90-15[HB(1-4);VB;B]BP,BJR,BRR
- Let date
- Friday, January 15, 2021
- Contract
- 68F54 · job page
- District
- District 4
- County
- Tazewell
- Highway
- Limits
- This project is 5.5 miles long and the structure repair work consists of bridge painting, bridge deck scarification and overlay, joint replacement, bearing replacement, slopewall repair, substructure repair, and other related work on various structures on 1-74 from 0.8 miles east of Morton Ave. to the Woodford County line.
- Classification
- Bridge painting, bridge deck scarification and overlay, joint replacement, bearing replacement, slopewall repa
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $4,871,748 | ||
| 2 | Otto Baum Company, Inc. | $5,190,778 | +6.5% | |
| 3 | White Construction LLC | $5,459,142 | +12.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Otto Baum Compa… | #3 White Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326444 | SURFACE FILLER SPL | 22 | GALLON | $550.00 | $467.91 | $115.00 | |
| 2 | X0327980 | PAVMT MRKG REM WTR BL | 1,344 | SQ FT | $6.00 | $6.44 | $6.00 | |
| 3 | X5030550 | PROTECTIVE COAT SPL | 1,420 | SQ YD | $30.00 | $22.34 | $45.00 | |
| 4 | X7010218 | TRAF CONT & PROT SPL | 3 | EACH | $8,000.00 | $19,590.00 | $9,475.00 | |
| 5 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,000.00 | $4,345.76 | $3,000.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 28,621 | SQ FT | $0.9000 | $0.7500 | $0.7000 | |
| 7 | Z0001002 | GDRL AGG EROS CONT | 87 | TON | $195.00 | $95.66 | $195.00 | |
| 8 | Z0001899 | JACK & REM EX BEARING | 36 | EACH | $1,250.00 | $1,664.17 | $1,200.00 | |
| 9 | Z0001903 | STRUCT STEEL REMOV | 240 | POUND | $3.50 | $4.49 | $8.00 | |
| 10 | Z0001905 | STRUCT STEEL REPAIR | 1,050 | POUND | $19.00 | $25.24 | $36.50 | |
| 11 | Z0003600 | BEAM STRAIGHTENING | 1 | L SUM | $25,000.00 | $29,598.48 | $12,000.00 | |
| 12 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $40,000.00 | $43,825.65 | $40,000.00 | |
| 13 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $40,000.00 | $43,825.65 | $40,000.00 | |
| 14 | Z0007103 | C&D LEAD PT CL RS N3 | 1 | L SUM | $60,000.00 | $65,287.91 | $60,000.00 | |
| 15 | Z0007104 | C&D LEAD PT CL RS N4 | 1 | L SUM | $60,000.00 | $65,287.91 | $60,000.00 | |
| 16 | Z0007105 | C&D LEAD PT CL RS N5 | 1 | L SUM | $40,000.00 | $43,825.65 | $40,000.00 | |
| 17 | Z0007106 | C&D LEAD PT CL RS N6 | 1 | L SUM | $40,000.00 | $43,825.65 | $40,000.00 | |
| 18 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $78,000.00 | $84,603.95 | $78,000.00 | |
| 19 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $78,000.00 | $84,603.95 | $78,000.00 | |
| 20 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $90,000.00 | $97,481.31 | $90,000.00 | |
| 21 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $90,000.00 | $97,481.31 | $90,000.00 | |
| 22 | Z0010505 | CLEAN & PT STL BR N5 | 1 | L SUM | $80,000.00 | $86,750.18 | $80,000.00 | |
| 23 | Z0010506 | CLEAN & PT STL BR N6 | 1 | L SUM | $80,000.00 | $86,750.18 | $80,000.00 | |
| 24 | Z0012130 | BR DECK SCAR 3/4 | 6,029 | SQ YD | $42.50 | $48.65 | $49.00 | |
| 25 | Z0012162 | BR DK MIC C OVL 2 1/4 | 6,029 | SQ YD | $86.00 | $82.82 | $110.20 | |
| 26 | Z0012754 | STR REP CON DP = < 5 | 775.2 | SQ FT | $175.00 | $226.03 | $168.00 | |
| 27 | Z0012755 | STR REP CON DP OVER 5 | 47 | SQ FT | $275.00 | $382.13 | $360.00 | |
| 28 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $20,000.00 | $17,062.49 | $15,900.00 | |
| 29 | Z0016002 | DECK SLAB REP (FD-T2) | 2.4 | SQ YD | $2,050.00 | $2,936.45 | $2,200.00 | |
| 30 | Z0016200 | DECK SLAB REP (PART) | 21.7 | SQ YD | $535.00 | $684.68 | $1,080.00 | |
| 31 | Z0018051 | DRAINAGE SCUPPERS ADJ | 8 | EACH | $1,000.00 | $808.68 | $2,400.00 | |
| 32 | Z0073500 | TEMP SUPPORT SYSTEM | 1 | L SUM | $28,000.00 | $184,707.00 | $47,500.00 | |
| 33 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 34 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 35 | 20200500 | EARTH EXC WID | 27 | CU YD | $325.00 | $73.50 | $650.00 | |
| 36 | 40600295 | P BIT MATLS TACK CT | 12,799 | POUND | $1.00 | $1.07 | $1.00 | |
| 37 | 40600982 | HMA SURF REM BUTT JT | 3,341 | SQ YD | $10.00 | $10.73 | $10.00 | |
| 38 | 40602985 | HMA BC IL-9.5 N70 | 9 | TON | $675.00 | $697.52 | $650.00 | |
| 39 | 40604062 | HMA SC IL-9.5 D N70 | 216 | TON | $300.00 | $305.84 | $285.00 | |
| 40 | 42001300 | PROTECTIVE COAT | 5,658 | SQ YD | $3.00 | $1.88 | $2.10 | |
| 41 | 44000157 | HMA SURF REM 2 | 876 | SQ YD | $12.00 | $12.88 | $12.00 | |
| 42 | 44000173 | HMA SURF REM 6 | 6,739 | SQ YD | $15.00 | $16.10 | $15.00 | |
| 43 | 44201053 | CL B PATCH T4 17 | 27 | SQ YD | $250.00 | $298.45 | $260.00 | |
| 44 | 44201055 | CL B PATCH T2 17 | 70 | SQ YD | $260.00 | $320.97 | $260.00 | |
| 45 | 44201057 | CL B PATCH T3 17 | 64 | SQ YD | $250.00 | $316.06 | $260.00 | |
| 46 | 44201299 | DOWEL BARS 1 1/2 | 270 | EACH | $18.50 | $21.50 | $25.00 | |
| 47 | 44213200 | SAW CUTS | 698 | FOOT | $8.00 | $8.40 | $7.00 | |
| 48 | 44213204 | TIE BARS 3/4 | 7 | EACH | $25.00 | $18.38 | $14.00 | |
| 49 | 48102100 | AGG WEDGE SHLD TYPE B | 79 | TON | $150.00 | $95.41 | $150.00 | |
| 50 | 48203100 | HMA SHOULDERS | 2,522 | TON | $115.00 | $118.04 | $110.00 | |
| 51 | 50102400 | CONC REM | 131.1 | CU YD | $3,200.00 | $3,249.52 | $4,500.00 | |
| 52 | 50104650 | SLOPE WALL REMOV | 134 | SQ YD | $38.00 | $59.25 | $85.00 | |
| 53 | 50157300 | PROTECTIVE SHIELD | 483 | SQ YD | $65.00 | $116.55 | $90.00 | |
| 54 | 50300225 | CONC STRUCT | 36.3 | CU YD | $925.00 | $1,548.58 | $1,250.00 | |
| 55 | 50300255 | CONC SUP-STR | 139.3 | CU YD | $3,150.00 | $2,883.37 | $3,850.00 | |
| 56 | 50300260 | BR DECK GROOVING | 5,096 | SQ YD | $9.00 | $9.47 | $6.75 | |
| 57 | 50500405 | F & E STRUCT STEEL | 1,600 | POUND | $9.00 | $10.06 | $10.00 | |
| 58 | 50800205 | REINF BARS, EPOXY CTD | 21,220 | POUND | $3.00 | $2.84 | $3.00 | |
| 59 | 50800515 | BAR SPLICERS | 172 | EACH | $32.00 | $29.29 | $42.50 | |
| 60 | 51100300 | SLOPE WALL 6 | 134 | SQ YD | $220.00 | $233.95 | $185.00 | |
| 61 | 52000025 | PREF JOINT SEAL 2 | 135 | FOOT | $70.00 | $90.80 | $138.00 | |
| 62 | 52000030 | PREF JOINT SEAL 2 1/2 | 280 | FOOT | $75.00 | $111.54 | $146.00 | |
| 63 | 52000035 | PREF JOINT SEAL 2 3/4 | 145 | FOOT | $80.00 | $115.73 | $154.00 | |
| 64 | 52000110 | PREF JT STRIP SEAL | 816 | FOOT | $185.00 | $203.40 | $232.00 | |
| 65 | 52100010 | ELAST BEARING ASSY T1 | 36 | EACH | $1,000.00 | $1,009.25 | $1,300.00 | |
| 66 | 52100520 | ANCHOR BOLTS 1 | 72 | EACH | $95.00 | $90.49 | $140.00 | |
| 67 | 60300105 | FR & GRATES ADJUST | 8 | EACH | $2,000.00 | $1,339.75 | $1,750.00 | |
| 68 | 63000001 | SPBGR TY A 6FT POSTS | 1,250 | FOOT | $23.00 | $24.68 | $23.00 | |
| 69 | 63100085 | TRAF BAR TERM T6 | 5 | EACH | $2,850.00 | $3,058.37 | $2,850.00 | |
| 70 | 63100167 | TR BAR TRM T1 SPL TAN | 5 | EACH | $2,700.00 | $2,897.40 | $2,700.00 | |
| 71 | 63200310 | GUARDRAIL REMOV | 1,687 | FOOT | $5.50 | $5.37 | $5.00 | |
| 72 | 67000400 | ENGR FIELD OFFICE A | 14 | CAL MO | $1,925.00 | $2,217.96 | $1,550.00 | |
| 73 | 67100100 | MOBILIZATION | 1 | L SUM | $290,000.00 | $326,100.00 | $325,000.00 | |
| 74 | 70100205 | TRAF CONT-PROT 701401 | 4 | EACH | $1,500.00 | $4,466.75 | $12,750.00 | |
| 75 | 70100207 | TRAF CONT-PROT 701402 | 4 | EACH | $50,000.00 | $14,808.61 | $24,000.00 | |
| 76 | 70103815 | TR CONT SURVEILLANCE | 120 | CAL DA | $0.0100 | $337.93 | $1.00 | |
| 77 | 70107025 | CHANGEABLE MESSAGE SN | 140 | CAL DA | $60.00 | $75.12 | $70.00 | |
| 78 | 70300100 | SHORT TERM PAVT MKING | 328 | FOOT | $1.10 | $2.15 | $3.00 | |
| 79 | 70300150 | SHRT TRM PAVT MK REM | 110 | SQ FT | $1.90 | $3.22 | $2.00 | |
| 80 | 70300904 | PAVT MARK TAPE T4 4 | 85,862 | FOOT | $1.10 | $1.18 | $1.10 | |
| 81 | 70400100 | TEMP CONC BARRIER | 4,075 | FOOT | $28.00 | $26.83 | $38.00 | |
| 82 | 70400200 | REL TEMP CONC BARRIER | 3,525 | FOOT | $10.00 | $9.66 | $9.44 | |
| 83 | 70600250 | IMP ATTN TEMP NRD TL3 | 12 | EACH | $5,000.00 | $2,897.41 | $3,000.00 | |
| 84 | 70600350 | IMP ATTN REL NRD TL3 | 6 | EACH | $300.00 | $1,073.11 | $1,500.00 | |
| 85 | 72501000 | TERMINAL MARKER - DA | 5 | EACH | $35.00 | $37.56 | $35.00 | |
| 86 | 78009004 | MOD URETH PM LINE 4 | 10,695 | FOOT | $1.20 | $0.4300 | $0.4000 | |
| 87 | 78009006 | MOD URETH PM LINE 6 | 2,284 | FOOT | $1.80 | $2.09 | $1.95 | |
| 88 | 78200005 | GRDRAIL REF TYPE A | 20 | EACH | $8.00 | $8.59 | $8.00 |