FAP 532 22 BRIDGE
- Let date
- Friday, March 10, 2023
- Contract
- 62R68 · job page
- District
- District 1
- County
- Will
- Highway
- Limits
- (575-Ft) Improvements consist of bridge joint replace/repairs of structure carrying Arsenal Road (SN 099-3392) over BNSF Railroad and Jackson Creek in the Village of Elwood, Will County.
- Classification
- Bridge joint replace/repairs of structure carrying Arsenal Road (SN 099-3392) over BNSF Railroad and Jackson C
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. T. Ferro Construction Co. Low bidder | $258,287 | ||
| 2 | Herlihy Mid-Continent Company | $290,214 | +12.4% | |
| 3 | Path Construction Company, Inc. | $309,030 | +19.6% | |
| 4 | Areatha Construction Co., Inc. | $314,106 | +21.6% | |
| 5 | D. Construction, Inc. | $316,570 | +22.6% | |
| 6 | Lorig Construction Company | $322,199 | +24.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. T. Ferro Con… | #2 Herlihy Mid-Con… | #3 Path Constructi… | #4 Areatha Constru… | #5 D. Construction… | #6 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X6700407 | ENGR FLD OFF A D1 | 6 | CAL MO | $500.00 | $3,113.00 | $3,000.00 | $2,000.00 | $4,000.00 | $1,500.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $13,500.00 | $13,500.00 | $70,000.00 | $13,500.00 | $20,000.00 | $109,000.00 | |
| 3 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $20.00 | $20.00 | $15.00 | $20.00 | $25.00 | $20.00 | |
| 4 | 50102400 | CONC REM | 10.4 | CU YD | $4,000.00 | $3,591.00 | $2,300.00 | $3,107.70 | $2,500.00 | $2,600.00 | |
| 5 | 50157300 | PROTECTIVE SHIELD | 176 | SQ YD | $100.00 | $0.1000 | $150.00 | $120.15 | $85.00 | $1.00 | |
| 6 | 50300255 | CONC SUP-STR | 10.4 | CU YD | $1,850.00 | $2,333.00 | $2,700.00 | $4,023.25 | $2,250.00 | $2,300.00 | |
| 7 | 50300300 | PROTECTIVE COAT | 70 | SQ YD | $2.00 | $3.00 | $26.00 | $12.75 | $5.00 | $2.00 | |
| 8 | 50800205 | REINF BARS, EPOXY CTD | 1,450 | POUND | $3.00 | $4.75 | $3.50 | $4.50 | $2.75 | $3.25 | |
| 9 | 50800515 | BAR SPLICERS | 14 | EACH | $75.00 | $81.00 | $150.00 | $118.10 | $75.00 | $100.00 | |
| 10 | 52000110 | PREF JT STRIP SEAL | 162 | FOOT | $315.00 | $451.50 | $250.00 | $326.15 | $220.00 | $210.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $17,407.30 | $18,000.00 | $18,000.00 | $19,000.00 | $16,000.00 | |
| 12 | 70107025 | CHANGEABLE MESSAGE SN | 60 | CAL DA | $30.00 | $30.00 | $30.00 | $30.00 | $75.00 | $30.00 | |
| 13 | 70300150 | SHRT TRM PAVT MK REM | 7,680 | SQ FT | $0.0100 | $0.5000 | $0.0100 | $1.50 | $2.50 | $0.1000 | |
| 14 | 70307120 | TEMP PVT MK L4 T4 TAPE | 23,040 | FOOT | $1.05 | $1.05 | $0.2500 | $1.05 | $2.00 | $1.10 | |
| 15 | 70400100 | TEMP CONC BARRIER | 1,125 | FOOT | $27.00 | $18.00 | $29.00 | $36.40 | $30.00 | $30.00 | |
| 16 | 70400125 | PIN TEMP CONC BARRIER | 25 | EACH | $40.00 | $25.00 | $22.00 | $32.35 | $50.00 | $20.00 | |
| 17 | 70400200 | REL TEMP CONC BARRIER | 1,125 | FOOT | $7.50 | $18.00 | $4.50 | $6.20 | $12.00 | $4.00 | |
| 18 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $4,488.00 | $4,488.00 | $4,488.00 | $4,488.00 | $6,000.00 | $5,000.00 | |
| 19 | 70600327 | IMP ATTN REL FRW TL3 | 2 | EACH | $1,983.00 | $1,983.00 | $1,983.00 | $1,983.00 | $1,500.00 | $2,500.00 | |
| 20 | 78009004 | MOD URETH PM LINE 4 | 2,600 | FOOT | $2.00 | $2.00 | $2.25 | $2.00 | $2.20 | $2.00 | |
| 21 | 78009012 | MOD URETH PM LINE 12 | 350 | FOOT | $6.00 | $6.00 | $7.00 | $6.00 | $6.60 | $6.00 | |
| 22 | 78100300 | REPLACEMENT REFLECTOR | 50 | EACH | $25.00 | $25.00 | $38.95 | $25.00 | $27.50 | $25.00 | |
| 23 | 78300200 | RAISED REF PVT MK REM | 50 | EACH | $0.0100 | $15.50 | $25.00 | $25.00 | $10.00 | $30.00 | |
| 24 | 78300202 | PAVMT MRKG REM WTR BL | 1,350 | SQ FT | $2.50 | $2.50 | $3.00 | $2.50 | $2.75 | $3.00 |