FAI 55 22 BJ
- Let date
- Friday, June 16, 2023
- Contract
- 62R88 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (2,404-Ft) The proposed improvement consists of bridge deck (SN 016-2665) overlay and joint repairs of I 55 (Stevenson Expressway) at US 12/20/45 (La- Grange Road) (overpass) in the Village of Hodgkins and the City of Countryside, Cook County.
- Classification
- Bridge deck (SN 016-2665) overlay and joint repairs of I 55 (Stevenson Expressway) at US 12/20/45 (La- Grange
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,656,000 | ||
| 2 | Areatha Construction Co., Inc. | $1,791,993 | +8.2% | |
| 3 | Martam Construction Incorporated | $1,856,995 | +12.1% | |
| 4 | Lorig Construction Company | $1,878,540 | +13.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Areatha Constru… | #3 Martam Construc… | #4 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0931400 | INLET BOX ADJ SPL | 4 | EACH | $4,000.00 | $5,010.85 | $2,100.00 | $2,900.00 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 9 | UNIT | $250.00 | $641.20 | $500.00 | $800.00 | |
| 3 | X5030250 | BR DECK GROOVING LONG | 2,866 | SQ YD | $5.50 | $7.00 | $7.70 | $5.25 | |
| 4 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $4,000.00 | $2,500.00 | $4,500.00 | $1,700.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $150,000.00 | $35,000.00 | $188,000.00 | $285,000.00 | |
| 6 | X7010240 | TR CONT SURVEILL SPL | 65 | CAL DA | $0.0100 | $200.00 | $440.00 | $400.00 | |
| 7 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $0.0100 | $63,900.00 | $60,000.00 | $9,000.00 | |
| 8 | X7830050 | RAISD REF PM REFL REM | 98 | EACH | $10.00 | $6.00 | $30.00 | $6.00 | |
| 9 | Z0006016 | BR DK LTX C OLY 2 3/4 | 3,386 | SQ YD | $103.00 | $125.55 | $122.00 | $115.00 | |
| 10 | Z0012130 | BR DECK SCAR 3/4 | 3,386 | SQ YD | $42.00 | $46.85 | $42.00 | $50.00 | |
| 11 | Z0012750 | CONC MEDIAN REPAIR | 40 | SQ FT | $75.00 | $175.40 | $125.00 | $80.00 | |
| 12 | Z0012754 | STR REP CON DP = < 5 | 142 | SQ FT | $145.00 | $143.90 | $190.00 | $400.00 | |
| 13 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $8,975.00 | $9,000.00 | $45,000.00 | |
| 14 | Z0029090 | DIAMOND GRIND BR SEC | 3,160 | SQ YD | $8.75 | $9.60 | $8.50 | $8.25 | |
| 15 | Z0030850 | TEMP INFO SIGNING | 155 | SQ FT | $25.00 | $20.00 | $18.00 | $15.00 | |
| 16 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 17 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 158 | CU YD | $80.00 | $56.75 | $85.00 | $70.00 | |
| 19 | 21001000 | GEOTECH FAB F/GR STAB | 222 | SQ YD | $5.00 | $3.00 | $5.00 | $5.00 | |
| 20 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $7,920.00 | $7,200.00 | $4,000.00 | $3,500.00 | |
| 21 | 25000400 | NITROGEN FERT NUTR | 30 | POUND | $5.50 | $5.00 | $5.00 | $4.00 | |
| 22 | 25000500 | PHOSPHORUS FERT NUTR | 30 | POUND | $5.50 | $5.00 | $5.00 | $4.00 | |
| 23 | 25000600 | POTASSIUM FERT NUTR | 30 | POUND | $5.50 | $5.00 | $5.00 | $4.00 | |
| 24 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $7,920.00 | $7,200.00 | $3,000.00 | $2,800.00 | |
| 25 | 28000400 | PERIMETER EROS BAR | 827 | FOOT | $4.40 | $4.00 | $5.00 | $4.50 | |
| 26 | 28000510 | INLET FILTERS | 4 | EACH | $330.00 | $300.00 | $200.00 | $160.00 | |
| 27 | 30300001 | AGG SUBGRADE IMPROVE | 74 | CU YD | $74.00 | $45.00 | $122.00 | $104.00 | |
| 28 | 31101200 | SUB GRAN MAT B 4 | 652 | SQ YD | $10.00 | $28.55 | $8.00 | $15.00 | |
| 29 | 40600290 | BIT MATLS TACK CT | 665 | POUND | $0.0100 | $3.65 | $4.00 | $3.75 | |
| 30 | 40600982 | HMA SURF REM BUTT JT | 834 | SQ YD | $0.0100 | $33.90 | $8.00 | $36.00 | |
| 31 | 40605026 | P HMA SC SMA 9.5 F N80 | 145 | TON | $150.00 | $378.40 | $400.00 | $400.00 | |
| 32 | 44004250 | PAVED SHLD REMOVAL | 624 | SQ YD | $15.00 | $33.90 | $15.00 | $27.00 | |
| 33 | 48102100 | AGG WEDGE SHLD TYPE B | 52 | TON | $35.00 | $101.30 | $120.00 | $73.00 | |
| 34 | 48203045 | HMA SHOULDERS 12 | 652 | SQ YD | $55.00 | $89.95 | $95.00 | $96.00 | |
| 35 | 50102400 | CONC REM | 18.2 | CU YD | $2,000.00 | $1,961.70 | $1,800.00 | $2,400.00 | |
| 36 | 50157300 | PROTECTIVE SHIELD | 2,153 | SQ YD | $70.00 | $58.00 | $45.00 | $1.00 | |
| 37 | 50300255 | CONC SUP-STR | 21.9 | CU YD | $2,500.00 | $3,942.15 | $2,250.00 | $2,700.00 | |
| 38 | 50300300 | PROTECTIVE COAT | 3,460 | SQ YD | $0.0100 | $2.10 | $1.00 | $1.00 | |
| 39 | 50800205 | REINF BARS, EPOXY CTD | 2,870 | POUND | $2.25 | $4.00 | $4.00 | $3.50 | |
| 40 | 50800515 | BAR SPLICERS | 40 | EACH | $60.00 | $55.80 | $55.00 | $85.00 | |
| 41 | 52000110 | PREF JT STRIP SEAL | 204 | FOOT | $235.00 | $295.70 | $235.00 | $200.00 | |
| 42 | 58700300 | CONCRETE SEALER | 5,064 | SQ FT | $3.00 | $1.90 | $1.00 | $3.00 | |
| 43 | 59000200 | EPOXY CRACK INJECTION | 24 | FOOT | $60.00 | $125.00 | $90.00 | $300.00 | |
| 44 | 63301210 | REM RE-E SPBGR TY A | 455 | FOOT | $21.45 | $19.45 | $22.00 | $23.00 | |
| 45 | 63301990 | REM RE-E T B TERM T1 | 4 | EACH | $1,364.00 | $1,240.00 | $1,400.00 | $2,000.00 | |
| 46 | 63302700 | REM RE-E T B TERM T6 | 4 | EACH | $2,486.00 | $2,260.00 | $2,500.00 | $2,000.00 | |
| 47 | 66900200 | NON SPL WASTE DISPOSL | 160 | CU YD | $90.00 | $120.40 | $75.00 | $74.00 | |
| 48 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,650.00 | $1,200.00 | $1,400.00 | $800.00 | |
| 49 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,200.00 | $4,200.00 | $8,500.00 | $2,500.00 | |
| 50 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $500.00 | $2,800.00 | $1,500.00 | |
| 51 | 66901006 | REG SUB MON | 15 | CAL DA | $990.00 | $700.00 | $200.00 | $840.00 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $92,600.00 | $112,668.00 | $112,000.00 | $100,000.00 | |
| 53 | 70107025 | CHANGEABLE MESSAGE SN | 225 | CAL DA | $50.00 | $27.00 | $40.00 | $35.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 2,107 | FOOT | $1.00 | $0.9500 | $1.00 | $1.00 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 703 | SQ FT | $0.5000 | $3.00 | $1.50 | $1.25 | |
| 56 | 70307120 | TEMP PVT MK L4 T4 TAPE | 13,457 | FOOT | $1.21 | $1.00 | $1.40 | $1.25 | |
| 57 | 70307130 | TEMP PVT MK L6 T4 TAPE | 502 | FOOT | $1.49 | $1.50 | $2.20 | $2.00 | |
| 58 | 70307140 | TEMP PVT MK L8 T4 TAPE | 5,594 | FOOT | $2.42 | $2.00 | $2.70 | $2.50 | |
| 59 | 70307160 | TEMP PVT MK L12 T4 TAPE | 1,515 | FOOT | $3.63 | $3.00 | $7.00 | $6.75 | |
| 60 | 70400100 | TEMP CONC BARRIER | 1,575 | FOOT | $30.00 | $33.60 | $26.00 | $27.00 | |
| 61 | 70400125 | PIN TEMP CONC BARRIER | 435 | EACH | $20.00 | $19.00 | $15.00 | $18.00 | |
| 62 | 70400200 | REL TEMP CONC BARRIER | 2,650 | FOOT | $15.00 | $3.50 | $8.00 | $3.00 | |
| 63 | 70600260 | IMP ATTN TEMP FRN TL3 | 8 | EACH | $6,500.00 | $5,415.00 | $6,000.00 | $7,500.00 | |
| 64 | 70600332 | IMP ATTN REL FRN TL3 | 6 | EACH | $2,000.00 | $2,045.00 | $2,200.00 | $3,500.00 | |
| 65 | 78000200 | THPL PVT MK LINE 4 | 4,966 | FOOT | $1.60 | $1.45 | $0.9000 | $0.8500 | |
| 66 | 78000500 | THPL PVT MK LINE 8 | 3,430 | FOOT | $2.15 | $1.95 | $2.20 | $2.00 | |
| 67 | 78000600 | THPL PVT MK LINE 12 | 622 | FOOT | $3.65 | $3.35 | $3.30 | $3.00 | |
| 68 | 78004235 | PREF PL PM TB IL LN 7 | 191 | FOOT | $16.50 | $15.00 | $16.00 | $15.00 | |
| 69 | 78004625 | PREF PL PM TD STD LN 5 | 989 | FOOT | $16.50 | $15.00 | $13.00 | $12.00 | |
| 70 | 78009004 | MOD URETH PM LINE 4 | 1,091 | FOOT | $3.25 | $2.95 | $5.00 | $4.00 | |
| 71 | 78009008 | MOD URETH PM LINE 8 | 820 | FOOT | $4.55 | $4.15 | $7.00 | $6.00 | |
| 72 | 78011030 | GRV RCSD PVT MRKG 6 | 989 | FOOT | $0.8300 | $0.8000 | $2.20 | $2.00 | |
| 73 | 78011040 | GRV RCSD PVT MRKG 8 | 191 | FOOT | $1.05 | $0.9500 | $11.00 | $10.00 | |
| 74 | 78011045 | GRV RCSD PVT MRKG 9 | 170 | FOOT | $1.49 | $1.35 | $13.00 | $12.00 | |
| 75 | 78100100 | RAISED REFL PAVT MKR | 18 | EACH | $302.50 | $2.75 | $300.00 | $275.00 | |
| 76 | 78100300 | REPLACEMENT REFLECTOR | 98 | EACH | $11.50 | $10.45 | $20.00 | $28.00 | |
| 77 | 78300200 | RAISED REF PVT MK REM | 18 | EACH | $10.00 | $20.00 | $110.00 | $30.00 | |
| 78 | 78300202 | PAVMT MRKG REM WTR BL | 6,025 | SQ FT | $3.30 | $1.10 | $1.40 | $1.25 |