2015-038B
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $644,048 | ||
| 2 | D. Construction, Inc. | $773,452 | +20.1% | |
| 3 | P. T. Ferro Construction Co. | $851,904 | +32.3% | |
| 4 | Lorusso Cement Contractors, Inc. | $872,110 | +35.4% | |
| 5 | Phoenix Corporation of the Quad Cities | $873,996 | +35.7% | |
| 6 | Riber Construction, Inc. | $972,637 | +51.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 D. Construction… | #3 P. T. Ferro Con… | #4 Lorusso Cement … | #5 Phoenix Corpora… | #6 Riber Construct… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 919 | SQ FT | $1.25 | $2.10 | $2.00 | $2.10 | $2.75 | $3.63 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,930.00 | $1,000.00 | $5,000.00 | $7,245.00 | $31,000.00 | $9,300.00 | |
| 3 | X7015005 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $25.20 | $50.00 | $25.00 | $36.75 | $50.00 | $50.00 | |
| 4 | X7030005 | TEMP PAVT MKING REMOV | 5,249 | SQ FT | $0.9500 | $0.5000 | $0.0100 | $0.7400 | $0.4500 | $0.4500 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,000.00 | $2,000.00 | $5,000.00 | $6,242.25 | $4,800.00 | $6,000.00 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $15.10 | $25.00 | $15.00 | $15.75 | $20.00 | $15.00 | |
| 7 | Z0054400 | ROCK FILL | 160 | CU YD | $62.75 | $45.00 | $75.00 | $52.90 | $75.00 | $67.00 | |
| 8 | Z0062456 | TEMP PAVEMENT | 1,306 | SQ YD | $33.45 | $35.20 | $35.00 | $43.41 | $31.15 | $35.20 | |
| 9 | 20100110 | TREE REMOV 6-15 | 34 | UNIT | $30.00 | $33.00 | $30.00 | $57.75 | $40.00 | $30.00 | |
| 10 | 20100210 | TREE REMOV OVER 15 | 36 | UNIT | $40.00 | $44.00 | $40.00 | $57.75 | $40.00 | $40.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 1,365 | CU YD | $12.55 | $19.50 | $35.00 | $23.12 | $24.00 | $42.00 | |
| 12 | 20201200 | REM & DISP UNS MATL | 430 | CU YD | $11.50 | $25.00 | $30.00 | $40.83 | $24.00 | $34.00 | |
| 13 | 20400800 | FURNISHED EXCAVATION | 152 | CU YD | $11.85 | $20.00 | $35.00 | $54.05 | $24.00 | $48.00 | |
| 14 | 20700220 | POROUS GRAN EMBANK | 195 | CU YD | $44.50 | $45.00 | $125.00 | $50.20 | $105.00 | $63.00 | |
| 15 | 21101625 | TOPSOIL F & P 6 | 3,872 | SQ YD | $7.05 | $9.90 | $5.20 | $7.35 | $4.00 | $7.00 | |
| 16 | 25000210 | SEEDING CL 2A | 0.7 | ACRE | $2,517.00 | $2,897.40 | $2,400.00 | $2,625.00 | $2,500.00 | $2,500.00 | |
| 17 | 25000310 | SEEDING CL 4 | 0.1 | ACRE | $1,561.00 | $1,421.53 | $6,900.00 | $16,275.00 | $15,500.00 | $15,500.00 | |
| 18 | 25000400 | NITROGEN FERT NUTR | 72 | POUND | $2.00 | $3.30 | $2.00 | $2.10 | $2.00 | $2.00 | |
| 19 | 25000500 | PHOSPHORUS FERT NUTR | 72 | POUND | $2.00 | $3.30 | $2.00 | $2.10 | $2.00 | $2.00 | |
| 20 | 25000600 | POTASSIUM FERT NUTR | 72 | POUND | $2.00 | $3.30 | $2.00 | $2.10 | $2.00 | $2.00 | |
| 21 | 25100630 | EROSION CONTR BLANKET | 3,872 | SQ YD | $1.40 | $0.8300 | $1.20 | $1.47 | $1.45 | $1.40 | |
| 22 | 28000250 | TEMP EROS CONTR SEED | 400 | POUND | $0.0100 | $2.09 | $8.00 | $6.83 | $2.75 | $6.50 | |
| 23 | 28000305 | TEMP DITCH CHECKS | 40 | FOOT | $8.25 | $10.34 | $8.00 | $31.50 | $11.00 | $30.00 | |
| 24 | 28000400 | PERIMETER EROS BAR | 2,273 | FOOT | $2.10 | $2.31 | $2.00 | $5.18 | $3.00 | $4.50 | |
| 25 | 28001100 | TEMP EROS CONTR BLANK | 3,872 | SQ YD | $0.0100 | $0.7700 | $1.20 | $2.30 | $2.00 | $2.00 | |
| 26 | 28100127 | STONE RIPRAP CL B4 | 36 | SQ YD | $59.75 | $60.00 | $70.00 | $17.48 | $120.00 | $100.00 | |
| 27 | 28200200 | FILTER FABRIC | 36 | SQ YD | $4.75 | $3.00 | $5.00 | $9.37 | $1.50 | $3.50 | |
| 28 | 30300001 | AGG SUBGRADE IMPROVE | 50 | CU YD | $44.20 | $45.00 | $50.00 | $47.96 | $90.00 | $69.00 | |
| 29 | 30300112 | AGG SUBGRADE IMPR 12 | 2,848 | SQ YD | $12.95 | $16.50 | $14.00 | $14.26 | $18.00 | $23.00 | |
| 30 | 31101200 | SUB GRAN MAT B 4 | 1,409 | SQ YD | $4.90 | $6.00 | $4.50 | $5.98 | $12.00 | $10.00 | |
| 31 | 40600290 | BIT MATLS TACK CT | 1,343 | POUND | $1.25 | $0.0100 | $2.50 | $0.5800 | $0.0100 | $0.8200 | |
| 32 | 40600635 | LEV BIND MM N70 | 126 | TON | $85.00 | $77.00 | $80.00 | $83.84 | $90.00 | $77.00 | |
| 33 | 40600982 | HMA SURF REM BUTT JT | 24 | SQ YD | $12.15 | $17.60 | $0.0100 | $12.08 | $75.00 | $17.60 | |
| 34 | 40603340 | HMA SC "D" N70 | 251 | TON | $76.00 | $77.00 | $80.00 | $87.40 | $100.00 | $77.00 | |
| 35 | 44000100 | PAVEMENT REM | 1,418 | SQ YD | $6.00 | $12.10 | $14.00 | $17.88 | $12.00 | $12.10 | |
| 36 | 44000158 | HMA SURF REM 2 1/4 | 2,984 | SQ YD | $1.75 | $3.10 | $4.50 | $5.98 | $4.50 | $3.10 | |
| 37 | 44004250 | PAVED SHLD REMOVAL | 2,487 | SQ YD | $3.60 | $11.00 | $8.00 | $11.16 | $10.00 | $11.00 | |
| 38 | 44201809 | CL D PATCH T4 13 | 112 | SQ YD | $80.00 | $110.00 | $85.00 | $119.60 | $80.00 | $110.00 | |
| 39 | 48203029 | HMA SHOULDERS 8 | 2,534 | SQ YD | $27.25 | $34.10 | $30.00 | $35.08 | $29.25 | $34.10 | |
| 40 | 50100100 | REM EXIST STRUCT | 1 | EACH | $0.0100 | $10,000.00 | $28,000.00 | $9,430.00 | $48,000.00 | $25,000.00 | |
| 41 | 50200450 | REM/DISP UNS MATL-STR | 160 | CU YD | $24.85 | $25.00 | $0.0100 | $40.25 | $35.00 | $42.00 | |
| 42 | 50800105 | REINFORCEMENT BARS | 13,870 | POUND | $1.25 | $2.50 | $1.20 | $1.26 | $1.55 | $1.11 | |
| 43 | 50800515 | BAR SPLICERS | 46 | EACH | $12.90 | $20.00 | $14.00 | $10.82 | $21.00 | $13.25 | |
| 44 | 52200020 | TEMP SOIL RETEN SYSTM | 570 | SQ FT | $0.0100 | $50.00 | $75.00 | $68.25 | $5.00 | $80.00 | |
| 45 | 54003000 | CONC BOX CUL | 73 | CU YD | $1,020.00 | $750.00 | $1,600.00 | $1,159.20 | $1,100.00 | $1,500.00 | |
| 46 | 60100060 | CONC HDWL FOR P DRAIN | 4 | EACH | $200.00 | $250.00 | $300.00 | $414.75 | $325.00 | $570.00 | |
| 47 | 60108100 | PIPE UNDERDRAIN 4 SP | 87 | FOOT | $18.15 | $20.00 | $18.00 | $17.12 | $30.00 | $30.00 | |
| 48 | 60108204 | PIPE UNDERDR T 2 4 | 2,238 | FOOT | $8.80 | $16.00 | $18.00 | $9.66 | $15.00 | $20.00 | |
| 49 | 66900200 | NON SPL WASTE DISPOSL | 570 | CU YD | $90.50 | $65.00 | $70.00 | $109.94 | $25.00 | $52.00 | |
| 50 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $6,950.00 | $7,700.00 | $3,100.00 | $3,570.00 | $6,000.00 | $3,600.00 | |
| 51 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,720.00 | $1,500.00 | $1,200.00 | $1,596.00 | $2,200.00 | $1,950.00 | |
| 52 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,025.00 | $3,000.00 | $1,000.00 | $3,220.00 | $1,500.00 | $3,000.00 | |
| 53 | 67100100 | MOBILIZATION | 1 | L SUM | $38,200.00 | $34,200.00 | $50,000.00 | $23,000.00 | $88,636.82 | $58,500.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 446 | FOOT | $1.15 | $1.00 | $0.0100 | $1.58 | $2.00 | $1.00 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 148 | SQ FT | $3.80 | $1.00 | $0.0100 | $10.50 | $3.50 | $2.00 | |
| 56 | 70300220 | TEMP PVT MK LINE 4 | 5,568 | FOOT | $0.2000 | $0.5000 | $0.0100 | $0.3200 | $0.3000 | $0.3000 | |
| 57 | 70300260 | TEMP PVT MK LINE 12 | 398 | FOOT | $0.6000 | $1.00 | $0.0100 | $0.9500 | $1.00 | $1.00 | |
| 58 | 70300904 | PAVT MARK TAPE T4 4 | 9,130 | FOOT | $1.00 | $1.00 | $1.00 | $0.9500 | $0.9500 | $0.9500 | |
| 59 | 70400100 | TEMP CONC BARRIER | 1,209 | FOOT | $24.60 | $28.00 | $30.00 | $25.30 | $32.00 | $30.00 | |
| 60 | 70400200 | REL TEMP CONC BARRIER | 1,209 | FOOT | $6.40 | $12.00 | $7.00 | $14.95 | $6.00 | $4.00 | |
| 61 | 70600260 | IMP ATTN TEMP FRN TL3 | 4 | EACH | $4,550.00 | $4,500.00 | $2,500.00 | $4,725.00 | $5,900.00 | $9,000.00 | |
| 62 | 70600332 | IMP ATTN REL FRN TL3 | 4 | EACH | $2,250.00 | $1,500.00 | $1,500.00 | $2,328.90 | $1,900.00 | $2,600.00 | |
| 63 | 78000200 | THPL PVT MK LINE 4 | 2,784 | FOOT | $0.9100 | $1.00 | $0.9000 | $1.84 | $1.15 | $1.11 | |
| 64 | 78000600 | THPL PVT MK LINE 12 | 199 | FOOT | $4.55 | $4.95 | $4.50 | $6.30 | $3.35 | $3.33 | |
| 65 | 78100100 | RAISED REFL PAVT MKR | 16 | EACH | $75.50 | $82.50 | $110.00 | $183.75 | $150.00 | $165.72 | |
| 66 | 78200011 | BARR WALL REF TYPE C | 98 | EACH | $7.55 | $20.00 | $9.00 | $6.30 | $10.00 | $10.00 | |
| 67 | 78300200 | RAISED REF PVT MK REM | 16 | EACH | $6.45 | $10.00 | $0.0100 | $31.50 | $15.00 | $25.00 |