(10-VB)BP 2024
- Let date
- Friday, January 17, 2025
- Contract
- 62X49 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- This improvement consists of a Bridge Painting of the existing structure (049-0171) carrying IL 59 over Rollins Road, the existing structure (049-0016) carrying Washington Road over US 41, and the existing structure (049-0097) carrying Washington Road over the UP RR in the Village of FOX Lake, and the Village of FOX Lake, and the City of Park City in Lake County for a total length of 749 feet.
- Classification
- A Bridge Painting of the existing structure (049-0171) carrying IL 59 over Rollins Road, the existing structur ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Capital Industrial Services, LLC Low bidder | $893,330 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $945,648 | +5.9% | |
| 3 | Civil Coatings and Construction Inc. | $1,867,673 | +109.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Capital Industr… | #2 ERA-Valdivia Co… | #3 Civil Coatings … |
|---|---|---|---|---|---|---|---|---|
| 1 | X5060601 | C&D N-LEAD PT C RS N1 | 1 | L SUM | $18,046.00 | $47,226.00 | $1,000.00 | |
| 2 | X5060603 | C&D N-LEAD PT C RS N3 | 1 | L SUM | $61,658.00 | $109,420.00 | $1,000.00 | |
| 3 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $600.00 | $1,200.00 | $50.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $46,000.00 | $10,000.00 | $46,000.00 | |
| 5 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $70,681.00 | $124,195.00 | $1,000.00 | |
| 6 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $72,785.00 | $118,065.00 | $400,000.00 | |
| 7 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $278,836.00 | $248,390.00 | $625,442.00 | |
| 8 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $242,743.00 | $218,840.00 | $620,000.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 154.2 | SQ FT | $16.00 | $10.00 | $16.00 | |
| 10 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $3,500.00 | $7,500.00 | $12,000.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $44,600.00 | $35,000.00 | $90,000.00 | |
| 12 | 70107005 | PAVT MK BLKOUT TAPE 5 | 1,690 | FOOT | $2.00 | $0.1000 | $2.00 | |
| 13 | 70300150 | SHRT TRM PAVT MK REM | 2,254 | SQ FT | $1.50 | $0.1000 | $1.50 | |
| 14 | 70307120 | TEMP PVT MK L4 T4 TAPE | 6,760 | FOOT | $1.28 | $0.1000 | $1.28 | |
| 15 | 70400100 | TEMP CONC BARRIER | 600 | FOOT | $27.00 | $10.00 | $42.75 | |
| 16 | 70400200 | REL TEMP CONC BARRIER | 600 | FOOT | $10.00 | $5.00 | $13.50 | |
| 17 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $3,300.00 | $250.00 | $7,000.00 | |
| 18 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $300.00 | $250.00 | $2,500.00 |