2020-078-RS&SW
- Let date
- Friday, March 5, 2021
- Contract
- 62L56 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- (7.6-Mile) SMART overlay, patching and pedestrian ramps on IL 137 from south of Greenwood Avenue to north of Russell Road in the Villages of Beach Park, Winthrop Harbor and Cities of Waukegan and Zion.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J. A. Johnson Paving Company Low bidder | $4,258,746 | ||
| 2 | Payne & Dolan, Inc. | $4,828,277 | +13.4% | |
| 3 | Peter Baker & Son Co. | $5,025,027 | +18.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. A. Johnson P… | #2 Payne & Dolan, … | #3 Peter Baker & S… |
|---|---|---|---|---|---|---|---|---|
| 1 | K1003680 | MULCH | 43 | SQ YD | $15.00 | $15.00 | $18.00 | |
| 2 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $12,000.00 | $12,000.00 | $10,000.00 | |
| 3 | X0327036 | BIKE PATH REM | 125 | SQ YD | $15.00 | $8.00 | $41.00 | |
| 4 | X1700067 | STAMP COL PCC SDWLK 5 | 1,422 | SQ FT | $18.00 | $18.00 | $16.00 | |
| 5 | X4400501 | COMB C&G REMOV REPL < = 10FT | 990 | FOOT | $49.00 | $75.00 | $48.00 | |
| 6 | X4421825 | CL D PTCH T1 9 SPL | 62 | SQ YD | $78.00 | $80.00 | $169.00 | |
| 7 | X4421826 | CL D PTCH T2 9 SPL | 158 | SQ YD | $77.00 | $58.00 | $174.00 | |
| 8 | X4421827 | CL D PTCH T4 9 SPL | 102 | SQ YD | $76.00 | $36.00 | $133.00 | |
| 9 | X4421829 | CL D PTCH T3 9 SPL | 175 | SQ YD | $75.00 | $41.00 | $135.00 | |
| 10 | X5537800 | SS CLEANED 12 | 4,320 | FOOT | $2.25 | $2.00 | $2.25 | |
| 11 | X6030310 | FR & LIDS ADJUST SPL | 105 | EACH | $850.00 | $650.00 | $1,092.00 | |
| 12 | X7030005 | TEMP PAVT MKING REMOV | 68,117 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 13 | X8140238 | REBLD EX DBL HANDHOLE | 3 | EACH | $2,300.00 | $2,500.00 | $2,680.00 | |
| 14 | Z0004562 | COMB C C&G REM & REPL | 6,000 | FOOT | $40.00 | $56.65 | $48.00 | |
| 15 | Z0018500 | DRAINAGE STR CLEANED | 360 | EACH | $269.00 | $290.00 | $269.00 | |
| 16 | Z0018600 | DRAINAGE STR RECONST | 10 | EACH | $10.00 | $1,150.00 | $2,027.00 | |
| 17 | Z0030850 | TEMP INFO SIGNING | 385.5 | SQ FT | $4.00 | $4.00 | $4.00 | |
| 18 | Z0033700 | LONG JOINT SEALANT | 91,380 | FOOT | $1.90 | $1.90 | $2.11 | |
| 19 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 20 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 21 | 20100110 | TREE REMOV 6-15 | 14 | UNIT | $49.00 | $100.00 | $100.00 | |
| 22 | 20101200 | TREE ROOT PRUNING | 7 | EACH | $195.00 | $350.00 | $150.00 | |
| 23 | 20200100 | EARTH EXCAVATION | 317 | CU YD | $46.00 | $115.00 | $40.00 | |
| 24 | 21101615 | TOPSOIL F & P 4 | 545 | SQ YD | $5.98 | $5.98 | $7.00 | |
| 25 | 25000400 | NITROGEN FERT NUTR | 8.5 | POUND | $4.00 | $4.00 | $3.00 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 8.5 | POUND | $4.00 | $4.00 | $3.00 | |
| 27 | 25200110 | SODDING SALT TOLERANT | 545 | SQ YD | $15.00 | $15.00 | $13.00 | |
| 28 | 25200200 | SUPPLE WATERING | 7 | UNIT | $25.00 | $25.00 | $0.0100 | |
| 29 | 40600290 | BIT MATLS TACK CT | 113,714 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 30 | 40600400 | MIX CR JTS FLANGEWYS | 379 | TON | $100.00 | $110.00 | $175.00 | |
| 31 | 40600982 | HMA SURF REM BUTT JT | 1,266 | SQ YD | $2.00 | $10.25 | $5.00 | |
| 32 | 40601005 | HMA REPL OVER PATCH | 566 | TON | $80.00 | $105.00 | $198.00 | |
| 33 | 40604060 | HMA SC IL-9.5 D N50 | 10 | TON | $100.00 | $200.00 | $875.00 | |
| 34 | 40604062 | HMA SC IL-9.5 D N70 | 21,227 | TON | $82.00 | $70.25 | $77.70 | |
| 35 | 42001300 | PROTECTIVE COAT | 3,516 | SQ YD | $1.00 | $1.80 | $1.00 | |
| 36 | 42400200 | PC CONC SIDEWALK 5 | 11,756 | SQ FT | $7.00 | $8.75 | $9.00 | |
| 37 | 42400800 | DETECTABLE WARNINGS | 1,481 | SQ FT | $32.00 | $30.00 | $32.00 | |
| 38 | 44000155 | HMA SURF REM 1 1/2 | 252,698 | SQ YD | $2.00 | $2.30 | $3.25 | |
| 39 | 44000200 | DRIVE PAVEMENT REM | 37 | SQ YD | $25.00 | $28.00 | $42.00 | |
| 40 | 44000300 | CURB REM | 40 | FOOT | $10.00 | $12.00 | $4.00 | |
| 41 | 44000600 | SIDEWALK REM | 12,300 | SQ FT | $2.15 | $2.90 | $3.00 | |
| 42 | 44002216 | HMA RM OV PATCH 4 | 2,527 | SQ YD | $10.00 | $4.25 | $5.00 | |
| 43 | 44003100 | MEDIAN REMOVAL | 50 | SQ FT | $8.00 | $12.00 | $5.00 | |
| 44 | 44004250 | PAVED SHLD REMOVAL | 13 | SQ YD | $50.00 | $8.50 | $25.00 | |
| 45 | 44201761 | CL D PATCH T1 10 | 155 | SQ YD | $82.00 | $62.00 | $85.00 | |
| 46 | 44201765 | CL D PATCH T2 10 | 1,010 | SQ YD | $81.00 | $48.50 | $75.00 | |
| 47 | 44201769 | CL D PATCH T3 10 | 758 | SQ YD | $80.00 | $41.00 | $70.00 | |
| 48 | 44201771 | CL D PATCH T4 10 | 758 | SQ YD | $79.00 | $35.50 | $70.00 | |
| 49 | 60250200 | CB ADJUST | 4 | EACH | $350.00 | $400.00 | $525.00 | |
| 50 | 60250400 | CB ADJ NEW T1F OL | 1 | EACH | $780.00 | $800.00 | $802.00 | |
| 51 | 60255500 | MAN ADJUST | 6 | EACH | $550.00 | $425.00 | $485.00 | |
| 52 | 60257900 | MAN RECONST | 1 | EACH | $1,400.00 | $1,350.00 | $2,537.00 | |
| 53 | 60260100 | INLETS ADJUST | 7 | EACH | $350.00 | $400.00 | $275.00 | |
| 54 | 60260300 | INLETS ADJ NEW T1F OL | 2 | EACH | $750.00 | $800.00 | $596.00 | |
| 55 | 60265700 | VV ADJUST | 5 | EACH | $550.00 | $425.00 | $617.00 | |
| 56 | 60266600 | VALVE BOX ADJ | 4 | EACH | $300.00 | $300.00 | $210.00 | |
| 57 | 60300105 | FR & GRATES ADJUST | 60 | EACH | $400.00 | $400.00 | $637.00 | |
| 58 | 60404950 | FR & GRATES T24 | 15 | EACH | $400.00 | $400.00 | $325.00 | |
| 59 | 60600605 | CONC CURB TB | 132 | FOOT | $22.00 | $36.50 | $26.00 | |
| 60 | 66900200 | NON SPL WASTE DISPOSL | 205 | CU YD | $176.95 | $78.14 | $100.00 | |
| 61 | 66900530 | SOIL DISPOSAL ANALY | 10 | EACH | $1,875.00 | $1,600.00 | $1,200.00 | |
| 62 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $4,700.00 | $900.00 | $2,200.00 | |
| 63 | 66901006 | REG SUB MON | 30 | CAL DA | $550.00 | $680.00 | $780.00 | |
| 64 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,500.00 | $1,000.00 | $3,000.00 | |
| 65 | 67100100 | MOBILIZATION | 1 | L SUM | $147,000.00 | $740,000.00 | $311,586.56 | |
| 66 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 67 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 68 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $40,500.00 | $40,500.00 | $100,500.00 | |
| 69 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 70 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 71 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 72 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 73 | 70300100 | SHORT TERM PAVT MKING | 28,518 | FOOT | $0.0100 | $0.0100 | $0.2500 | |
| 74 | 70300150 | SHRT TRM PAVT MK REM | 9,506 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 75 | 70300210 | TEMP PVT MK LTR & SYM | 2,718 | SQ FT | $0.0100 | $1.00 | $0.0100 | |
| 76 | 70300220 | TEMP PVT MK LINE 4 | 156,860 | FOOT | $0.0100 | $0.2000 | $0.0100 | |
| 77 | 70300240 | TEMP PVT MK LINE 6 | 10,398 | FOOT | $0.0100 | $0.2800 | $0.0100 | |
| 78 | 70300260 | TEMP PVT MK LINE 12 | 6,319 | FOOT | $0.0100 | $0.6500 | $0.0100 | |
| 79 | 70300280 | TEMP PVT MK LINE 24 | 2,056 | FOOT | $0.0100 | $1.00 | $0.0100 | |
| 80 | 70300520 | PAVT MARK TAPE T3 4 | 14,259 | FOOT | $0.0100 | $0.0100 | $1.07 | |
| 81 | 78000100 | THPL PVT MK LTR & SYM | 2,718 | SQ FT | $3.89 | $3.89 | $3.89 | |
| 82 | 78000200 | THPL PVT MK LINE 4 | 156,860 | FOOT | $0.5000 | $0.5000 | $0.5000 | |
| 83 | 78000400 | THPL PVT MK LINE 6 | 10,398 | FOOT | $0.7500 | $0.7500 | $0.7500 | |
| 84 | 78000600 | THPL PVT MK LINE 12 | 6,319 | FOOT | $1.50 | $1.50 | $1.50 | |
| 85 | 78000650 | THPL PVT MK LINE 24 | 2,056 | FOOT | $3.89 | $3.89 | $3.89 | |
| 86 | 78100100 | RAISED REFL PAVT MKR | 5,101 | EACH | $20.00 | $20.00 | $20.00 | |
| 87 | 78300200 | RAISED REF PVT MK REM | 4,251 | EACH | $1.00 | $9.25 | $10.80 | |
| 88 | 85000200 | MAIN EX TR SIG INSTAL | 10 | EACH | $1,500.00 | $2,400.00 | $660.00 | |
| 89 | 88600600 | DET LOOP REPL | 9,130 | FOOT | $15.50 | $16.50 | $15.90 | |
| 90 | 89500400 | RELOC EX PED PUSH-BUT | 40 | EACH | $350.00 | $400.00 | $402.00 | |
| 91 | 89502376 | REBUILD EX HANDHOLE | 9 | EACH | $1,500.00 | $2,100.00 | $1,780.00 |