D4 BRIDGE DECK OVERLAY 2025
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $2,366,430 | ||
| 2 | Stark Excavating, Inc. | $2,499,743 | +5.6% | |
| 3 | Brandt Construction Co. | $2,693,250 | +13.8% | |
| 4 | Laverdiere Construction, Inc. | $3,053,691 | +29.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 Stark Excavatin… | #3 Brandt Construc… | #4 Laverdiere Cons… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326444 | SURFACE FILLER SPL | 4 | GALLON | $1,725.49 | $1,200.00 | $1,500.00 | $1,510.00 | |
| 2 | X1300003 | CLEAN APP SLAB DRAIN | 4 | EACH | $349.65 | $375.00 | $2,500.00 | $2,000.00 | |
| 3 | X4404400 | PAVT REMOVAL SPL | 129 | SQ YD | $56.53 | $165.00 | $40.00 | $80.00 | |
| 4 | X5030550 | PROTECTIVE COAT SPL | 668 | SQ YD | $66.48 | $46.00 | $60.00 | $24.00 | |
| 5 | Z0001002 | GDRL AGG EROS CONT | 943 | TON | $127.57 | $95.00 | $105.00 | $69.00 | |
| 6 | Z0012130 | BR DECK SCAR 3/4 | 2,456 | SQ YD | $78.23 | $84.00 | $120.00 | $78.00 | |
| 7 | Z0012162 | BR DK MIC C OVL 2 1/4 | 2,456 | SQ YD | $143.80 | $170.00 | $180.00 | $203.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $7,577.54 | $16,250.00 | $15,000.00 | $11,500.00 | |
| 9 | Z0041895 | POLYMER CONCRETE | 10.3 | CU FT | $1,678.54 | $1,500.00 | $4,500.00 | $1,066.00 | |
| 10 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 12 | 20200600 | EXC & GR EX SHOULDER | 18 | UNIT | $3,577.42 | $1,650.00 | $2,300.00 | $3,935.00 | |
| 13 | 30300112 | AGG SUBGRADE IMPR 12 | 721 | SQ YD | $109.03 | $56.00 | $77.00 | $125.00 | |
| 14 | 40600295 | P BIT MATLS TACK CT | 2,585 | POUND | $7.74 | $8.75 | $1.00 | $9.00 | |
| 15 | 40600982 | HMA SURF REM BUTT JT | 1,860 | SQ YD | $58.40 | $65.00 | $45.00 | $65.00 | |
| 16 | 40600990 | TEMPORARY RAMP | 297 | SQ YD | $69.50 | $75.00 | $105.00 | $90.00 | |
| 17 | 40603205 | P HMA BC IL-9.5 N50 | 145.1 | TON | $885.75 | $1,000.00 | $665.00 | $1,019.00 | |
| 18 | 40604160 | P HMA SC IL-9.5 D N50 | 156.5 | TON | $833.07 | $950.00 | $665.00 | $958.00 | |
| 19 | 44000300 | CURB REM | 240 | FOOT | $12.22 | $30.00 | $60.00 | $25.00 | |
| 20 | 44004250 | PAVED SHLD REMOVAL | 721 | SQ YD | $88.34 | $38.00 | $45.00 | $102.00 | |
| 21 | 44201809 | CL D PATCH T4 13 | 132 | SQ YD | $507.04 | $600.00 | $765.00 | $634.00 | |
| 22 | 48203029 | HMA SHOULDERS 8 | 721 | SQ YD | $206.08 | $235.00 | $170.00 | $250.00 | |
| 23 | 50300260 | BR DECK GROOVING | 2,317 | SQ YD | $14.23 | $12.50 | $8.50 | $15.00 | |
| 24 | 50300300 | PROTECTIVE COAT | 2,459 | SQ YD | $4.61 | $6.00 | $12.00 | $5.00 | |
| 25 | 60260100 | INLETS ADJUST | 10 | EACH | $1,457.00 | $2,000.00 | $3,100.00 | $1,257.00 | |
| 26 | 60600605 | CONC CURB TB | 240 | FOOT | $68.43 | $100.00 | $95.00 | $73.00 | |
| 27 | 63000001 | SPBGR TY A 6FT POSTS | 2,439 | FOOT | $33.60 | $37.00 | $35.00 | $40.00 | |
| 28 | 63100085 | TRAF BAR TERM T6 | 16 | EACH | $3,570.00 | $3,800.00 | $3,820.00 | $4,250.00 | |
| 29 | 63100167 | TR BAR TRM T1 SPL TAN | 14 | EACH | $2,835.00 | $3,000.00 | $3,035.00 | $3,375.00 | |
| 30 | 63100169 | TR BAR TRM T1 SPL FLR | 2 | EACH | $2,835.00 | $3,000.00 | $3,035.00 | $3,375.00 | |
| 31 | 63200310 | GUARDRAIL REMOV | 3,428 | FOOT | $8.08 | $6.75 | $15.00 | $17.00 | |
| 32 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,583.06 | $2,500.00 | $4,000.00 | $3,350.00 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $106,188.05 | $149,980.00 | $140,000.00 | $280,000.00 | |
| 34 | 70100405 | TRAF CONT-PROT 701321 | 4 | EACH | $10,500.00 | $15,000.00 | $9,000.00 | $10,000.00 | |
| 35 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $997.50 | $1,200.00 | $10.00 | $30,160.00 | |
| 36 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $997.50 | $1,075.00 | $10.00 | $3,800.00 | |
| 37 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $997.50 | $2,550.00 | $10.00 | $4,800.00 | |
| 38 | 70103815 | TR CONT SURVEILLANCE | 240 | CAL DA | $1.51 | $0.0100 | $400.00 | $0.0100 | |
| 39 | 70106500 | TEMP BR TRAF SIGNALS | 4 | EACH | $18,643.54 | $17,500.00 | $35,000.00 | $50,000.00 | |
| 40 | 70106700 | TEMP RUMBLE STRIPS | 24 | EACH | $914.04 | $1,500.00 | $1,100.00 | $1,200.00 | |
| 41 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $78.75 | $150.00 | $140.00 | $174.00 | |
| 42 | 70300100 | SHORT TERM PAVT MKING | 593 | FOOT | $1.69 | $2.75 | $2.25 | $4.00 | |
| 43 | 70300150 | SHRT TRM PAVT MK REM | 199 | SQ FT | $5.08 | $2.75 | $4.50 | $2.00 | |
| 44 | 70307120 | TEMP PVT MK L4 T4 TAPE | 8,670 | FOOT | $2.39 | $1.55 | $2.25 | $1.75 | |
| 45 | 70307210 | TEMP PVT MK L24 T4 TAPE | 192 | FOOT | $15.73 | $10.75 | $5.50 | $11.00 | |
| 46 | 70400100 | TEMP CONC BARRIER | 1,662.5 | FOOT | $34.25 | $47.00 | $40.00 | $61.00 | |
| 47 | 70400200 | REL TEMP CONC BARRIER | 1,662.5 | FOOT | $3.78 | $9.00 | $15.00 | $18.00 | |
| 48 | 70600251 | IMP ATTN TEMP NRN TL3 | 8 | EACH | $6,841.01 | $5,775.00 | $1,685.00 | $4,400.00 | |
| 49 | 70600352 | IMP ATTN REL NRN TL3 | 8 | EACH | $919.52 | $1,200.00 | $560.00 | $1,500.00 | |
| 50 | 72501000 | TERMINAL MARKER - DA | 16 | EACH | $47.25 | $50.00 | $50.00 | $57.00 | |
| 51 | 78001110 | PAINT PVT MK LINE 4 | 6,397 | FOOT | $0.6700 | $0.7500 | $1.40 | $0.7700 | |
| 52 | 78100100 | RAISED REFL PAVT MKR | 34 | EACH | $131.25 | $140.00 | $310.00 | $150.00 | |
| 53 | 78100200 | TEMP RAIS REF PVT MKR | 400 | EACH | $13.51 | $16.00 | $20.00 | $26.00 | |
| 54 | 78200006 | GRDRAIL REF TYPE B | 45 | EACH | $31.50 | $30.00 | $35.00 | $38.00 | |
| 55 | 78200011 | BARR WALL REF TYPE C | 80 | EACH | $43.12 | $15.00 | $6.00 | $16.00 | |
| 56 | 78300200 | RAISED REF PVT MK REM | 434 | EACH | $10.31 | $8.50 | $30.00 | $50.00 | |
| 57 | 78300202 | PVT MKG REM WTR BLAST | 6,400 | SQ FT | $1.35 | $1.40 | $2.25 | $1.50 |