(43-BR)BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $9,110,397 | ||
| 2 | White Construction LLC | $9,420,225 | +3.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 White Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X0322936 | REMOV EX FLAR END SEC | 3 | EACH | $400.00 | $265.00 | |
| 2 | X0323660 | DROP BOX NO.1 | 1 | EACH | $11,000.00 | $9,025.00 | |
| 3 | X0327112 | STUMP REMOVAL ACRES | 1.75 | ACRE | $20,250.00 | $5,600.00 | |
| 4 | X0327423 | CONNECT EXIST CULVERT | 2 | EACH | $2,200.00 | $285.00 | |
| 5 | X1200055 | INFILTRATION AGG | 42 | CU YD | $500.00 | $345.00 | |
| 6 | X2010400 | STUMP REMOVAL ONLY | 103 | UNIT | $12.25 | $40.00 | |
| 7 | X4020700 | AGG SURF CSE B 8 | 329 | SQ YD | $24.25 | $20.00 | |
| 8 | X4400110 | TEMP PAVT REMOVAL | 3,167 | SQ YD | $7.25 | $7.00 | |
| 9 | X5030305 | CONC WEARING SURF 5 | 558.4 | SQ YD | $118.00 | $115.00 | |
| 10 | X5040100 | PREC BRIDGE APP SLAB | 4,875 | SQ FT | $40.00 | $40.00 | |
| 11 | X6062700 | CONC GUTTER TA SPL | 114 | FOOT | $85.00 | $70.00 | |
| 12 | X6670109 | PERM SURVEY TIES | 5 | EACH | $795.00 | $275.00 | |
| 13 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $17,000.00 | $29,980.00 | |
| 14 | X7030005 | TEMP PAVT MKING REMOV | 12,000 | SQ FT | $1.10 | $1.50 | |
| 15 | X7040125 | PIN TEMP CONC BARRIER | 1,270 | EACH | $29.00 | $5.00 | |
| 16 | X7050165 | TEMP TR BAR TM T1 SPL | 1 | EACH | $3,250.00 | $3,200.00 | |
| 17 | Z0001002 | GDRL AGG EROS CONT | 171 | TON | $86.00 | $65.00 | |
| 18 | Z0004522 | HMA DRIVEWAY PAVT 6 | 215 | SQ YD | $90.00 | $61.00 | |
| 19 | Z0004638 | PAVT BREAKING | 2,711 | SQ YD | $4.00 | $4.00 | |
| 20 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $13,000.00 | $13,500.00 | |
| 21 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $27,000.00 | $40,500.00 | |
| 22 | Z0022800 | FENCE REMOVAL | 550 | FOOT | $6.40 | $5.00 | |
| 23 | Z0024475 | TUBULAR MARKER | 77 | EACH | $180.00 | $175.00 | |
| 24 | Z0046304 | P UNDR FOR STRUCT 4 | 250 | FOOT | $28.00 | $35.00 | |
| 25 | Z0062456 | TEMP PAVEMENT | 4,677 | SQ YD | $71.50 | $70.00 | |
| 26 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 27 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 28 | 20100500 | TREE REMOV ACRES | 0.75 | ACRE | $26,000.00 | $13,000.00 | |
| 29 | 20800150 | TRENCH BACKFILL | 272 | CU YD | $47.00 | $75.00 | |
| 30 | 21101505 | TOPSOIL EXC & PLAC | 341 | CU YD | $27.00 | $20.00 | |
| 31 | 21101615 | TOPSOIL F & P 4 | 24,536 | SQ YD | $5.00 | $4.00 | |
| 32 | 25000210 | SEEDING CL 2A | 5.25 | ACRE | $530.00 | $520.00 | |
| 33 | 25000400 | NITROGEN FERT NUTR | 457 | POUND | $1.00 | $1.00 | |
| 34 | 25000500 | PHOSPHORUS FERT NUTR | 457 | POUND | $1.00 | $1.00 | |
| 35 | 25000600 | POTASSIUM FERT NUTR | 457 | POUND | $1.00 | $1.00 | |
| 36 | 25000750 | MOWING | 5.25 | ACRE | $250.00 | $230.00 | |
| 37 | 25100115 | MULCH METHOD 2 | 5.25 | ACRE | $1,500.00 | $1,515.00 | |
| 38 | 25100630 | EROSION CONTR BLANKET | 24,536 | SQ YD | $1.00 | $1.00 | |
| 39 | 28000250 | TEMP EROS CONTR SEED | 487 | POUND | $9.00 | $7.00 | |
| 40 | 28000305 | TEMP DITCH CHECKS | 470 | FOOT | $7.00 | $15.00 | |
| 41 | 28000400 | PERIMETER EROS BAR | 5,115 | FOOT | $3.25 | $2.50 | |
| 42 | 28000500 | INLET & PIPE PROTECT | 12 | EACH | $150.00 | $290.00 | |
| 43 | 28000510 | INLET FILTERS | 6 | EACH | $250.00 | $310.00 | |
| 44 | 28100105 | STONE RIPRAP CL A3 | 59 | SQ YD | $33.00 | $65.00 | |
| 45 | 28100107 | STONE RIPRAP CL A4 | 53 | SQ YD | $94.00 | $98.00 | |
| 46 | 28100109 | STONE RIPRAP CL A5 | 2,209 | SQ YD | $97.00 | $90.00 | |
| 47 | 28200200 | FILTER FABRIC | 2,063 | SQ YD | $3.50 | $3.00 | |
| 48 | 31100910 | SUB GRAN MAT A 12 | 11,645 | SQ YD | $25.00 | $25.00 | |
| 49 | 31101200 | SUB GRAN MAT B 4 | 479 | SQ YD | $11.00 | $15.00 | |
| 50 | 35100500 | AGG BASE CSE A 6 | 1,009 | SQ YD | $23.00 | $16.00 | |
| 51 | 40600982 | HMA SURF REM BUTT JT | 206 | SQ YD | $25.00 | $14.00 | |
| 52 | 40603205 | P HMA BC IL-9.5 N50 | 30 | TON | $380.00 | $236.00 | |
| 53 | 40603535 | P HMA SC "D" N50 | 39 | TON | $176.00 | $236.00 | |
| 54 | 40701831 | HMA PAVT FD 7 1/2 | 345 | SQ YD | $108.00 | $54.00 | |
| 55 | 40701861 | HMA PAVT FD 9 | 658 | SQ YD | $105.00 | $78.25 | |
| 56 | 42000080 | PVT CON PCC BR APP SL | 360 | SQ YD | $170.00 | $140.00 | |
| 57 | 42300400 | PCC DRIVEWAY PAVT 8 | 264 | SQ YD | $105.00 | $80.00 | |
| 58 | 44000100 | PAVEMENT REM | 3,337 | SQ YD | $20.00 | $17.00 | |
| 59 | 44000165 | HMA SURF REM 4 | 564 | SQ YD | $13.00 | $9.00 | |
| 60 | 44000200 | DRIVE PAVEMENT REM | 429 | SQ YD | $9.50 | $16.00 | |
| 61 | 44004000 | PAVED DITCH REMOVAL | 397 | FOOT | $10.00 | $5.00 | |
| 62 | 44004250 | PAVED SHLD REMOVAL | 1,757 | SQ YD | $10.00 | $18.00 | |
| 63 | 48100500 | AGGREGATE SHLDS A 6 | 39 | SQ YD | $50.00 | $37.00 | |
| 64 | 48102100 | AGG WEDGE SHLD TYPE B | 132 | TON | $66.00 | $66.00 | |
| 65 | 48203013 | HMA SHOULDERS 4 | 564 | SQ YD | $56.00 | $29.00 | |
| 66 | 50100100 | REM EXIST STRUCT | 1 | EACH | $115,000.00 | $140,000.00 | |
| 67 | 50105220 | PIPE CULVERT REMOV | 463 | FOOT | $11.28 | $13.00 | |
| 68 | 50200100 | STRUCTURE EXCAVATION | 542 | CU YD | $11.50 | $20.00 | |
| 69 | 50200300 | COFFERDAM EXCAVATION | 991 | CU YD | $19.00 | $35.00 | |
| 70 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $113,000.00 | $210,000.00 | |
| 71 | 50300225 | CONC STRUCT | 419.3 | CU YD | $785.00 | $660.00 | |
| 72 | 50300255 | CONC SUP-STR | 758.3 | CU YD | $1,100.00 | $950.00 | |
| 73 | 50300260 | BR DECK GROOVING | 2,918 | SQ YD | $7.50 | $5.50 | |
| 74 | 50300265 | SEAL COAT CONC | 178 | CU YD | $200.00 | $290.00 | |
| 75 | 50300300 | PROTECTIVE COAT | 3,240 | SQ YD | $2.50 | $1.25 | |
| 76 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $2,450,000.00 | $2,545,000.00 | |
| 77 | 50500505 | STUD SHEAR CONNECTORS | 11,130 | EACH | $3.30 | $3.75 | |
| 78 | 50800205 | REINF BARS, EPOXY CTD | 242,010 | POUND | $1.50 | $1.55 | |
| 79 | 50800515 | BAR SPLICERS | 1,021 | EACH | $27.00 | $60.00 | |
| 80 | 50800530 | MECHANICAL SPLICERS | 322 | EACH | $68.00 | $75.00 | |
| 81 | 51201610 | FUR STL PILE HP12X63 | 1,107 | FOOT | $77.00 | $97.00 | |
| 82 | 51201710 | FUR STL PILE HP12X84 | 871 | FOOT | $95.00 | $115.00 | |
| 83 | 51202305 | DRIVING PILES | 1,978 | FOOT | $0.0100 | $0.0100 | |
| 84 | 51203610 | TEST PILE ST HP12X63 | 1 | EACH | $7,600.00 | $5,500.00 | |
| 85 | 51203710 | TEST PILE ST HP12X84 | 2 | EACH | $7,500.00 | $6,500.00 | |
| 86 | 51500100 | NAME PLATES | 1 | EACH | $620.00 | $750.00 | |
| 87 | 52000110 | PREF JT STRIP SEAL | 168.5 | FOOT | $180.00 | $180.00 | |
| 88 | 52100010 | ELAST BEARING ASSY T1 | 14 | EACH | $5,000.00 | $4,500.00 | |
| 89 | 52100520 | ANCHOR BOLTS 1 | 56 | EACH | $72.00 | $115.00 | |
| 90 | 52100540 | ANCHOR BOLTS 1 1/2 | 28 | EACH | $205.00 | $215.00 | |
| 91 | 52200020 | TEMP SOIL RETEN SYSTM | 3,963 | SQ FT | $36.00 | $27.50 | |
| 92 | 542D0220 | P CUL CL D 1 15 | 37 | FOOT | $51.00 | $43.00 | |
| 93 | 542D0226 | P CUL CL D 1 21 | 71 | FOOT | $65.00 | $65.00 | |
| 94 | 542D0241 | P CUL CL D 1 36 | 10 | FOOT | $230.00 | $100.00 | |
| 95 | 542D1081 | P CUL CL D 2 36 | 43 | FOOT | $130.00 | $105.00 | |
| 96 | 54213657 | PRC FLAR END SEC 12 | 1 | EACH | $1,300.00 | $670.00 | |
| 97 | 54213660 | PRC FLAR END SEC 15 | 3 | EACH | $1,320.00 | $925.00 | |
| 98 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $1,400.00 | $1,175.00 | |
| 99 | 54213675 | PRC FLAR END SEC 30 | 2 | EACH | $2,250.00 | $1,875.00 | |
| 100 | 54262721 | METAL FL END SEC 21" | 1 | EACH | $980.00 | $445.00 | |
| 101 | 54262736 | METAL FL END SEC 36" | 2 | EACH | $1,850.00 | $795.00 | |
| 102 | 550A0050 | STORM SEW CL A 1 12 | 13 | FOOT | $51.00 | $60.00 | |
| 103 | 550A0070 | STORM SEW CL A 1 15 | 27 | FOOT | $55.00 | $63.00 | |
| 104 | 550A0090 | STORM SEW CL A 1 18 | 60 | FOOT | $53.00 | $70.00 | |
| 105 | 550A0120 | STORM SEW CL A 1 24 | 122 | FOOT | $62.00 | $80.00 | |
| 106 | 550A0130 | STORM SEW CL A 1 27 | 82 | FOOT | $93.00 | $105.00 | |
| 107 | 550A0140 | STORM SEW CL A 1 30 | 597 | FOOT | $75.00 | $120.00 | |
| 108 | 59100100 | GEOCOMPOSITE WALL DR | 186 | SQ YD | $24.00 | $40.00 | |
| 109 | 60100060 | CONC HDWL FOR P DRAIN | 3 | EACH | $350.00 | $300.00 | |
| 110 | 60108100 | PIPE UNDERDRAIN 4 SP | 24 | FOOT | $30.00 | $30.00 | |
| 111 | 60219000 | MAN TA 4 DIA T8G | 1 | EACH | $3,600.00 | $3,450.00 | |
| 112 | 60221100 | MAN TA 5 DIA T1F CL | 1 | EACH | $4,130.00 | $4,100.00 | |
| 113 | 60221700 | MAN TA 5 DIA T8G | 4 | EACH | $4,000.00 | $4,300.00 | |
| 114 | 60224005 | MAN TA 6 DIA T8G | 1 | EACH | $5,600.00 | $5,000.00 | |
| 115 | 60240303 | INLETS TB T9F&G | 2 | EACH | $2,400.00 | $2,200.00 | |
| 116 | 60500060 | REMOV INLETS | 1 | EACH | $770.00 | $235.00 | |
| 117 | 60600095 | CLASS SI CONC OUTLET | 0.9 | CU YD | $1,260.00 | $765.00 | |
| 118 | 60607400 | COMB CC&G TB9.24 | 270 | FOOT | $90.00 | $55.00 | |
| 119 | 63000001 | SPBGR TY A 6FT POSTS | 525 | FOOT | $30.00 | $30.25 | |
| 120 | 63100085 | TRAF BAR TERM T6 | 3 | EACH | $2,900.00 | $2,850.00 | |
| 121 | 63100167 | TR BAR TRM T1 SPL TAN | 3 | EACH | $3,300.00 | $3,200.00 | |
| 122 | 63200310 | GUARDRAIL REMOV | 595 | FOOT | $5.50 | $6.40 | |
| 123 | 64300430 | IMP ATTEN NRD TL2 | 1 | EACH | $7,500.00 | $3,960.00 | |
| 124 | 66600105 | FUR ERECT ROW MARKERS | 13 | EACH | $275.00 | $310.00 | |
| 125 | 66700205 | PERM SURV MKRS T1 | 5 | EACH | $615.00 | $285.00 | |
| 126 | 66900200 | NON SPL WASTE DISPOSL | 24 | CU YD | $145.00 | $25.00 | |
| 127 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $915.00 | $900.00 | |
| 128 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,350.00 | $2,300.00 | |
| 129 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,350.00 | $2,300.00 | |
| 130 | 66901006 | REG SUB MON | 2 | CAL DA | $1,120.00 | $1,100.00 | |
| 131 | 67000400 | ENGR FIELD OFFICE A | 18 | CAL MO | $2,000.00 | $1,960.00 | |
| 132 | 67100100 | MOBILIZATION | 1 | L SUM | $260,000.00 | $565,213.47 | |
| 133 | 70103815 | TR CONT SURVEILLANCE | 300 | CAL DA | $0.0100 | $1.00 | |
| 134 | 70107025 | CHANGEABLE MESSAGE SN | 300 | CAL DA | $50.00 | $50.00 | |
| 135 | 70300100 | SHORT TERM PAVT MKING | 59 | FOOT | $20.00 | $5.00 | |
| 136 | 70300150 | SHRT TRM PAVT MK REM | 19 | SQ FT | $20.00 | $3.00 | |
| 137 | 70300220 | TEMP PVT MK LINE 4 | 36,000 | FOOT | $1.50 | $1.35 | |
| 138 | 70400100 | TEMP CONC BARRIER | 2,650 | FOOT | $33.50 | $40.00 | |
| 139 | 70400200 | REL TEMP CONC BARRIER | 2,390 | FOOT | $6.50 | $3.00 | |
| 140 | 70500100 | TEMP SPBGR TY A | 75 | FOOT | $31.00 | $30.25 | |
| 141 | 70500665 | TEMP TR BAR TERM T6 | 1 | EACH | $2,900.00 | $2,850.00 | |
| 142 | 70600250 | IMP ATTN TEMP NRD TL3 | 3 | EACH | $4,700.00 | $4,300.00 | |
| 143 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $830.00 | $725.00 | |
| 144 | 72000100 | SIGN PANEL T1 | 9 | SQ FT | $37.00 | $36.00 | |
| 145 | 72400500 | RELOC SIN PAN ASSY TA | 9 | EACH | $200.00 | $200.00 | |
| 146 | 72400600 | RELOC SIN PAN ASSY TB | 1 | EACH | $200.00 | $200.00 | |
| 147 | 72501000 | TERMINAL MARKER - DA | 3 | EACH | $56.00 | $40.00 | |
| 148 | 72800100 | TELES STL SIN SUPPORT | 14 | FOOT | $43.00 | $42.00 | |
| 149 | 78009004 | MOD URETH PM LINE 4 | 11,362 | FOOT | $1.00 | $1.00 | |
| 150 | 78009024 | MOD URETH PM LINE 24 | 17 | FOOT | $30.00 | $175.00 | |
| 151 | 78100100 | RAISED REFL PAVT MKR | 64 | EACH | $132.00 | $140.00 | |
| 152 | 78200005 | GRDRAIL REF TYPE A | 15 | EACH | $8.00 | $8.00 | |
| 153 | 78300200 | RAISED REF PVT MK REM | 10 | EACH | $46.00 | $65.00 | |
| 154 | Z0034105 | MATL TRANSFER DEVICE | 8,770 | TON | $5.30 | $5.00 | |
| 155 | 20200100 | EARTH EXCAVATION | 5,595 | CU YD | $20.00 | $12.00 | |
| 156 | 20400800 | FURNISHED EXCAVATION | 16,820 | CU YD | $27.00 | $33.00 | |
| 157 | 40600295 | P BIT MATLS TACK CT | 20,541 | POUND | $1.35 | $1.00 | |
| 158 | 40701896 | HMA PAVT FD 10 3/4 | 8,350 | SQ YD | $79.00 | $83.55 | |
| 159 | 42001300 | PROTECTIVE COAT | 730 | SQ YD | $0.0100 | $1.85 | |
| 160 | 48203029 | HMA SHOULDERS 8 | 2,942 | SQ YD | $65.00 | $50.00 |