2019-069-RS&SW
- Let date
- Friday, January 17, 2020
- Contract
- 62J54 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- 4.6 miles of designed overlay and ADA pedestrian ramp improvements on Golf road from IL 43 (Waukegan Road) to McCormick Boulevard in the Villages of Glenview, Golf, Morton Grove, Skokie and City of Evanston.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $5,648,000 | ||
| 2 | Plote Construction, Inc. | $5,948,168 | +5.3% | |
| 3 | Peter Baker & Son Co. | $6,508,470 | +15.2% | |
| 4 | Arrow Road Construction Co. | $6,590,582 | +16.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 Plote Construct… | #3 Peter Baker & S… | #4 Arrow Road Cons… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $22,697.25 | $92,300.00 | $20,000.00 | $22,000.00 | |
| 2 | X0326898 | CENTERLN RUM STRIP 16 | 3,791 | FOOT | $2.25 | $1.00 | $2.25 | $1.89 | |
| 3 | X5537800 | SS CLEANED 12 | 2,000 | FOOT | $5.00 | $3.00 | $3.00 | $5.00 | |
| 4 | X6030310 | FR & LIDS ADJUST SPL | 100 | EACH | $660.00 | $650.00 | $685.00 | $685.00 | |
| 5 | X7030005 | TEMP PAVT MKING REMOV | 39,948 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 6 | X7240600 | REM RE-ERECT EX SIGN | 6 | EACH | $125.00 | $150.00 | $125.00 | $150.00 | |
| 7 | X7800815 | HS THPL PM LN 4 | 7,582 | FOOT | $0.8500 | $0.6000 | $0.8500 | $0.5800 | |
| 8 | Z0004562 | COMB C C&G REM & REPL | 4,080 | FOOT | $36.00 | $37.00 | $40.00 | $40.00 | |
| 9 | Z0018500 | DRAINAGE STR CLEANED | 75 | EACH | $360.00 | $375.00 | $325.00 | $360.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 359.8 | SQ FT | $16.00 | $3.00 | $16.00 | $3.00 | |
| 11 | Z0033700 | LONG JOINT SEALANT | 81,500 | FOOT | $2.20 | $2.25 | $1.91 | $2.19 | |
| 12 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $3,500.00 | $1,000.00 | $7,500.00 | |
| 13 | Z0053600 | RESET BENCH MONUMENT | 1 | EACH | $1,600.00 | $1,500.00 | $450.00 | $2,000.00 | |
| 14 | Z0064800 | SELECTIVE CLEARING | 46 | UNIT | $300.00 | $299.00 | $405.00 | $299.00 | |
| 15 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 20101200 | TREE ROOT PRUNING | 16 | EACH | $100.00 | $100.00 | $200.00 | $100.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 217 | CU YD | $62.00 | $5.00 | $95.00 | $79.00 | |
| 19 | 20201200 | REM & DISP UNS MATL | 217 | CU YD | $65.00 | $5.00 | $150.00 | $79.00 | |
| 20 | 21101615 | TOPSOIL F & P 4 | 938 | SQ YD | $7.00 | $8.00 | $7.30 | $6.98 | |
| 21 | 25200110 | SODDING SALT TOLERANT | 938 | SQ YD | $14.00 | $9.50 | $9.50 | $14.00 | |
| 22 | 25200200 | SUPPLE WATERING | 10 | UNIT | $25.00 | $0.0100 | $0.0100 | $25.00 | |
| 23 | 35501308 | HMA BASE CSE 6 | 460 | SQ YD | $69.00 | $72.00 | $60.00 | $68.25 | |
| 24 | 40600290 | BIT MATLS TACK CT | 94,989 | POUND | $0.5000 | $0.0100 | $2.50 | $1.49 | |
| 25 | 40600400 | MIX CR JTS FLANGEWYS | 213 | TON | $500.00 | $50.00 | $585.00 | $185.00 | |
| 26 | 40600982 | HMA SURF REM BUTT JT | 1,835 | SQ YD | $15.00 | $19.00 | $1.00 | $4.74 | |
| 27 | 40602985 | HMA BC IL-9.5 N70 | 15,612 | TON | $64.00 | $76.00 | $77.00 | $77.70 | |
| 28 | 40604060 | HMA SC IL-9.5 D N50 | 26 | TON | $190.00 | $275.00 | $258.00 | $380.06 | |
| 29 | 40605026 | P HMA SC SMA 9.5 F N80 | 13,858 | TON | $92.75 | $80.00 | $111.00 | $110.50 | |
| 30 | 42001300 | PROTECTIVE COAT | 3,381 | SQ YD | $1.25 | $1.25 | $1.00 | $1.00 | |
| 31 | 42300400 | PCC DRIVEWAY PAVT 8 | 230 | SQ YD | $61.00 | $65.00 | $76.00 | $76.00 | |
| 32 | 42400200 | PC CONC SIDEWALK 5 | 18,700 | SQ FT | $6.10 | $7.00 | $6.00 | $6.00 | |
| 33 | 42400800 | DETECTABLE WARNINGS | 1,631 | SQ FT | $31.00 | $35.00 | $32.00 | $32.00 | |
| 34 | 44000156 | HMA SURF REM 1 3/4 | 2,003 | SQ YD | $3.00 | $5.25 | $2.75 | $19.40 | |
| 35 | 44000164 | HMA SURF REM 3 3/4 | 139,388 | SQ YD | $5.25 | $9.95 | $6.75 | $10.25 | |
| 36 | 44000200 | DRIVE PAVEMENT REM | 460 | SQ YD | $14.50 | $16.00 | $13.00 | $16.00 | |
| 37 | 44000600 | SIDEWALK REM | 18,700 | SQ FT | $2.00 | $2.00 | $2.00 | $2.00 | |
| 38 | 44003100 | MEDIAN REMOVAL | 81 | SQ FT | $6.30 | $10.00 | $12.00 | $12.00 | |
| 39 | 44201761 | CL D PATCH T1 10 | 1,000 | SQ YD | $106.00 | $35.00 | $95.00 | $30.00 | |
| 40 | 44201765 | CL D PATCH T2 10 | 1,750 | SQ YD | $102.00 | $35.00 | $90.00 | $29.00 | |
| 41 | 44201769 | CL D PATCH T3 10 | 1,750 | SQ YD | $98.00 | $35.00 | $85.00 | $28.00 | |
| 42 | 44201771 | CL D PATCH T4 10 | 1,500 | SQ YD | $96.00 | $35.00 | $80.00 | $28.00 | |
| 43 | 60250200 | CB ADJUST | 15 | EACH | $420.00 | $500.00 | $400.00 | $400.00 | |
| 44 | 60252800 | CB RECONST | 5 | EACH | $1,260.00 | $1,200.00 | $1,000.00 | $1,000.00 | |
| 45 | 60255500 | MAN ADJUST | 19 | EACH | $460.00 | $500.00 | $450.00 | $450.00 | |
| 46 | 60257900 | MAN RECONST | 2 | EACH | $1,450.00 | $1,400.00 | $1,350.00 | $1,350.00 | |
| 47 | 60260100 | INLETS ADJUST | 2 | EACH | $360.00 | $400.00 | $400.00 | $400.00 | |
| 48 | 60262700 | INLETS RECONST | 3 | EACH | $1,050.00 | $1,000.00 | $900.00 | $900.00 | |
| 49 | 60266600 | VALVE BOX ADJ | 4 | EACH | $310.00 | $350.00 | $325.00 | $325.00 | |
| 50 | 60300105 | FR & GRATES ADJUST | 5 | EACH | $410.00 | $450.00 | $400.00 | $400.00 | |
| 51 | 60300305 | FR & LIDS ADJUST | 5 | EACH | $410.00 | $500.00 | $500.00 | $500.00 | |
| 52 | 60406000 | FR & LIDS T1 OL | 5 | EACH | $360.00 | $400.00 | $495.00 | $495.00 | |
| 53 | 60406100 | FR & LIDS T1 CL | 25 | EACH | $360.00 | $400.00 | $495.00 | $495.00 | |
| 54 | 60618300 | CONC MEDIAN SURF 4 | 81 | SQ FT | $6.00 | $15.00 | $24.00 | $24.00 | |
| 55 | 66900200 | NON SPL WASTE DISPOSL | 217 | CU YD | $100.00 | $210.00 | $185.00 | $160.00 | |
| 56 | 66900530 | SOIL DISPOSAL ANALY | 8 | EACH | $1,650.00 | $1,200.00 | $1,300.00 | $1,300.00 | |
| 57 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,950.00 | $2,500.00 | $2,400.00 | $2,000.00 | |
| 58 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $900.00 | $2,200.00 | $2,100.00 | $750.00 | |
| 59 | 66901006 | REG SUB MON | 5 | CAL DA | $680.00 | $870.00 | $980.00 | $1,000.00 | |
| 60 | 67000400 | ENGR FIELD OFFICE A | 8 | CAL MO | $3,500.00 | $3,300.00 | $3,000.00 | $2,500.00 | |
| 61 | 67100100 | MOBILIZATION | 1 | L SUM | $334,214.50 | $345,000.00 | $388,000.00 | $390,000.00 | |
| 62 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $100.00 | $1.00 | $1.00 | $1.00 | |
| 63 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $152,000.00 | $323,000.00 | $235,000.00 | $353,400.00 | |
| 64 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $100.00 | $1.00 | $1.00 | $1.00 | |
| 65 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $1.00 | $1.00 | $1.00 | |
| 66 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $7,500.00 | $1.00 | $7,000.00 | $1.00 | |
| 67 | 70300100 | SHORT TERM PAVT MKING | 70,191 | FOOT | $0.8000 | $0.0100 | $0.3500 | $0.0100 | |
| 68 | 70300150 | SHRT TRM PAVT MK REM | 23,397 | SQ FT | $1.35 | $0.0100 | $0.0100 | $0.0100 | |
| 69 | 70300210 | TEMP PVT MK LTR & SYM | 2,627 | SQ FT | $1.50 | $1.00 | $1.50 | $0.0100 | |
| 70 | 70300220 | TEMP PVT MK LINE 4 | 58,761 | FOOT | $0.2200 | $0.2000 | $0.2200 | $0.0100 | |
| 71 | 70300240 | TEMP PVT MK LINE 6 | 9,346 | FOOT | $0.5000 | $0.2600 | $0.5000 | $0.0100 | |
| 72 | 70300260 | TEMP PVT MK LINE 12 | 2,486 | FOOT | $0.8000 | $0.6000 | $0.8000 | $0.0100 | |
| 73 | 70300280 | TEMP PVT MK LINE 24 | 2,209 | FOOT | $1.50 | $1.00 | $1.50 | $0.0100 | |
| 74 | 70300520 | PAVT MARK TAPE T3 4 | 17,548 | FOOT | $1.20 | $0.0100 | $0.7500 | $1.32 | |
| 75 | 78000100 | THPL PVT MK LTR & SYM | 2,627 | SQ FT | $4.00 | $4.00 | $4.00 | $4.00 | |
| 76 | 78000200 | THPL PVT MK LINE 4 | 58,761 | FOOT | $0.5000 | $0.5500 | $0.5000 | $0.5500 | |
| 77 | 78000400 | THPL PVT MK LINE 6 | 9,346 | FOOT | $0.6500 | $0.8000 | $0.6500 | $0.8000 | |
| 78 | 78000500 | THPL PVT MK LINE 8 | 660 | FOOT | $1.00 | $1.25 | $1.00 | $1.25 | |
| 79 | 78000600 | THPL PVT MK LINE 12 | 2,486 | FOOT | $1.50 | $2.00 | $1.50 | $2.00 | |
| 80 | 78000650 | THPL PVT MK LINE 24 | 2,209 | FOOT | $4.00 | $4.00 | $4.00 | $4.00 | |
| 81 | 78009000 | MOD URETH PM LTR-SYM | 39 | SQ FT | $6.00 | $9.00 | $6.00 | $9.00 | |
| 82 | 78009004 | MOD URETH PM LINE 4 | 1,620 | FOOT | $1.85 | $3.00 | $1.85 | $3.00 | |
| 83 | 78009006 | MOD URETH PM LINE 6 | 115 | FOOT | $4.00 | $4.50 | $4.00 | $4.50 | |
| 84 | 78009012 | MOD URETH PM LINE 12 | 25 | FOOT | $10.00 | $9.00 | $10.00 | $9.00 | |
| 85 | 78100100 | RAISED REFL PAVT MKR | 1,500 | EACH | $25.00 | $25.00 | $25.00 | $25.00 | |
| 86 | 78300200 | RAISED REF PVT MK REM | 1,500 | EACH | $7.50 | $10.00 | $10.00 | $4.55 | |
| 87 | 85000200 | MAIN EX TR SIG INSTAL | 7 | EACH | $2,600.00 | $2,500.00 | $2,500.00 | $2,500.00 | |
| 88 | 88600600 | DET LOOP REPL | 6,415 | FOOT | $17.00 | $17.00 | $17.00 | $17.00 | |
| 89 | 89500400 | RELOC EX PED PUSH-BUT | 10 | EACH | $430.00 | $425.00 | $425.00 | $425.00 | |
| 90 | 89502376 | REBUILD EX HANDHOLE | 15 | EACH | $2,200.00 | $2,100.00 | $2,100.00 | $2,100.00 |