D5 BRIDGE PAINTING 2023-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | ERA-Valdivia Contractors, Inc. Low bidder | $2,159,568 | ||
| 2 | Venus Painting Co. | $2,208,908 | +2.3% | |
| 3 | Civil Coatings and Construction Inc. | $2,383,923 | +10.4% | |
| 4 | Three Star Painting, Inc. | $2,536,000 | +17.4% | |
| 5 | Royal Bridge, Inc. | $4,179,700 | +93.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ERA-Valdivia Co… | #2 Venus Painting … | #3 Civil Coatings … | #4 Three Star Pain… | #5 Royal Bridge, I… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327271 | TRAF CONT RD CLOSURE | 1 | EACH | $1,500.00 | $10,000.00 | $7,500.00 | $5,000.00 | $6,000.00 | |
| 2 | X2700001 | TEMP RUMBLE STRIPS SP | 96 | EACH | $100.00 | $150.00 | $420.00 | $1,000.00 | $1,500.00 | |
| 3 | X5067501 | BR CLN & PT WAR #1 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 4 | X5067502 | BR CLN & PT WAR #2 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 5 | X5067503 | BR CLN & PT WAR #3 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 6 | X5067504 | BR CLN & PT WAR #4 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 7 | X5067505 | BR CLN & PT WAR #5 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 8 | X5067506 | BR CLN & PT WAR #6 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 9 | X5067507 | BR CLN & PT WAR #7 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 10 | X5067508 | BR CLN & PT WAR #8 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 11 | X5067509 | BR CLN & PT WAR #9 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 12 | X5067510 | BR CLN & PT WAR #10 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 13 | X5067511 | BR CLN & PT WAR #11 | 1 | L SUM | $1,500.00 | $600.00 | $500.00 | $500.00 | $10,000.00 | |
| 14 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $88,596.00 | $6,000.00 | $1,000.00 | $2,000.00 | $85,000.00 | |
| 15 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $88,596.00 | $6,000.00 | $1,000.00 | $2,000.00 | $85,000.00 | |
| 16 | Z0007103 | C&D LEAD PT CL RS N3 | 1 | L SUM | $87,822.00 | $6,000.00 | $1,000.00 | $2,000.00 | $85,000.00 | |
| 17 | Z0007104 | C&D LEAD PT CL RS N4 | 1 | L SUM | $91,845.00 | $6,000.00 | $1,000.00 | $2,000.00 | $95,000.00 | |
| 18 | Z0007105 | C&D LEAD PT CL RS N5 | 1 | L SUM | $176,850.00 | $6,000.00 | $1,000.00 | $2,000.00 | $155,000.00 | |
| 19 | Z0007106 | C&D LEAD PT CL RS N6 | 1 | L SUM | $92,682.00 | $6,000.00 | $1,000.00 | $2,000.00 | $100,000.00 | |
| 20 | Z0007107 | C&D LEAD PT CL RS N7 | 1 | L SUM | $92,682.00 | $6,000.00 | $1,000.00 | $2,000.00 | $100,000.00 | |
| 21 | Z0007108 | C&D LEAD PT CL RS N8 | 1 | L SUM | $113,337.00 | $6,000.00 | $1,000.00 | $2,000.00 | $100,000.00 | |
| 22 | Z0007109 | C&D LEAD PT CL RS N9 | 1 | L SUM | $240,975.00 | $6,000.00 | $1,000.00 | $2,000.00 | $215,000.00 | |
| 23 | Z0007110 | C&D LEAD PT CL RS N10 | 1 | L SUM | $82,548.00 | $6,000.00 | $1,000.00 | $2,000.00 | $85,000.00 | |
| 24 | Z0007111 | C&D LEAD PT CL RS N11 | 1 | L SUM | $86,346.00 | $6,000.00 | $1,000.00 | $2,000.00 | $85,000.00 | |
| 25 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $49,220.00 | $145,830.00 | $120,053.00 | $147,492.00 | $142,000.00 | |
| 26 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $49,220.00 | $145,830.00 | $120,053.00 | $147,492.00 | $142,000.00 | |
| 27 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $48,790.00 | $150,840.00 | $130,650.00 | $160,888.00 | $142,000.00 | |
| 28 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $51,025.00 | $160,416.00 | $137,072.00 | $160,000.00 | $162,000.00 | |
| 29 | Z0010505 | CLEAN & PT STL BR N5 | 1 | L SUM | $98,250.00 | $250,225.00 | $228,150.00 | $282,115.00 | $273,000.00 | |
| 30 | Z0010506 | CLEAN & PT STL BR N6 | 1 | L SUM | $51,490.00 | $155,720.00 | $151,844.00 | $172,000.00 | $173,000.00 | |
| 31 | Z0010507 | CLEAN & PT STL BR N7 | 1 | L SUM | $51,490.00 | $155,720.00 | $151,844.00 | $172,000.00 | $173,000.00 | |
| 32 | Z0010508 | CLEAN & PT STL BR N8 | 1 | L SUM | $62,965.00 | $150,787.00 | $151,750.00 | $192,984.00 | $162,000.00 | |
| 33 | Z0010509 | CLEAN & PT STL BR N9 | 1 | L SUM | $133,875.00 | $300,428.00 | $302,703.00 | $409,000.00 | $382,866.00 | |
| 34 | Z0010510 | CLEAN & PT STL BR N10 | 1 | L SUM | $45,860.00 | $145,256.00 | $110,098.00 | $163,496.50 | $142,000.00 | |
| 35 | Z0010511 | CLEAN & PT STL BR N11 | 1 | L SUM | $47,970.00 | $145,256.00 | $103,986.00 | $150,795.50 | $143,000.00 | |
| 36 | 67100100 | MOBILIZATION | 1 | L SUM | $100,000.00 | $100,000.00 | $105,000.00 | $117,717.00 | $250,000.00 | |
| 37 | 70100207 | TRAF CONT-PROT 701402 | 36 | EACH | $1,000.00 | $1,000.00 | $9,800.00 | $1,500.00 | $3,194.28 | |
| 38 | 70107025 | CHANGEABLE MESSAGE SN | 48 | CAL DA | $88.00 | $100.00 | $125.00 | $40.00 | $80.00 | |
| 39 | 70400100 | TEMP CONC BARRIER | 5,400 | FOOT | $5.00 | $6.00 | $23.00 | $10.00 | $20.00 | |
| 40 | 70400200 | REL TEMP CONC BARRIER | 5,400 | FOOT | $2.50 | $3.00 | $1.00 | $3.00 | $10.00 | |
| 41 | 70600250 | IMP ATTN TEMP NRD TL3 | 18 | EACH | $770.00 | $600.00 | $800.00 | $200.00 | $7,000.00 | |
| 42 | 70600350 | IMP ATTN REL NRD TL3 | 18 | EACH | $275.00 | $300.00 | $200.00 | $100.00 | $2,000.00 |