(3197A&B)RS-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Arrow Road Construction Co. Low bidder | $1,518,531 | ||
| 2 | J. A. Johnson Paving Company | $1,573,573 | +3.6% | |
| 3 | Bigane Paving Company | $1,749,890 | +15.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Arrow Road Cons… | #2 J. A. Johnson P… | #3 Bigane Paving C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $8,000.00 | $14,000.00 | $5,200.00 | |
| 2 | X0327611 | REM & REIN BRIC PAVER | 32 | SQ FT | $10.00 | $15.00 | $20.00 | |
| 3 | X2010350 | TREE REMOV ACRES SPL | 0.15 | ACRE | $20,000.00 | $20,000.00 | $20,000.00 | |
| 4 | X2020110 | GRADING & SHAP SHLDRS | 24 | UNIT | $70.00 | $150.00 | $110.00 | |
| 5 | X2501800 | SEEDING CL 4 MOD | 0.15 | ACRE | $1,600.00 | $1,000.00 | $4,000.00 | |
| 6 | X5537800 | SS CLEANED 12 | 280 | FOOT | $3.50 | $3.50 | $2.50 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 80 | EACH | $600.00 | $600.00 | $575.00 | |
| 8 | X7030005 | TEMP PAVT MKING REMOV | 11,665 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 9 | X7240500 | RELOC EX SIGNS | 5 | EACH | $200.00 | $150.00 | $120.00 | |
| 10 | X8950205 | REBLD EX HANDHOLE SPL | 1 | EACH | $2,850.00 | $2,850.00 | $2,850.00 | |
| 11 | Z0004562 | COMB C C&G REM & REPL | 5,120 | FOOT | $25.50 | $28.00 | $25.50 | |
| 12 | Z0018500 | DRAINAGE STR CLEANED | 28 | EACH | $300.00 | $300.00 | $325.00 | |
| 13 | Z0030850 | TEMP INFO SIGNING | 102.8 | SQ FT | $15.00 | $15.00 | $15.00 | |
| 14 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 16 | 20100110 | TREE REMOV 6-15 | 15 | UNIT | $20.00 | $20.00 | $20.00 | |
| 17 | 20100210 | TREE REMOV OVER 15 | 30 | UNIT | $25.00 | $25.00 | $25.00 | |
| 18 | 20200100 | EARTH EXCAVATION | 145 | CU YD | $65.00 | $65.00 | $65.00 | |
| 19 | 21101615 | TOPSOIL F & P 4 | 988 | SQ YD | $5.00 | $5.00 | $5.50 | |
| 20 | 25000400 | NITROGEN FERT NUTR | 12 | POUND | $4.00 | $2.00 | $3.00 | |
| 21 | 25000500 | PHOSPHORUS FERT NUTR | 12 | POUND | $4.00 | $2.00 | $3.00 | |
| 22 | 25000600 | POTASSIUM FERT NUTR | 12 | POUND | $4.00 | $2.00 | $3.00 | |
| 23 | 25100630 | EROSION CONTR BLANKET | 745 | SQ YD | $4.00 | $3.00 | $1.25 | |
| 24 | 25200110 | SODDING SALT TOLERANT | 1,002 | SQ YD | $5.00 | $10.00 | $9.00 | |
| 25 | 25200200 | SUPPLE WATERING | 3.5 | UNIT | $9.00 | $25.00 | $300.00 | |
| 26 | 35501308 | HMA BASE CSE 6 | 5 | SQ YD | $85.00 | $140.00 | $400.00 | |
| 27 | 35501316 | HMA BASE CSE 8 | 12 | SQ YD | $90.00 | $185.00 | $450.00 | |
| 28 | 40600290 | BIT MATLS TACK CT | 41,751 | POUND | $1.00 | $0.0100 | $0.5000 | |
| 29 | 40600400 | MIX CR JTS FLANGEWYS | 188 | TON | $85.00 | $1.00 | $100.00 | |
| 30 | 40600827 | P LB MM IL-4.75 N50 | 2,551 | TON | $79.20 | $78.50 | $88.00 | |
| 31 | 40600982 | HMA SURF REM BUTT JT | 745 | SQ YD | $5.00 | $2.00 | $14.00 | |
| 32 | 40603335 | HMA SC "D" N50 | 2 | TON | $225.00 | $390.00 | $200.00 | |
| 33 | 40603340 | HMA SC "D" N70 | 5,244 | TON | $67.50 | $72.00 | $73.00 | |
| 34 | 42001300 | PROTECTIVE COAT | 2,145 | SQ YD | $0.5000 | $0.5000 | $0.5000 | |
| 35 | 42300200 | PCC DRIVEWAY PAVT 6 | 125 | SQ YD | $56.00 | $56.00 | $55.00 | |
| 36 | 42300400 | PCC DRIVEWAY PAVT 8 | 7 | SQ YD | $57.00 | $57.00 | $57.00 | |
| 37 | 42400200 | PC CONC SIDEWALK 5 | 14,907 | SQ FT | $5.50 | $6.05 | $5.35 | |
| 38 | 42400800 | DETECTABLE WARNINGS | 1,188 | SQ FT | $24.00 | $24.00 | $24.00 | |
| 39 | 44000155 | HMA SURF REM 1 1/2 | 1,702 | SQ YD | $1.50 | $1.70 | $3.75 | |
| 40 | 44000158 | HMA SURF REM 2 1/4 | 60,718 | SQ YD | $1.60 | $2.60 | $4.25 | |
| 41 | 44000200 | DRIVE PAVEMENT REM | 135 | SQ YD | $16.00 | $16.00 | $16.00 | |
| 42 | 44000600 | SIDEWALK REM | 14,208 | SQ FT | $1.50 | $2.00 | $1.25 | |
| 43 | 44201777 | CL D PATCH T2 11 | 319 | SQ YD | $27.00 | $96.00 | $65.00 | |
| 44 | 44201781 | CL D PATCH T3 11 | 90 | SQ YD | $27.00 | $76.00 | $60.00 | |
| 45 | 44201783 | CL D PATCH T4 11 | 1,049 | SQ YD | $26.00 | $76.00 | $60.00 | |
| 46 | 48102100 | AGG WEDGE SHLD TYPE B | 64 | TON | $50.00 | $55.00 | $80.00 | |
| 47 | 60250400 | CB ADJ NEW T1F OL | 1 | EACH | $605.00 | $605.00 | $600.00 | |
| 48 | 60252800 | CB RECONST | 2 | EACH | $900.00 | $900.00 | $900.00 | |
| 49 | 60255800 | MAN ADJ NEW T1F CL | 1 | EACH | $700.00 | $700.00 | $700.00 | |
| 50 | 60257900 | MAN RECONST | 2 | EACH | $1,000.00 | $1,000.00 | $1,000.00 | |
| 51 | 60266600 | VALVE BOX ADJ | 9 | EACH | $180.00 | $180.00 | $160.00 | |
| 52 | 60300105 | FR & GRATES ADJUST | 2 | EACH | $325.00 | $325.00 | $325.00 | |
| 53 | 60300305 | FR & LIDS ADJUST | 44 | EACH | $280.00 | $305.00 | $280.00 | |
| 54 | 60404940 | FR & GRATES T23 | 2 | EACH | $375.00 | $350.00 | $375.00 | |
| 55 | 60406000 | FR & LIDS T1 OL | 15 | EACH | $305.00 | $305.00 | $305.00 | |
| 56 | 60406100 | FR & LIDS T1 CL | 15 | EACH | $305.00 | $305.00 | $305.00 | |
| 57 | 66900200 | NON SPL WASTE DISPOSL | 145 | CU YD | $120.00 | $110.00 | $100.00 | |
| 58 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $1,500.00 | $2,800.00 | $2,500.00 | |
| 59 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,600.00 | $1,360.00 | $750.00 | |
| 60 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,500.00 | $3,000.00 | $3,000.00 | |
| 61 | 67100100 | MOBILIZATION | 1 | L SUM | $117,400.00 | $90,000.00 | $100,000.00 | |
| 62 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $94,000.00 | $36,145.44 | $1.00 | |
| 63 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $18,000.00 | |
| 64 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 65 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $7,100.00 | |
| 66 | 70300100 | SHORT TERM PAVT MKING | 30,809 | FOOT | $0.0100 | $0.0100 | $1.50 | |
| 67 | 70300150 | SHRT TRM PAVT MK REM | 10,270 | SQ FT | $0.0100 | $0.0100 | $2.00 | |
| 68 | 70300210 | TEMP PVT MK LTR & SYM | 219 | SQ FT | $0.0100 | $0.0100 | $1.00 | |
| 69 | 70300220 | TEMP PVT MK LINE 4 | 16,545 | FOOT | $0.0100 | $0.0100 | $0.1000 | |
| 70 | 70300240 | TEMP PVT MK LINE 6 | 3,405 | FOOT | $0.0100 | $0.0100 | $0.2000 | |
| 71 | 70300250 | TEMP PVT MK LINE 8 | 624 | FOOT | $0.0100 | $0.0100 | $0.4000 | |
| 72 | 70300260 | TEMP PVT MK LINE 12 | 336 | FOOT | $0.0100 | $0.0100 | $0.6000 | |
| 73 | 70300280 | TEMP PVT MK LINE 24 | 652 | FOOT | $0.0100 | $0.0100 | $1.00 | |
| 74 | 70300520 | PAVT MARK TAPE T3 4 | 7,703 | FOOT | $1.35 | $0.8500 | $0.4500 | |
| 75 | 72400200 | REMOV SIN PAN ASSY TB | 1 | EACH | $35.00 | $35.00 | $100.00 | |
| 76 | 72400600 | RELOC SIN PAN ASSY TB | 2 | EACH | $35.00 | $65.00 | $135.00 | |
| 77 | 78000100 | THPL PVT MK LTR & SYM | 219 | SQ FT | $3.50 | $3.50 | $4.00 | |
| 78 | 78000200 | THPL PVT MK LINE 4 | 16,545 | FOOT | $0.5200 | $0.5200 | $0.5000 | |
| 79 | 78000400 | THPL PVT MK LINE 6 | 3,405 | FOOT | $0.8000 | $0.8000 | $0.8000 | |
| 80 | 78000500 | THPL PVT MK LINE 8 | 624 | FOOT | $1.20 | $1.20 | $1.10 | |
| 81 | 78000600 | THPL PVT MK LINE 12 | 336 | FOOT | $1.75 | $1.75 | $2.20 | |
| 82 | 78000650 | THPL PVT MK LINE 24 | 652 | FOOT | $3.50 | $3.50 | $3.85 | |
| 83 | 78100100 | RAISED REFL PAVT MKR | 701 | EACH | $23.50 | $23.50 | $25.00 | |
| 84 | 78300200 | RAISED REF PVT MK REM | 565 | EACH | $8.00 | $2.00 | $5.00 | |
| 85 | 85000200 | MAIN EX TR SIG INSTAL | 5 | EACH | $420.00 | $420.00 | $420.00 | |
| 86 | 88600600 | DET LOOP REPL | 1,612 | FOOT | $16.00 | $16.00 | $16.00 | |
| 87 | 89500400 | RELOC EX PED PUSH-BUT | 10 | EACH | $327.00 | $327.00 | $327.00 | |
| 88 | 89502376 | REBUILD EX HANDHOLE | 6 | EACH | $2,830.00 | $2,830.00 | $2,830.00 |