2019-066-RS&SW
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $814,877 | ||
| 2 | J. A. Johnson Paving Company | $852,852 | +4.7% | |
| 3 | Lindahl Brothers, Inc. | $857,175 | +5.2% | |
| 4 | K-Five Construction Corporation | $894,344 | +9.8% | |
| 5 | R. W. Dunteman Company | $895,558 | +9.9% | |
| 6 | Builders Paving, LLC | $945,888 | +16.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 J. A. Johnson P… | #3 Lindahl Brother… | #4 K-Five Construc… | #5 R. W. Dunteman … | #6 Builders Paving… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $2,995.00 | $2,995.00 | $5,000.00 | $7,300.00 | $3,194.00 | $7,250.00 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 7 | UNIT | $275.00 | $200.00 | $600.00 | $350.00 | $439.14 | $250.00 | |
| 3 | X5537800 | SS CLEANED 12 | 100 | FOOT | $6.00 | $3.00 | $25.00 | $6.00 | $3.00 | $5.00 | |
| 4 | X6030310 | FR & LIDS ADJUST SPL | 77 | EACH | $650.00 | $650.00 | $650.00 | $650.00 | $772.32 | $700.00 | |
| 5 | X7030005 | TEMP PAVT MKING REMOV | 4,778 | SQ FT | $0.3900 | $0.0100 | $0.7500 | $0.0100 | $0.3900 | $0.0500 | |
| 6 | Z0004538 | HMA DRIVEWAY PAVT 10 | 77.78 | SQ YD | $70.00 | $120.00 | $59.51 | $119.41 | $64.54 | $120.00 | |
| 7 | Z0004562 | COMB C C&G REM & REPL | 1,597 | FOOT | $33.00 | $33.00 | $34.80 | $38.85 | $33.00 | $38.65 | |
| 8 | Z0018500 | DRAINAGE STR CLEANED | 20 | EACH | $320.00 | $280.00 | $500.00 | $365.65 | $280.00 | $500.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 102.8 | SQ FT | $15.00 | $15.00 | $16.00 | $17.14 | $15.00 | $16.00 | |
| 10 | Z0033700 | LONG JOINT SEALANT | 4,312 | FOOT | $3.25 | $2.27 | $2.27 | $3.75 | $2.97 | $3.15 | |
| 11 | 20100210 | TREE REMOV OVER 15 | 43 | UNIT | $60.00 | $60.00 | $60.00 | $66.27 | $58.00 | $60.00 | |
| 12 | 20101350 | TREE PRUN OVER 10 | 11 | EACH | $100.00 | $100.00 | $100.00 | $91.41 | $80.00 | $100.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 66 | CU YD | $200.00 | $65.00 | $81.89 | $80.00 | $60.00 | $75.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 462 | SQ YD | $7.60 | $8.00 | $6.98 | $8.68 | $7.60 | $7.60 | |
| 15 | 25000400 | NITROGEN FERT NUTR | 9 | POUND | $3.00 | $20.00 | $4.00 | $3.43 | $3.00 | $3.00 | |
| 16 | 25000500 | PHOSPHORUS FERT NUTR | 9 | POUND | $3.00 | $20.00 | $4.00 | $3.43 | $3.00 | $3.00 | |
| 17 | 25000600 | POTASSIUM FERT NUTR | 9 | POUND | $3.00 | $20.00 | $4.00 | $3.43 | $3.00 | $3.00 | |
| 18 | 25200110 | SODDING SALT TOLERANT | 462 | SQ YD | $9.50 | $16.00 | $14.00 | $10.86 | $9.50 | $9.50 | |
| 19 | 25200200 | SUPPLE WATERING | 5 | UNIT | $0.0100 | $100.00 | $25.00 | $0.0100 | $0.0100 | $0.0100 | |
| 20 | 31102100 | SUB GRAN MAT C 4 | 46 | SQ YD | $50.00 | $15.00 | $16.09 | $3.00 | $23.68 | $15.50 | |
| 21 | 40400070 | ASP EMUL SLRY SEAL MC | 470 | SQ YD | $10.00 | $75.00 | $75.00 | $5.00 | $75.00 | $10.00 | |
| 22 | 40600290 | BIT MATLS TACK CT | 13,061 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.00 | $1.00 | |
| 23 | 40600400 | MIX CR JTS FLANGEWYS | 30 | TON | $90.00 | $300.00 | $250.00 | $305.00 | $523.04 | $445.00 | |
| 24 | 40600982 | HMA SURF REM BUTT JT | 379 | SQ YD | $10.00 | $3.00 | $10.00 | $3.82 | $5.35 | $38.00 | |
| 25 | 40603200 | P HMA BC IL-4.75 N50 | 813 | TON | $115.00 | $93.00 | $102.00 | $98.39 | $128.33 | $85.00 | |
| 26 | 40604060 | HMA SC IL-9.5 D N50 | 1,649 | TON | $82.00 | $75.00 | $74.00 | $87.74 | $99.27 | $68.50 | |
| 27 | 40800050 | INCIDENTAL HMA SURF | 5 | TON | $500.00 | $200.00 | $250.00 | $125.00 | $354.19 | $190.00 | |
| 28 | 42001300 | PROTECTIVE COAT | 1,273 | SQ YD | $1.00 | $1.00 | $1.54 | $1.00 | $0.5000 | $1.00 | |
| 29 | 42300200 | PCC DRIVEWAY PAVT 6 | 16 | SQ YD | $64.00 | $64.00 | $66.54 | $74.27 | $80.00 | $62.00 | |
| 30 | 42300400 | PCC DRIVEWAY PAVT 8 | 63 | SQ YD | $72.00 | $72.00 | $79.85 | $89.13 | $75.00 | $70.00 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 11,453 | SQ FT | $6.15 | $6.15 | $7.17 | $8.00 | $5.60 | $6.95 | |
| 32 | 42400800 | DETECTABLE WARNINGS | 856 | SQ FT | $30.00 | $30.00 | $30.45 | $33.99 | $32.00 | $30.00 | |
| 33 | 44000158 | HMA SURF REM 2 1/4 | 19,350 | SQ YD | $3.25 | $4.00 | $3.00 | $3.78 | $3.49 | $5.25 | |
| 34 | 44000200 | DRIVE PAVEMENT REM | 156 | SQ YD | $14.00 | $14.00 | $12.28 | $18.85 | $30.84 | $35.00 | |
| 35 | 44000600 | SIDEWALK REM | 11,558 | SQ FT | $1.80 | $1.80 | $2.05 | $2.29 | $1.75 | $2.00 | |
| 36 | 44004250 | PAVED SHLD REMOVAL | 509 | SQ YD | $12.00 | $15.00 | $9.58 | $18.72 | $8.42 | $18.00 | |
| 37 | 44201761 | CL D PATCH T1 10 | 50 | SQ YD | $110.00 | $86.00 | $70.00 | $120.00 | $28.40 | $122.00 | |
| 38 | 44201765 | CL D PATCH T2 10 | 200 | SQ YD | $110.00 | $86.00 | $70.00 | $115.00 | $28.07 | $106.50 | |
| 39 | 44201769 | CL D PATCH T3 10 | 100 | SQ YD | $110.00 | $86.00 | $70.00 | $114.00 | $28.81 | $106.00 | |
| 40 | 44201771 | CL D PATCH T4 10 | 50 | SQ YD | $110.00 | $86.00 | $70.00 | $113.00 | $28.40 | $95.50 | |
| 41 | 48102100 | AGG WEDGE SHLD TYPE B | 40 | TON | $80.00 | $75.00 | $86.12 | $142.08 | $88.70 | $72.00 | |
| 42 | 48203029 | HMA SHOULDERS 8 | 554 | SQ YD | $38.00 | $50.00 | $53.00 | $49.01 | $40.46 | $55.00 | |
| 43 | 56109210 | WATER VALVES ADJUST | 3 | EACH | $300.00 | $300.00 | $300.00 | $342.79 | $300.00 | $385.00 | |
| 44 | 60252800 | CB RECONST | 2 | EACH | $1,000.00 | $1,000.00 | $1,000.00 | $1,142.65 | $1,000.00 | $1,000.00 | |
| 45 | 60300305 | FR & LIDS ADJUST | 10 | EACH | $400.00 | $400.00 | $400.00 | $457.06 | $400.00 | $385.00 | |
| 46 | 60406100 | FR & LIDS T1 CL | 4 | EACH | $385.00 | $385.00 | $385.00 | $439.92 | $385.00 | $390.00 | |
| 47 | 60603800 | COMB CC&G TB6.12 | 91 | FOOT | $25.00 | $25.00 | $34.80 | $38.85 | $40.00 | $30.65 | |
| 48 | 66900200 | NON SPL WASTE DISPOSL | 66 | CU YD | $75.00 | $120.00 | $88.25 | $50.00 | $99.31 | $100.00 | |
| 49 | 66900530 | SOIL DISPOSAL ANALY | 5 | EACH | $1,300.00 | $1,750.00 | $1,750.00 | $1,999.63 | $1,300.00 | $1,750.00 | |
| 50 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,350.00 | $2,950.00 | $2,950.00 | $3,370.81 | $2,350.00 | $2,500.00 | |
| 51 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,000.00 | $900.00 | $900.00 | $1,028.38 | $2,000.00 | $2,500.00 | |
| 52 | 66901006 | REG SUB MON | 20 | CAL DA | $1.00 | $680.00 | $680.00 | $777.00 | $850.00 | $700.00 | |
| 53 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,200.00 | $2,500.00 | $5,500.00 | $3,500.00 | $2,875.00 | $3,000.00 | |
| 54 | 67100100 | MOBILIZATION | 1 | L SUM | $58,600.00 | $51,000.00 | $49,000.00 | $52,000.00 | $51,027.79 | $55,000.00 | |
| 55 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $6,999.00 | $40,845.26 | $12,000.00 | $10,000.00 | $14,999.00 | $30,734.90 | |
| 56 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 57 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $6,000.00 | |
| 58 | 70300100 | SHORT TERM PAVT MKING | 2,424 | FOOT | $0.5000 | $0.0100 | $0.7500 | $1.00 | $1.00 | $1.25 | |
| 59 | 70300150 | SHRT TRM PAVT MK REM | 202 | SQ FT | $3.00 | $0.0100 | $0.7500 | $1.00 | $2.00 | $8.00 | |
| 60 | 70300220 | TEMP PVT MK LINE 4 | 6,308 | FOOT | $0.4000 | $0.0100 | $0.3500 | $0.0100 | $0.4000 | $0.2500 | |
| 61 | 70300240 | TEMP PVT MK LINE 6 | 625 | FOOT | $0.6000 | $0.0100 | $0.4000 | $0.0100 | $0.6000 | $0.4500 | |
| 62 | 70300260 | TEMP PVT MK LINE 12 | 1,462 | FOOT | $1.20 | $0.0100 | $1.00 | $0.0100 | $1.20 | $0.5500 | |
| 63 | 70300280 | TEMP PVT MK LINE 24 | 450 | FOOT | $2.40 | $0.0100 | $2.00 | $0.0100 | $2.40 | $1.00 | |
| 64 | 70300520 | PAVT MARK TAPE T3 4 | 606 | FOOT | $1.35 | $0.9500 | $0.9500 | $2.00 | $0.9500 | $2.00 | |
| 65 | 72400100 | REMOV SIN PAN ASSY TA | 1 | EACH | $35.00 | $35.00 | $40.00 | $171.40 | $35.00 | $200.00 | |
| 66 | 72400500 | RELOC SIN PAN ASSY TA | 1 | EACH | $65.00 | $65.00 | $140.00 | $285.66 | $65.00 | $300.00 | |
| 67 | 72800100 | TELES STL SIN SUPPORT | 10 | FOOT | $15.50 | $15.50 | $12.00 | $13.71 | $15.50 | $15.00 | |
| 68 | 78000200 | THPL PVT MK LINE 4 | 6,308 | FOOT | $0.6000 | $0.6000 | $0.6000 | $0.5600 | $0.6000 | $0.7000 | |
| 69 | 78000400 | THPL PVT MK LINE 6 | 625 | FOOT | $0.7500 | $0.7500 | $0.7500 | $0.8600 | $0.7500 | $1.40 | |
| 70 | 78000600 | THPL PVT MK LINE 12 | 1,462 | FOOT | $1.60 | $1.60 | $1.60 | $2.29 | $1.60 | $2.50 | |
| 71 | 78000650 | THPL PVT MK LINE 24 | 450 | FOOT | $5.00 | $5.00 | $5.00 | $4.57 | $5.00 | $5.00 | |
| 72 | 78100100 | RAISED REFL PAVT MKR | 187 | EACH | $37.00 | $37.00 | $37.00 | $38.79 | $37.00 | $37.75 | |
| 73 | 78300200 | RAISED REF PVT MK REM | 181 | EACH | $9.00 | $3.00 | $19.00 | $8.57 | $16.66 | $16.00 | |
| 74 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $2,620.10 | $3,000.00 | $3,000.00 | $3,427.94 | $3,000.00 | $16,500.00 | |
| 75 | 89502376 | REBUILD EX HANDHOLE | 2 | EACH | $2,246.10 | $2,250.00 | $2,250.00 | $2,570.96 | $2,250.00 | $5,000.00 |