$173.96Avg low bid / EACH
$241.35Avg of all bids
—Avg engineer's estimate
5Jobs · 91 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 2 | 68 | $189.41 | $203.68 |
| 2025 | 3 | 23 | $128.26 | $283.44 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 76U38 | Madison, St.clairDistrict 8 | 60 EACH | $200.00 | Gerstner Electric, Inc. |
| Apr 24, 2026 | 97840 | MadisonDistrict 8 | 8 EACH | $110.00 | Christ Bros. Asphalt, Inc. |
| Aug 1, 2025 | 61L46 | DupageDistrict 1 | 4 EACH | $250.00 | A Lamp Concrete Contractors, Inc. |
| Apr 25, 2025 | 97839 | MadisonDistrict 8 | 18 EACH | $65.00 | Charles E. Mahoney Co. |
| Jan 17, 2025 | 61K68 | KaneDistrict 1 | 1 EACH | $780.00 | Martam Construction Incorporated |