | 40600290 | BIT MATLS TACK CT | 1,165 | POUND | $12.64 | $3.50 | $13.00 | |
| 15 | 40600982 | HMA SURF REM BUTT JT | 623 | SQ YD | $15.80 | $23.27 | $16.00 | |
| 16 | 40600990 | TEMPORARY RAMP | 506 | SQ YD | $46.48 | $23.59 | $28.00 | |
| 17 | 40604050 | HMA SC IL-9.5 C N50 | 254 | TON | $311.71 | $308.94 | $315.00 | |
| 18 | 44000156 | HMA SURF REM 1 3/4 | 1,968 | SQ YD | $15.80 | $23.26 | $16.00 | |
| 19 | 44004250 | PAVED SHLD REMOVAL | 12 | SQ YD | $139.22 | $133.86 | $125.00 | |
| 20 | 44201292 | DOWEL BARS 5/8 | 68 | EACH | $55.20 | $49.37 | $46.00 | |
| 21 | 48102100 | AGG WEDGE SHLD TYPE B | 64 | TON | $82.82 | $219.83 | $98.00 | |
| 22 | 48203029 | HMA SHOULDERS 8 | 636 | SQ YD | $126.37 | $157.36 | $127.00 | |
| 23 | 48203100 | HMA SHOULDERS | 80 | TON | $446.51 | $498.68 | $448.00 | |
| 24 | 48300500 | PCC SHOULDERS 10 | 89.6 | SQ YD | $200.25 | $219.97 | $260.00 | |
| 25 | 50102400 | CONC REM | 5.5 | CU YD | $5,278.74 | $3,834.10 | $4,600.00 | |
| 26 | 50300255 | CONC SUP-STR | 5.9 | CU YD | $6,155.83 | $4,745.28 | $6,750.00 | |
| 27 | 50300300 | PROTECTIVE COAT | 2,816 | SQ YD | $2.87 | $3.93 | $7.60 | |
| 28 | 50800205 | REINF BARS, EPOXY CTD | 14,670 | POUND | $2.16 | $2.01 | $3.35 | |
| 29 | 50800515 | BAR SPLICERS | 12 | EACH | $73.54 | $58.94 | $110.00 | |
| 30 | 52000110 | PREF JT STRIP SEAL | 69 | FOOT | $251.21 | $327.70 | $350.00 | |
| 31 | 53016002 | DECK SLAB REP (FD-T2) | 20 | SQ YD | $1,194.89 | $1,256.60 | $1,350.00 | |
| 32 | 53101002 | BR DECK SCAR 3/4 | 2,483 | SQ YD | $80.38 | $78.53 | $88.00 | |
| 33 | 53101609 | BR DK MIC C OVL 2 1/2 | 2,545 | SQ YD | $125.83 | $157.45 | $145.00 | |
| 34 | 54262712 | METAL FL END SEC 12" | 2 | EACH | $756.49 | $401.45 | $610.00 | |
| 35 | 60100945 | PIPE DRAINS 12 | 10 | FOOT | $95.06 | $46.77 | $165.00 | |
| 36 | 61000335 | TY G INLET BOX 610001 | 2 | EACH | $4,453.97 | $4,008.08 | $3,930.00 | |
| 37 | 63000001 | SPBGR TY A 6FT POSTS | 1,525 | FOOT | $36.12 | $36.02 | $36.00 | |
| 38 | 63100085 | TRAF BAR TERM T6 | 12 | EACH | $4,670.44 | $4,656.75 | $4,680.00 | |
| 39 | 63100167 | TR BAR TRM T1 SPL TAN | 12 | EACH | $3,985.93 | $3,974.25 | $3,995.00 | |
| 40 | 63200310 | GUARDRAIL REMOV | 2,177 | FOOT | $6.55 | $5.97 | $6.00 | |
| 41 | 66201120 | CONC SHLD CURB | 20 | FOOT | $103.58 | $87.34 | $115.00 | |
| 42 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $1,333.56 | $4,043.66 | $2,750.00 | |
| 43 | 67100100 | MOBILIZATION | 1 | L SUM | $226,541.34 | $40,462.93 | $116,500.00 | |
| 44 | 70100405 | TRAF CONT-PROT 701321 | 3 | EACH | $7,055.68 | $22,217.07 | $26,500.00 | |
| 45 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $105.31 | $105.00 | $2,500.00 | |
| 46 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $8,108.76 | $8,085.00 | $5,500.00 | |
| 47 | 70103815 | TR CONT SURVEILLANCE | 14 | CAL DA | $347.62 | $1.69 | $350.00 | |
| 48 | 70106500 | TEMP BR TRAF SIGNALS | 3 | EACH | $23,209.22 | $26,347.36 | $24,000.00 | |
| 49 | 70106700 | TEMP RUMBLE STRIPS | 18 | EACH | $822.05 | $1,006.70 | $975.00 | |
| 50 | 70107005 | PAVT MK BLKOUT TAPE 5 | 2,252.5 | FOOT | $1.97 | $4.82 | $3.00 | |
| 51 | 70107025 | CHANGEABLE MESSAGE SN | 360 | CAL DA | $73.72 | $73.50 | $95.00 | |
| 52 | 70300100 | SHORT TERM PAVT MKING | 341 | FOOT | $1.64 | $1.59 | $2.25 | |
| 53 | 70300150 | SHRT TRM PAVT MK REM | 57 | SQ FT | $4.81 | $2.09 | $15.00 | |
| 54 | 70400100 | TEMP CONC BARRIER | 1,522.5 | FOOT | $35.55 | $38.35 | $44.00 | |
| 55 | 70400200 | REL TEMP CONC BARRIER | 1,522.5 | FOOT | $8.26 | $3.98 | $10.50 | |
| 56 | 70600260 | IMP ATTN TEMP FRN TL3 | 6 | EACH | $9,100.00 | $8,477.51 | $11,500.00 | |
| 57 | 70600332 | IMP ATTN REL FRN TL3 | 8 | EACH | $500.00 | $4,015.21 | $3,500.00 | |
| 58 | 72501000 | TERMINAL MARKER - DA | 12 | EACH | $52.65 | $52.50 | $53.00 | |
| 59 | 78009005 | MOD URETH PM LINE 5 | 5,406 | FOOT | $3.90 | $2.42 | $3.25 | |
| 60 | 78100100 | RAISED REFL PAVT MKR | 19 | EACH | $444.96 | $236.25 | $237.50 | |
| 61 | 78200005 | GRDRAIL REF TYPE A | 40 | EACH | $10.53 | $10.50 | $10.50 | |
| 62 | 78300200 | RAISED REF PVT MK REM | 19 | EACH | $43.31 | $16.27 | $21.00 |